Sub topic 1
Why a single number is not enough
Prerequisites
This chapter assumes you know what a task, a duration, a dependency, and a critical path are in a project schedule. You should also be comfortable with averages and basic arithmetic.
Why a single point estimate hides risk
A single duration estimate, such as "this task takes 6 days," hides how much the real duration might vary. Tasks rarely finish exactly on time. A task that usually takes 6 days might finish in 4 when things go well, or take 14 when a key person is sick or a dependency slips.
Two tasks can share the same single estimate of 6 days and still carry very different risk. One may be well understood. The other may depend on an unknown vendor. A single number cannot show that difference.
Three-point estimates solve this by asking for a range instead of one value.
The three inputs
A three-point estimate uses three values for each task:
- Optimistic (O): the shortest duration if almost everything goes right.
- Most likely (M): the duration you expect under normal conditions.
- Pessimistic (P): the longest duration if most things go wrong, but not a disaster.
For example, a data migration task might have O = 4 days, M = 6 days, and P = 14 days. The range tells you that the task is uncertain and that the risk leans toward delay.
When eliciting these values, check that O ≤ M ≤ P. If the values violate this order, revisit the estimate before using it.
The triangular estimate
The simplest way to combine the three inputs is to take their simple average. This is called the triangular estimate because the three values form the corners of a triangular probability shape:
def triangular_estimate(o, m, p):
return (o + m + p) / 3
print(triangular_estimate(4, 6, 14)) # 8.0The result is 8.0 days. This is higher than the most likely value of 6 because the pessimistic value of 14 pulls the average upward. The triangular estimate treats all three values as equally important, which is its main weakness. The later PERT method gives the most likely value more weight.
Exercise
A task has O = 3, M = 5, and P = 11 days. What is its triangular estimate?
Show answer
(3 + 5 + 11) / 3 = 19 / 3, which is about 6.33 days.