Sub topic 11
Checking Scope Against Team and Time
This chapter assumes you have read the earlier chapters on the core loop and design pillars. You should be able to describe your game's core loop in a sentence and name three to five pillars. Here you will test whether the idea fits the team and timeline stated in your pitch.
Why scope belongs in a pitch
Scope is the amount of work a game needs, measured against the people and time available to do it. A producer or publisher reads the scope line to learn one thing: can this team plausibly finish this game?
An idea can be excellent and still be rejected for scope. A pitch that promises a 40-hour campaign from three people in nine months tells the reader the author has not thought about production. A pitch that fits its constraints tells the reader the author can ship.
Scope also connects to earlier chapters. The core loop tells you what must exist. The pillars tell you what you may cut. Scope checking uses both.
The working model: content, systems, and capacity
A scope check compares two quantities.
- Demand is the work the game needs. It comes from systems (rules the player interacts with) and content (the things those systems consume, such as levels, items, enemies, and art).
- Capacity is the work the team can deliver. It comes from team size, skills, and calendar time, minus time lost to meetings, bugs, polish, and illness.
Demand usually grows faster than people expect, for two reasons. First, content multiplies. Ten enemy types across five biomes is not ten pieces of work. It may be fifty, if each biome needs its own art, behavior, and balance. Second, every system needs testing, balancing, and tuning, which is invisible in the idea but large in the schedule.
Step 1: Separate the vertical slice from the full game
A vertical slice is a small section of the game that is fully playable and close to final quality. It shows the core loop working with real art, sound, and rules. A full game repeats and extends that slice.
Estimate in two parts:
- How long does it take to build the core loop at final quality?
- How many times must you repeat or vary it to reach the promised length?
In Lantern Keepers, the core loop is "assess the night, choose which lanterns stay lit, survive until dawn." The slice is one night with one village layout. The full game is some number of nights, village layouts, and threats.
Step 2: List the major cost drivers
Write down the items that cost the most. Typical drivers are:
- Custom 3D art or animation, which is slow and needs specialists.
- Online multiplayer, which adds networking, servers, security, and testing across many connections.
- Procedural generation, which reduces hand-made content but adds tools and debugging.
- Large amounts of narrative text or voice acting.
- Many platforms, each with its own certification and input rules.
- Systems that interact with each other, because each pair of interacting systems creates new edge cases.
You do not have to eliminate these. You have to know which ones your pitch depends on, and whether your team has the skills for them.
Step 3: Estimate with ranges and a buffer
Single-number estimates are almost always too optimistic. Use ranges and add a buffer.
Here is a small Python script that totals a task list using optimistic and pessimistic weeks, then compares the result against team capacity. It uses the three-point estimate (a weighted average of best case, likely case, and worst case), and it applies a buffer.
from dataclasses import dataclass
@dataclass
class Task:
name: str
best: float # person-weeks if everything goes well
likely: float # person-weeks, realistic
worst: float # person-weeks if problems appear
def expected(self) -> float:
# PERT weighted average: the likely case counts four times.
return (self.best + 4 * self.likely + self.worst) / 6
def check_scope(tasks, team_size, calendar_weeks, productive_ratio=0.6, buffer=0.25):
demand = sum(t.expected() for t in tasks)
demand_with_buffer = demand * (1 + buffer)
capacity = team_size * calendar_weeks * productive_ratio
return demand, demand_with_buffer, capacity
tasks = [
Task("Core loop prototype", 3, 5, 9),
Task("Lantern and light system", 4, 6, 10),
Task("Night threat AI", 3, 5, 8),
Task("Village layouts (6)", 6, 10, 16),
Task("Art pass", 12, 18, 28),
Task("UI and menus", 3, 4, 7),
Task("Audio", 2, 4, 6),
Task("Balancing and testing", 6, 10, 16),
]
demand, padded, capacity = check_scope(tasks, team_size=3, calendar_weeks=39)
print(f"Expected demand: {demand:.1f} person-weeks")
print(f"Demand with buffer: {padded:.1f} person-weeks")
print(f"Capacity: {capacity:.1f} person-weeks")
print("Fits" if padded <= capacity else "Over scope")For these numbers, expected demand is about 64 person-weeks and about 80 with the buffer. Capacity is 3 people × 39 weeks × 0.6, or about 70 person-weeks. The plan is over scope by about 10 person-weeks.
