Sub topic 7
Working with engineering on how and when
This chapter assumes you have worked on or alongside a product team and know the basic software development lifecycle. It also assumes you have read the earlier chapters on decision rights and on writing briefs. Here the focus is the working relationship with engineers: how they decide how to build something, and how you take part in decisions about when it ships.
The division of labor: what and why versus how and when
The PM owns the problem, the goal, and the priority. Engineering owns the technical approach and the effort it takes to deliver. The timeline sits where the two meet, so neither side can set it alone.
A common error is to treat "when" as a PM decision. If you pick a date and hand it to the team, you have made an estimate on their behalf. The opposite error is to treat "how" as none of your business. You do not choose the architecture, but you do need to understand it well enough to know what it costs and what it makes harder later.
| Question | Primary owner | Your role as PM |
|---|---|---|
| What problem are we solving, and for whom? | PM | Decide and explain |
| How much is the outcome worth? | PM | Provide evidence and a value case |
| How should we build it? | Engineering | Ask about options and trade-offs |
| How long will it take? | Engineering | Ask for a range, then discuss scope |
| Which scope fits the date? | Shared | Negotiate with engineering |
| Is the quality good enough to ship? | Shared | Hold the acceptance criteria, listen to risk |
Prepare the ground before engineers see the work
Engineers give better answers when they receive the problem early and in a usable form. Three habits make the biggest difference.
- Bring engineers into discovery. Invite a tech lead to a few customer calls or to the review of the data. They often spot a cheaper way to solve the problem, or a hidden constraint, before anything is designed.
- Share the problem, not a ready-made solution. A brief that says "add a dropdown here" leaves no room for a better idea. A brief that says "returning users abandon checkout because they must retype their address" lets the team pick the approach.
- Make the goal measurable. Engineers make many small decisions while building. A clear success measure lets them make those decisions without asking you each time.
If you only meet engineers after the design is finished, the first useful conversation is also the most expensive one, because any change now means rework.
Refinement: turning a brief into buildable work
Refinement (sometimes called grooming) is a recurring session where the team reads upcoming work, asks questions, and splits it into pieces small enough to build. It is the main place where "how" gets discussed with you in the room.
A useful refinement session for one item follows this order:
- State the problem and the intended outcome in two or three sentences.
- Walk through the acceptance criteria. These are the conditions that must be true for the item to count as done.
- Let engineers ask questions. Record every open question, even if you cannot answer it now.
- Identify risks and unknowns. Anything the team cannot estimate with confidence needs a spike.
- Split the item until each piece can be finished within a sprint, or within whatever cycle your team uses.
A spike is a short, time-boxed investigation that produces knowledge instead of shippable features. For example, "Spend two days finding out whether the payment provider supports saved cards in our region." You agree on the question and the time limit up front, and the result is an answer, not working code.
Technical trade-offs you should be able to discuss
You do not need to write code. You do need to follow the conversation when engineers bring up trade-offs. Common ones include:
- Speed now versus cost later. A quick implementation may add technical debt, which means shortcuts that make later changes slower or riskier. Debt is not always bad. Taking it on knowingly for a deadline that matters can be a sound choice, provided the team plans to pay it back.
- Build versus buy. Using a third-party service is usually faster at first but adds cost, vendor dependence, and limits on customization.
- Reuse versus fit. Extending an existing component is cheaper but may bend it into a shape it was not designed for.
- Scope versus quality. Cutting tests or review to hit a date moves risk onto customers and support.
- Reliability and performance. Some work does not show up as a feature, yet its absence causes outages and slow pages.
When an engineer raises one of these, ask three questions: what are the options, what does each one cost now and later, and what would make you change your recommendation. These questions work because they ask for reasoning instead of challenging the person.
Non-functional requirements and technical work
Features are not the only work. Security, performance, accessibility, monitoring, and maintenance all take capacity. If you only count visible features, the team will either miss the date or quietly skip this work.
Two practical approaches help:
- Write non-functional needs into the brief. For example: "The page must load in under two seconds on a mid-range phone." Engineers cannot meet a target nobody stated.
- Reserve capacity for technical work. Many teams set aside a fixed share of each cycle for debt, tooling, and upgrades. Agree on the share with the tech lead, and defend it when feature pressure rises.
Asking about estimates without turning them into promises
An estimate is a forecast under uncertainty. It becomes a commitment only when someone chooses to commit to it. Most conflicts over dates come from mixing the two.
