Workers who join or leave midway
Split the job into phases. Find the work done in each phase, then add the phases. Take A alone at 10 days (3 units per day) and B alone at 15 days (2 units per day), with 30 units of total work. A works alone for 2 days, then B joins.
- Work in phase 1: 2 × 3 = 6 units
- Remaining work: 30 − 6 = 24 units
- Combined rate: 3 + 2 = 5 units per day
- Time for phase 2: 24 ÷ 5 = 4.8 days
- Total time: 2 + 4.8 = 6.8 days
total = 30
rate_a = 3
rate_b = 2
done_a = 2 * rate_a # A works alone for 2 days
days_together = (total - done_a) / (rate_a + rate_b)
print(2 + days_together) # 6.8Alternating and cyclic schedules
When workers take turns, add one full cycle at a time. In a cycle of A then B, the work is 3 + 2 = 5 units. Six full cycles give 30 units in 12 days, because each cycle takes two days.
Sharing wages by work done
Divide pay in the ratio of work done, not time worked. A did 3 units and B did 2 units, so the 500 wage splits into 300 for A and 200 for B.
Men, days and hours
The relation is M1 × D1 × H1 / W1 = M2 × D2 × H2 / W2, where M is workers, D is days, H is hours per day, and W is work. Four men finish a job in 6 days, so the total is 4 × 6 = 24 man-days. Five days need 24 ÷ 5 = 4.8, so each day needs 3 men when the hours stay the same.
Pipes and cisterns: inlets and outlets as rates
Treat an inlet as a positive rate and an outlet as a negative rate. An inlet that fills a tank in 6 hours has rate 1/6 per hour. An outlet that empties it in 12 hours has rate −1/12. The net rate is 1/6 − 1/12 = 1/12, so the tank fills in 12 hours.
flowchart LR
I["Inlet: +1/6 per hour"] --> T["Tank"]
O["Outlet: -1/12 per hour"] --> Tcaption: Inlet and outlet pipes both feed one tank, and their rates add with signs. alt: Two arrows point into a tank. The inlet arrow is labelled plus one sixth per hour, and the outlet arrow is labelled minus one twelfth per hour.
Exercise
Four men finish a job in 6 days. How many men finish the same job in 8 days?
Show answer
Total work is 4 × 6 = 24 man-days. Dividing by 8 days gives 3 men.