Sub topic 7
Address risks and mitigations
This chapter assumes you can already describe a problem, a solution, a scope with deliverables, and a budget. You should also know how approvals work in your organization. Here you will add the risks section. It tells the decision maker what could go wrong, how likely that is, and what you will do about it.
Why a risks section helps approval
A risk is an uncertain event that, if it happens, changes your cost, timeline, or results. An issue is a problem that has already happened. A risks section covers risks only.
Many writers leave out risks because they fear a list of problems will make the proposal look weak. Experienced reviewers read it the other way. They know every project carries uncertainty. A proposal with no risks looks naive or dishonest, and the reviewer then has to guess what you missed.
A good risks section does three things:
- It shows you have thought about failure before it happens.
- It lets the approver judge exposure before committing money.
- It sets expectations, so a later problem is not a surprise.
Risks connect to the earlier chapters. Your scope plan and timeline are where most risks come from, such as a dependency on another team or a deadline tied to an outside event. Your budget is where most risks end up, as contingency money. Your value case assumptions are also risks, because each assumption might turn out wrong.
Identify risks from the reader's side
Start by listing risks, then cut the list to the ones your reader cares about. Four prompts help you find them.
- Walk the timeline. For each deliverable, ask what could delay it or make it cost more.
- List your dependencies. Include people, approvals, data, vendors, and systems you do not control.
- Review your assumptions. Every number in the budget and value case rests on something. Ask what happens if it is wrong.
- Ask the approver's questions. Think about what the decision maker will worry about, such as security, disruption to current work, staff capacity, or compliance.
Group the risks into categories so the reader can scan them.
| Category | Typical examples |
|---|---|
| Schedule | Key person unavailable, late delivery from a vendor, approvals that take longer than planned |
| Cost | Price increases, scope growth, underestimated effort |
| Technical or operational | Integration problems, poor data quality, disruption to daily work |
| People | Low adoption, resistance to change, loss of the project lead |
| External | Regulation changes, market shifts, supplier failure |
| Benefit | Savings or revenue arrive later or smaller than the value case claims |
Rate each risk
You do not need complex math. Rate each risk on two scales, likelihood (how probable it is) and impact (how much damage it does). Three levels are enough: low, medium, and high.
Use your reader's terms for impact. "High" should mean something concrete, for example "more than two weeks of delay" or "more than 10% over budget." Define those thresholds once, near the table, so the ratings are not arbitrary.
Combine the two ratings to get priority.
| Likelihood \ Impact | Low | Medium | High |
|---|---|---|---|
| **High** | Medium priority | High priority | High priority |
| **Medium** | Low priority | Medium priority | High priority |
| **Low** | Low priority | Low priority | Medium priority |
Spend your words on the high-priority risks. A low-likelihood, low-impact risk can be left out or covered in one line.
Choose a response for each risk
A mitigation is only one of several possible responses. Choose the response that fits the risk, then state it plainly.
- Avoid. Change the plan so the risk cannot occur. For example, drop a feature that depends on an unreliable data source.
- Reduce. Lower the likelihood or the impact. For example, run a two-week pilot before full rollout.
- Transfer. Move the risk to someone else. For example, use a fixed-price contract or buy insurance.
- Accept. Do nothing now because the cost of action exceeds the likely loss. Say you are accepting it and why.
Many risks also need a contingency, which is a backup plan or reserve used if the risk happens anyway. A common form is a budget reserve, such as 10% of the project cost, with a stated rule for who can release it. Name the trigger too. A trigger is an observable sign that the risk is occurring, such as "vendor has not delivered the test environment by week 3."
A strong mitigation is specific, has an owner, and has a date. Compare these two entries.
| Weak | Strong |
|---|---|
| "We will manage staffing risk carefully." | "A second analyst, Priya Nair, will be trained in weeks 1 to 4 so that one absence does not stop the work. Owner: project manager." |
| "Vendor delays are possible." | "The contract includes a 5% penalty per week of delay after week 6. If the test environment is not ready by week 3, we escalate to the vendor's account director." |
Write the risks section
A table is the usual format because readers can scan it and compare rows. Include these columns: the risk, its likelihood, its impact, the mitigation, and the owner. For long proposals, add the trigger.