Habits that keep estimates honest:
- Ask for a range ("two to four weeks") and ask what drives the spread.
- Ask what would make it take longer. The answer is your risk list.
- Do not ask for estimates in a meeting where the person feels pressure to give a smaller number.
- Do not turn a rough estimate into a date you announce to others.
- Revisit the estimate when you learn something new, and say so openly.
Pressure on an estimate rarely makes the work faster. It makes the number smaller, and the gap shows up later as missed dates or cut corners.
Planning and tracking the date
In planning, the team chooses how much work to take on for the next cycle, based on its past pace. Your part is to bring a clear priority order and to explain what matters most if capacity runs short. Engineers decide how much fits.
For tracking, prefer signals that show risk early over reports that show activity:
- Is the riskiest piece being built first?
- Are open questions being answered, or piling up?
- Is scope growing without anything being removed?
- Do items stay "in progress" for longer than usual?
If a date is at risk, say so as soon as you know, then bring options. The stakeholder update template from the topic plan applies here too: state what changed, the impact, the options, your recommendation, and when you need a decision.
Working during delivery
Once building starts, your job moves to being available and decisive.
- Answer questions the same day when you can. A blocked engineer waiting for a decision is a hidden delay.
- Make small decisions quickly and record them. Use the decision log in the brief so the reasoning is not lost.
- Check the work early. Look at partial builds, not only the finished result. It is much cheaper to correct a misunderstanding in week one than at the demo.
- Protect the team from churn. Route new requests through you. Do not let stakeholders ask engineers directly for changes in the middle of a cycle.
- Accept that some questions have no perfect answer. Pick the option that is easy to reverse and move on.
Common errors
| Error | What it looks like | What to do instead |
|---|---|---|
| Prescribing the solution | Brief lists screens and fields, with no problem stated | Describe the problem and the success measure |
| Date first, scope second | "We launch on the 18th, make it fit" | Share the constraint, then negotiate scope together |
| Treating estimates as promises | Quoting a best-case number to stakeholders | Share ranges and the assumptions behind them |
| Ignoring technical work | Every cycle is all features | Agree a standing share for debt and maintenance |
| Late involvement | Engineers first see the work after design is signed off | Include a tech lead in discovery |
| Hiding bad news | Date slips are mentioned only at the deadline | Raise risks as soon as you see them |
| Overriding on technical choices | PM chooses a framework or architecture | Ask for options and trade-offs, then respect the call |
A worked example
Suppose your goal is to cut checkout abandonment among returning customers. Your brief names the problem: returning users retype their address on every order. Success means fewer abandoned checkouts among returning users.
In refinement, the tech lead says there are two options. Option A stores addresses on the customer profile, which takes about three weeks. Option B reuses the address from the last order, which takes about one week but only works for customers with a past order. She also notes that the address service has no tests, so changes there are risky.
You ask what drives the range on Option A. She says the unknown is whether existing records have inconsistent formats. You agree on a two-day spike to sample the data. The spike shows the formats are mostly clean, and Option A is estimated at three to four weeks.
The launch date is in three weeks. Rather than ask the team to compress, you propose shipping Option B first, with Option A as the follow-up. You also agree to reserve a few days to add tests to the address service. You then tell the VP of Sales what ships on the date, what follows, and why. Nobody had to pretend an estimate was smaller than it was.
Exercise
A stakeholder asks you to commit to a March 4 launch. The tech lead's estimate for the full scope is three to five weeks, and March 4 is three weeks away. List two things you should do before answering, and one option you could offer the stakeholder.
Show answer
Before answering: (1) ask the tech lead what drives the range and what the main risks are, and (2) check whether any scope could be split out or deferred without losing the main goal. You could offer a reduced-scope launch on March 4 with the remaining items following later, or the full scope on a later date, and recommend one with your reasoning. You should not announce March 4 for the full scope, because the estimate is a range that may exceed three weeks.
Exercise
An engineer says a feature will take longer because the team needs to upgrade an outdated library first. What three questions can you ask to understand the trade-off, and why is it a mistake to simply tell the engineer to skip the upgrade?
Show answer
Ask: what are the options, what does each cost now and later, and what would change your recommendation. Telling the engineer to skip the upgrade overrides a technical decision you may not fully understand, and it may add risk or debt that slows later work or causes failures. It also teaches the team to hide technical needs. A better approach is to weigh the cost of the upgrade against the value of the date and decide together, possibly splitting the upgrade into its own planned work.