This chapter assumes you know DMAIC, can read a SIPOC map, and can calculate a proportion. The project Y is the single metric your project will try to improve. It comes from the measurable requirements at the bottom of the CTQ tree.
Choosing the project Y
Pick the requirement that matters most to the customer, that your team can measure now, and that your process can influence. Prefer a proportion such as "% of orders delivered within 3 days" over an average, because a proportion maps directly to defects.
Baselining the metric and setting a target
Measure the metric over a stable period, long enough to include normal variation. The result is your baseline. Set the target from the customer requirement and from what the process can realistically reach, not from a wish.
Small samples mislead. Four sampled orders with 2 misses give a 50% baseline, but that figure may shift widely with more data.
Validating the tree with customers and data
Test each branch of the tree before it becomes a charter commitment.
| Check | Question to ask | Evidence |
|---|---|---|
| Customer | Does this driver match what customers said? | Interview or survey notes |
| Measurable | Can we count defects from existing records? | Sample of real records |
| Controllable | Can our process change this result? | Process map review |
> Note: this must be a callout, not a blockquote. See the callout below.
Carrying the metric into the project charter
Record the project Y, its operational definition, its baseline, its target, and the customer requirement it serves. Link the goal statement to that metric so the sponsor can trace the project back to the customer.
Common pitfalls and how to spot them
- A metric nobody measures. If no record exists, the baseline is an estimate.
- A target copied from another project. Compare it with your own baseline and process capability.
- A driver with no requirement. If you cannot write a number for it, the branch is not ready.
- A metric that rewards the wrong behavior. Check whether the team could hit the target by lowering quality elsewhere.
Exercise
A team measured 2 defects in 4 orders and wants a 5% defect target. Can the team set that target from this sample? Explain.
Show answer
No. Four orders give too little data to estimate the true defect rate. Collect more orders over a stable period, then compare the baseline with the 5% target.