Sub topic 11
Production Planning and Manufacturing
This chapter covers how Production Planning (PP) turns demand into production orders and how those orders connect to Inventory and Finance. It assumes you know the organizational structure (plant, company code), material master data, and the Procurement and Inventory chapters.
What PP is responsible for
PP plans and executes in-house production. It answers three questions: what to make, in what quantity, and by when. It consumes components from stock and delivers finished goods back into stock. Because every step moves stock or costs money, PP depends on Inventory and Finance.
PP works at plant level. A material must be extended to a plant, with MRP and work scheduling views, before it can be planned or produced there.
Master data that drives production
| Object | Purpose |
|---|---|
| Material master (MRP views) | Defines procurement type (in-house or external), lot size, and planning parameters |
| Bill of material (BOM) | Lists the components and quantities needed for one unit of a product |
| Work center | A machine or labor resource with capacity and cost rates |
| Routing | The ordered operations performed at work centers |
The BOM says what goes in. The routing says how and where it is made. Work center cost rates link both to Controlling.
The plan-to-produce flow
- Demand arrives from sales orders or a forecast.
- Material Requirements Planning (MRP) compares demand with stock and open supply. It creates planned orders for in-house items and purchase requisitions for bought items.
- A planned order is converted into a production order.
- Components are issued to the order (goods issue).
- Operations are confirmed, which records time and yield.
- The finished product is received into stock (goods receipt).
- The order is settled to Finance.
How production connects to other modules
Each step creates a document in another area:
- Goods issue to the order reduces component stock and posts a consumption entry in Finance.
- Confirmations post activity costs from work centers to the order in Controlling.
- Goods receipt increases finished goods stock at standard or actual cost.
- Settlement clears the order's collected costs and posts the difference to variance accounts. These postings land in the Universal Journal (ACDOCA), so product costs and G/L balances reconcile.
Common errors
- Missing plant extension. MRP ignores a material that has no MRP view in that plant.
- No BOM or routing. The system cannot create a valid production order or cost it.
- Wrong procurement type. A component set to external procurement creates purchase requisitions, not planned orders.
- Unsettled orders. Costs stay on the order and do not reach the financial statements until settlement.
- Negative stock. Issuing components that were never received blocks or distorts costing.
Checking production orders
This query reads production order headers from table AUFK for one plant. It is a quick way to see that orders belong to a company code and plant.
SELECT aufnr, auart, bukrs, werks
FROM aufk
WHERE werks = '1010'
INTO TABLE @DATA(orders)
UP TO 100 ROWS.Exercise
A planner runs MRP, but a purchased component is never shown in the plan for plant 1010. Name two master data checks you would make.
Show answer
Check that the material is extended to plant 1010 with an MRP view, and that its MRP type allows planning (not "no planning"). Also confirm the procurement type and that the product's BOM lists the component with a valid date.