The productive_ratio is an assumption you should state. A value of 0.6 means that 60 percent of each week goes to building the game and the rest goes to meetings, tooling problems, and other overhead. Part-time teams or teams with day jobs should use a lower number.
Step 4: Find what to cut
When the check shows you are over scope, you have four levers.
| Lever | Example | Cost |
|---|---|---|
| Cut content | Ship four village layouts, not six | Shorter game, less variety |
| Cut a system | Remove the warmth mechanic | Loses depth, may break a pillar |
| Extend time | Plan twelve months, not nine | More funding or a longer wait |
| Add people | Hire an artist | Cost, onboarding, communication overhead |
Adding people late rarely helps as much as it seems to, because new members need time to learn the project and increase the number of people who must coordinate.
Use your pillars to choose cuts. A feature that does not support any pillar is the first to go. A feature that supports a pillar should be shrunk before it is removed. If you cut a feature that carries a pillar, the pillar is no longer true, and you should rewrite it or the game.
For Lantern Keepers, the pillar "Sessions fit in twenty minutes" suggests cutting the persistent map and the long campaign. The pillar "Every choice trades light for safety" suggests keeping the lantern system and cutting a side system such as crafting.
Step 5: Order the work so the game survives cuts
Build in an order that leaves a shippable game at every stage.
This is sometimes called a tiered scope plan: must-have, should-have, and nice-to-have. In the pitch you can state only the committed tier as the scope and mention the others as possible extensions. A publisher trusts a plan with a clear minimum.
Step 6: Write the scope line
The scope line in the pitch is one sentence that names the team, the time, the platform, and the size of the game. Compare these two lines.
Weak: "A big open game with lots of content, coming to all platforms."
Better: "Team of three, nine months, PC only. Six hand-built villages, each playable in about twenty minutes."
The better line has numbers that a reader can check. It also matches the pillars, since twenty-minute sessions are a pillar.
You can also record the scope check as data next to the pitch:
scope:
team: 3
calendar_months: 9
platform: "PC"
committed:
- "Core loop and lantern system"
- "Three village layouts"
stretch:
- "Three more layouts"
- "Crafting"
assumptions:
productive_ratio: 0.6
buffer: 0.25
risks:
- "Art pass has the widest estimate range"Common errors
- Estimating the idea, not the game. The idea has no cost. The game has art, tests, and polish. Estimate those explicitly.
- Forgetting the last 20 percent. Bug fixing, tuning, and store requirements often take as long as a third of the project. The buffer covers this.
- Assuming full-time, full-focus effort. Use a productive ratio below 1.
- Scoping to the best case. If every estimate is the optimistic number, the plan has no room for a single mistake.
- Hiding risk. Name the risky tasks. Readers respect a pitch that knows where it might fail.
- Copying a comparable's scope. A comparable title from a funded studio of fifty may be impossible for a team of three. Compare team size as well as design.
Edge cases
- Solo developers have no coordination overhead but no redundancy. Illness or a skill gap stops the project. Pick technology you already know.
- Reusing existing assets or engines reduces demand, but check licenses and the time needed to adapt them.
- Live service or early access games have no single end date. Scope the first release and state what ships at launch.
- Prototype pitches may ask for only a few months. Scope the pitch to the prototype and state what you will learn from it.
Exercise
A team of two has 30 weeks and a productive ratio of 0.5. Their task list has an expected demand of 40 person-weeks. With a 25 percent buffer, does the plan fit? Name one lever they could use if it does not.
Show answer
Capacity is 2 × 30 × 0.5 = 30 person-weeks. Demand with buffer is 40 × 1.25 = 50 person-weeks. The plan does not fit, since 50 is greater than 30. They could cut content, such as fewer levels, or cut a system that no pillar depends on. Extending the schedule would also work, but it needs about 50 weeks at the same ratio.
Exercise
A pitch says "Team of four, one year, all platforms, a 60-hour story campaign with voice acting, plus online co-op." Which cost drivers are in this line, and how would you rewrite the scope?
Show answer
The cost drivers are multiple platforms, a long narrative with voice acting, and online multiplayer. Together they exceed what four people can do in a year. A rewrite could be "Team of four, one year, PC only, a six-hour story campaign with text dialogue, local co-op." This removes the platform, voice, and networking costs and keeps a game that can be checked against the team.