Sub topic 6
IMG projects, scoping and project views
This chapter covers how to turn the full Reference IMG into a manageable work list. It assumes you can navigate SPRO, know that IMG activities change Customizing tables, and understand the difference between clients and between Customizing and Workbench objects.
Why the full IMG is too big to work with
The SAP Reference IMG contains thousands of activities for every application component SAP delivers. A project that implements Financial Accounting and Sales will touch a small share of them. Without a filter, consultants scroll through irrelevant nodes, miss required steps, and have no shared list of what is done.
An IMG project is the filter. It is a named selection of IMG activities, together with optional status and planning data. It does not copy any configuration, and it does not change what an activity does. It only controls which activities you see and how you track them.
What an IMG project contains
An IMG project is created in SPRO with the button SAP Reference IMG for browsing, or through Project Administration for managing projects. A project consists of:
- A name and description.
- A scope: the application components, countries or activities you selected from the Reference IMG.
- Optional project views, which are filtered subsets of the project.
- Optional planning data per activity, such as status, priority, responsible person, planned dates and notes.
Important points about how projects relate to the Reference IMG:
- The Reference IMG stays unchanged. The project only references its activities.
- Several projects can exist side by side in one system, with overlapping scope.
- Projects are stored as Customizing-related project data in the system. Moving them between systems is a separate step from moving the configuration itself.
Creating a project
The usual sequence in SPRO is:
- Choose SPRO - Customizing: Execute Project and open SAP Reference IMG.
- Choose Project Administration (or Edit Project) and select Create.
- Enter a project ID and a description.
- On the scope tab, choose Scope (often shown as Determine Scope) and select the application components, such as Financial Accounting or Sales and Distribution, that the project covers.
- Generate the project IMG. The system builds the list of activities that belong to the selected scope.
- Save and then open the project from SPRO to work with it.
Exact button names vary a little by release. The pattern stays the same: define the project, select scope, generate.
Scoping: selecting what belongs in the project
Scoping decides which activities appear. You can scope by:
- Application component, for example Sales and Distribution or Materials Management.
- Country, so that country-specific activities for countries you do not operate in are hidden.
- Individual activities, when you need one step from an otherwise out-of-scope area.
Scoping errors are the main source of confusion with projects:
| Symptom | Likely cause |
|---|---|
| An activity you need is missing from the project IMG | The component or country was not selected in scope, or the project IMG was not regenerated after the scope changed |
| Many irrelevant activities appear | Scope was set at too high a level, such as a whole application area |
| Two consultants see different activities | They opened different projects or different project views |
After you change scope, regenerate the project IMG. Until then, the displayed structure reflects the old selection.
Project views
A project view is a filtered subset of an IMG project. Use views to give each team or phase a smaller list than the whole project. Typical filter criteria include:
- Mandatory and critical activities only.
- Activities with a given status, such as not started or in process.
- Activities assigned to a given person or team.
- Activities of a given priority.
A view changes only what is displayed. The same activity can appear in several views, and the same underlying Customizing table is changed whichever view you used to reach it.
Status and planning data
Each activity in a project can carry planning data. Common fields are:
- Status, such as not processed, in process or completed.
- Responsible person.
- Planned start and end dates.
- Notes or attached documents.
A project lead can then create a view for activities that are in process or overdue and use it as a progress report. This data is project metadata. It tells you who thinks an activity is done. It does not prove that the configuration exists in the target system.
Projects and clients
IMG projects are not a way to isolate configuration between clients. Two points to keep straight:
- The Customizing you perform from a project still lands in the client you are logged on to, subject to the client settings in SCC4.
- The activity list in the project is the same in every client of the system where the project is visible, because it is derived from the Reference IMG.
If you work in a development client and your colleague in a test client of the same system, the activities you each run change separate sets of client-dependent data. The project does not reconcile them.
How a project relates to transport requests
The project and the request are independent mechanisms.
When you run an activity from a project view and save, the system asks for a Customizing request if the client allows recording. The request is the same one you would get when running the activity from the plain Reference IMG. Consequences:
- A request can contain changes made through several different projects.
- You can choose to keep one request per project phase by agreeing on naming and by selecting the right request when prompted, but the system does not enforce it.
- Releasing a request does not update project status.
Practical use of projects in a team
A workable pattern for a team of consultants:
- Create one project per implementation scope, for example a rollout to a new country.
- Define views per functional team, such as Finance, Logistics and Basis-related settings.
- Agree that each consultant sets status when finishing an activity.
- Create separate Customizing requests per team or topic, and give each a description that names the project and the area.
- Review views regularly, then verify the actual configuration in the target system before go-live.
Common errors
- Project IMG not regenerated. After a scope change, new activities do not appear. Regenerate the project IMG.
- Wrong project opened. Consultants work from the Reference IMG in one session and from a project in another, then compare lists that differ. Standardize the entry point.
- Assuming a project is transported. Project definitions and status do not travel with the Customizing request unless you transport them on purpose.
- Treating views as authorization. A view hides activities from the list but does not stop a user with access from calling the activity directly by transaction or view name.
- Status drift. Status set by hand ages quickly. Agree who owns it and when it is reviewed.
Reading the result in tables
An IMG project itself is only metadata, but the activities in it write to ordinary Customizing tables. The following report lists the company codes that the Enterprise Structure activities in the project would have produced in the current client. It is a quick check that configuration actually exists, independent of project status.
REPORT zdemo_company_codes.
SELECT bukrs, butxt, ort01, waers
FROM t001
ORDER BY bukrs
INTO TABLE @DATA(company_codes).
LOOP AT company_codes INTO DATA(cc).
WRITE: / cc-bukrs, cc-butxt, cc-ort01, cc-waers.
ENDLOOP.Open SQL returns only rows for the current logon client without a client condition, so run the report in each client you want to compare. A project that shows "completed" for the company code activity while this list is empty indicates status drift or a missing transport.
Summary
- An IMG project filters the Reference IMG by scope. It does not hold configuration.
- Scope is set by component, country or single activity, and the project IMG must be regenerated after a change.
- Project views narrow the list by status, priority, person or criticality, and affect display only.
- Status and planning data are manual project metadata and do not prove that a setting exists or was transported.
- Customizing requests are created by saving changes in the activity, not by working with the project.
Exercise
A consultant marks the activity "Define company code" as completed in the project, but the production client has no company code after the latest import. Give two reasons the project status and the production data can disagree, and one way to check the real state.
Show answer
Status is a manual flag, so it can be set without the change being saved or recorded in a request. The request containing the change may also not have been released or imported into production, or it was imported into a different client. To check the real state, read table T001 in the production client, for example with the report shown in this chapter or by viewing the table, or compare the system with the development system.
Exercise
You change the scope of a project to add the country-specific activities for a new country, but the activities do not appear in your view. What step is probably missing, and why would creating a new view not help?
Show answer
The project IMG was not regenerated after the scope change. A view is only a filter on the project IMG, so it cannot show activities that are not yet part of the generated project.