Here is a sample for a proposal to replace a customer support ticketing system.
| Risk | Likelihood | Impact | Mitigation | Owner |
|---|---|---|---|---|
| Data migration from the old system loses or corrupts tickets | Medium | High | Run two test migrations with sample data and compare record counts. Keep the old system read-only for 60 days after launch. | IT lead |
| Support agents do not adopt the new tool | Medium | Medium | Include two agents in the design review. Run a half-day training before launch and track weekly active use for the first 8 weeks. | Support manager |
| Vendor misses the integration date | Low | High | Contract penalty clause. Escalation to the vendor account director if the test environment is not ready by week 3. | Project manager |
| Licence prices rise at renewal | Medium | Low | Negotiate a three-year price cap in the contract. | Procurement |
After the table, add a short paragraph on the two or three risks that matter most. Explain them in plain sentences, because a table cell has little room for reasoning. Also state the contingency: "The budget includes a 10% reserve of $18,000. The steering group must approve any release."
Be honest about residual risk, the risk that remains after the mitigation. If the migration risk is still medium after your tests, say so. Approvers trust a proposal that admits what it cannot fully remove.
Show how risks feed the rest of the proposal
The risks section should agree with the other sections. Check these links:
- Each contingency amount in the risks section appears in the budget.
- Each mitigation task that takes time or money appears in the scope and timeline. If you promise a two-week pilot, it must be on the schedule.
- The value case states which benefits are uncertain, and the risks section explains how you will protect them.
- The executive summary mentions the one or two top risks and the plan for them, in a sentence.
Common errors
- Listing only generic risks. "Delays" and "budget overruns" apply to every project. Name the specific cause in your project.
- Mitigations that are only intentions. "We will monitor closely" is not a mitigation. Say who monitors what, how often, and what happens next.
- No owner. A risk without an owner is not managed.
- Hiding the biggest risk. If the main risk is that the project depends on one executive's support, say so. The approver is likely to see it anyway.
- Treating risk as a reason to delay. The section should show a path forward. Present risks as manageable conditions, not as reasons to refuse.
- Forgetting the risk of not acting. Sometimes the largest risk is doing nothing. Your problem statement describes it, so refer back to it in one sentence.
- Inconsistent numbers. A reserve in the risks section that does not match the budget undermines trust in both.
A short checklist
Before you move on, check that your risks section:
- Names specific risks drawn from your own timeline, dependencies, and assumptions.
- Rates each risk with defined thresholds.
- Gives each high-priority risk a response, an owner, and a date or trigger.
- States the contingency and who can release it.
- Admits residual risk.
- Matches the budget, timeline, and value case.
Exercise
A proposal says: "Risk: the project may be late. Mitigation: we will work hard to keep to the schedule." Name two problems with this entry and rewrite it so that it is specific. Assume the real cause is that the test data comes from another team, and you have 10 working days of slack in the plan.
Show answer
Problems: the risk is generic (it names no cause), and the mitigation is an intention with no owner, action, trigger, or date. A better version: "Risk: the data team may not deliver the test data by week 2 (likelihood medium, impact high, because the testing phase cannot start without it). Mitigation: the project manager agrees a delivery date with the data team lead in week 1 and checks progress weekly. If the data is not delivered by the end of week 2, we escalate to the sponsor and use up to 10 working days of schedule slack. Owner: project manager."
Exercise
Your proposal's value case assumes 80% of staff will use the new tool within three months. Which risk category does this belong to, and what is one mitigation you could write?
Show answer
It is a benefit risk (also a people or adoption risk), because the savings depend on the adoption assumption. One mitigation: involve a few staff members in design, run training before launch, and track weekly active use. If use is below 60% by month 2, the sponsor runs a review and the team adds follow-up coaching. State the owner, such as the department manager.