Sub topic 12
Review the week and calibrate estimates
This chapter assumes you already keep a task list, estimate durations, and place blocks on a calendar with recurring events. Here you close the loop. A weekly review compares what you planned with what happened, and it turns the difference into better estimates for next week.
What the review is for
A plan is a guess. Without a check, the same guess repeats every week and the same errors repeat with it. A 20-minute review once a week gives you your own data on three questions:
- Which tasks took longer or shorter than estimated?
- Which blocks were moved, shortened, or skipped?
- Which parts of the week held up, and which kept breaking?
Record the data during the week
Reviewing from memory is unreliable, because people remember the dramatic overruns and forget the small ones. Keep the record cheap. At the end of each block, edit the calendar event and add one line to the description: the actual time spent and a one-word status.
- done: finished within the block.
- over: needed more time than planned.
- moved: rescheduled to another slot.
- dropped: not done this week.
Run the review in four steps
- Scan the week. Open last week in your calendar and count blocks by status.
- Compute the ratio. For each task type, divide actual time by estimated time. A ratio of 1.5 means the work took 50% longer than planned.
- Find the cause. Decide whether each miss came from a bad estimate, an interruption, or a block in the wrong place. Only the first cause calls for changing your estimates.
- Change one or two things. Adjust the estimates and the template, then stop.
The script below computes the ratios from a small log. It runs as shown.
from collections import defaultdict
# (task type, estimated minutes, actual minutes)
log = [
("writing", 60, 90),
("writing", 90, 120),
("email", 30, 25),
("email", 30, 35),
("reports", 45, 80),
]
totals = defaultdict(lambda: [0, 0])
for kind, estimated, actual in log:
totals[kind][0] += estimated
totals[kind][1] += actual
for kind, (estimated, actual) in sorted(totals.items()):
ratio = actual / estimated
print(f"{kind}: ratio {ratio:.2f}")
# email: ratio 0.92
# reports: ratio 1.78
# writing: ratio 1.40Apply the ratios
Multiply future estimates for a task type by its ratio, then round up to a block size you use, such as 15 or 30 minutes. If writing runs at 1.40, a 60-minute estimate becomes 84 minutes, so book 90. Email at 0.92 needs no change. Reports at 1.78 suggest a larger problem, such as unclear scope or missing inputs. Fix the cause before you simply pad the estimate.
Common errors
- Too little data. Two tasks of one type tell you little. Wait for four or five before you trust a ratio.
- Changing everything at once. If you edit ten things, you cannot tell which change helped.
- Blaming yourself for external causes. A block lost to an unplanned meeting is a protection problem, not an estimation problem. Handle it with the practices from the chapters on protecting blocks and handling disruptions.
- Skipping the review in a bad week. A bad week holds the most useful data.
Exercise
Last week you estimated 4 tasks of type "planning" at 30 minutes each, and they took 40, 50, 35, and 45 minutes. What is the ratio, and what estimate should you use for a new planning task that you now guess at 30 minutes?
Show answer
Estimated total is 120 minutes and actual total is 170 minutes, so the ratio is 170 / 120 ≈ 1.42. A new 30-minute guess becomes about 43 minutes, so book a 45-minute block.