Review the week and calibrate estimates
This chapter assumes you already keep a calendar with typed blocks (deep work, shallow work, meetings, personal), that you estimate tasks before placing them, and that your week has buffers. A weekly review turns your calendar from a plan into a source of evidence. Without it, your estimates stay guesses and the same mistakes repeat every Monday.
What the weekly review is for
A weekly review compares what you planned with what happened, then changes next week's plan based on the difference. It answers three questions:
- Which estimates were wrong, and by how much?
- Which disruptions were predictable enough to plan for?
- Does the ideal-week template still match your real energy and commitments?
Keep it short. Twenty minutes at the end of the week is enough. A review that takes an hour tends to get skipped.
Gather the data
You need three facts for each block you planned:
- Planned duration in minutes.
- Actual duration in minutes, meaning how long the work really took, not how long the block lasted.
- Outcome: done, partly done, moved, or dropped.
If you edit blocks as the day changes, as the previous chapter describes, your calendar already holds most of this. Resize a block when it runs over. Leave a moved block visible by adding "(moved)" to its title, so you can count it later. Record the cause of any large gap in a few words, such as "unclear spec" or "interrupted by support request".
Here is a sample log from one week.
| Block | Type | Planned (min) | Actual (min) | Ratio | Cause of gap |
|---|---|---|---|---|---|
| Draft report section | deep | 60 | 90 | 1.50 | More research than expected |
| Draft report section | deep | 45 | 70 | 1.56 | Restarted after a rewrite |
| Draft report section | deep | 90 | 120 | 1.33 | Interrupted twice |
| Clear inbox | shallow | 30 | 25 | 0.83 | Few messages |
| Clear inbox | shallow | 30 | 35 | 1.17 | One long thread |
| Clear inbox | shallow | 20 | 20 | 1.00 | None |
The ratio is actual divided by planned. A ratio of 1.5 means the task took 50% longer than planned. A ratio below 1 means you overestimated.
Compute a calibration ratio
One bad estimate tells you little. Look at ratios per task category, because writing, email, and meetings overrun in different ways. Use the median instead of the average. A single disaster task can pull an average far from your typical result, but it barely moves a median.
The script below groups a log by category, prints the median ratio, and shows how to apply it to a new estimate. It rounds up to the next 15 minutes, which matches common calendar grids.
import math
from collections import defaultdict
from statistics import median
log = [
("writing", 60, 90),
("writing", 45, 70),
("writing", 90, 120),
("email", 30, 25),
("email", 30, 35),
("email", 20, 20),
]
def median_ratios(entries):
groups = defaultdict(list)
for category, planned, actual in entries:
groups[category].append(actual / planned)
return {category: median(values) for category, values in groups.items()}
def calibrated(planned_minutes, ratio, grid=15):
return math.ceil(planned_minutes * ratio / grid) * grid
ratios = median_ratios(log)
for category in sorted(ratios):
print(category, round(ratios[category], 2))
print("New writing task, gut estimate 60 min ->", calibrated(60, ratios["writing"]), "min")
# email 1.0
# writing 1.5
# New writing task, gut estimate 60 min -> 90 minYou can do the same in a spreadsheet with one row per block and a MEDIAN formula per category. The tool does not matter. What matters is that you compute a number and then use it.
Read the patterns, not the single misses
Different gaps need different fixes. Sort each large gap into one of these causes before you change anything.
| Pattern | What it looks like | Fix |
|---|---|---|
| Consistent underestimate | Same category runs 30–60% over every week | Multiply estimates by the category ratio |
| Scope drift | Task grew because requirements changed | Split the task, or estimate after clarifying scope |
| Interruptions | Blocks run over because of other people | Add buffers or schedule a sanctioned interruption window |
| Bad placement | Deep work overruns only in the afternoon | Move it to your high-energy window |
| Overcommitment | Many blocks dropped at the end of the week | Plan fewer blocks, not shorter ones |
| Overestimate | Ratio below 0.8 | Reduce the block and give the time to something else |
The common error here is treating every overrun as an estimation problem. If a task took 90 minutes of work in a 60-minute block but you also lost 30 minutes to interruptions, your estimate was right and your protection failed. Fixing the estimate would hide the real cause.
Review blocks by type and by energy
Estimate accuracy is only one view. Also count blocks by type:
- Deep work: how many hours did you plan, and how many did you complete? Many people plan 20 hours and finish 8. Plan your template around the number you actually finish.
- Shallow work: did it spread into deep-work time? If so, your shallow blocks are too short or too few.
- Meetings: compare the meetings you accepted with the ones you wanted. A pattern of unplanned meetings inside protected blocks points to a weakness in how you protect them, not to your estimates.
- Personal: check whether it was the first thing dropped. If so, treat it as a fixed commitment in the template.
Then look at energy. Mark the blocks where you felt sharp and the ones where you struggled. If your best work keeps coming at 14:00 but your template puts deep work at 09:00, change the template. The data beats your assumption about your own rhythm.
Make small, specific changes
Change a few things per week at most. If you change everything, you cannot tell which change helped. Use these three levers in this order:
- Estimates: apply the category ratio to new tasks.
- Buffers: lengthen or move them if the same kind of disruption appeared three times.
- Template: change the ideal week only after a pattern holds for about three weeks.
A single odd week, such as a holiday, a launch, or an illness, should not reshape your template. Tag it as an exception and exclude it from your ratios.
A 20-minute review routine
Run the review at the same time each week, such as Friday afternoon, and put it on the calendar as a block.
- Spend five minutes marking each block done, partly done, moved, or dropped.
- Spend five minutes on actual durations. Fill gaps from memory, but note when you are unsure.
- Spend five minutes computing ratios and listing the top two causes of gaps.
- Spend five minutes choosing no more than three changes. Write them at the top of next week's plan.
Edge cases and limits
- Small samples: with fewer than five data points in a category, treat the ratio as a hint. Round toward a simple multiplier such as 1.25 or 1.5.
- Mixed-size tasks: a ratio from 15-minute tasks may not apply to 3-hour tasks. Long tasks tend to overrun by a larger proportion. Keep separate ratios for short and long tasks if you have enough data.
- Skewed logs: if you only record blocks that went wrong, your ratios will look worse than reality. Log all of them.
- Time spent logging: if recording takes more than a minute or two a day, simplify. Resizing calendar blocks is usually cheaper than a separate time tracker.
- Meetings: you rarely control their length, so measure them differently. Track how often they overran, and add transition time after those meetings instead of changing their estimates.
- Gaming the numbers: if you shorten blocks just to hit a ratio of 1.0, you are measuring your edits and not your work. Plan first, record honestly after.
Exercise
Exercise
Over three weeks your "report writing" blocks have median ratio 1.4. You plan a new report section with a gut estimate of 100 minutes, using a 15-minute grid. Separately, two of last week's overruns were caused by colleagues interrupting you. How long should the new block be, and what should you change about the interruptions?
Show answer
Multiply 100 by 1.4 to get 140 minutes, then round up to the next 15 minutes: 150 minutes. The interruption overruns are not estimation errors, so do not put them into the ratio. Change the protection instead, for example with a "busy" status, a "focus" label that others can see, or a set interruption window, and adjust buffers if the interruptions are unavoidable.