Kanban and WIP Limits as a Pull Mechanism
This chapter assumes you can split a process into steps, read simple ratios, and know what a value stream is.
Kanban and WIP limits as a pull mechanism
A kanban board shows each work item as a card that moves across columns, one column per step. A work in progress (WIP) limit caps how many cards a column may hold at once. When a step has free capacity, it pulls the next item from the step before it. Nothing moves forward just because it is ready.
Little's Law states that average cycle time equals WIP divided by throughput. If throughput stays at 5 items per day, cutting WIP from 30 to 10 reduces average cycle time from 6 days to 2 days.
WIP_LIMIT = 3
def can_pull_new_work(in_progress):
"""Pull a new item only when the step is below its WIP limit."""
return in_progress < WIP_LIMIT
print(can_pull_new_work(2)) # True: capacity is free
print(can_pull_new_work(3)) # False: finish something firstPrinciple 5: Pursue perfection
Perfection means the process keeps improving until every step adds value and no work sits idle. Lean teams treat the current process as a draft. Waste returns in new forms, so the search never ends.
Kaizen and the Plan-Do-Check-Act cycle
Kaizen is continuous improvement made in small steps by the people who do the work. The Plan-Do-Check-Act (PDCA) cycle gives kaizen a repeatable structure:
- Plan: state the problem and a measurable target.
- Do: run a small trial.
- Check: compare the result with the target.
- Act: keep the change if it works, or adjust and run the cycle again.
Applying the five principles together
Use the five principles in order. Specify value from the customer's view. Map the value stream to find steps that add no value. Make the remaining work flow by reducing batch size and WIP. Let the customer pull work through the system with kanban. Then repeat the cycle with PDCA. Each principle depends on the one before it, so skipping one weakens the rest.
For a first improvement, choose the step with the longest waiting time, set a WIP limit on it, and measure cycle time before and after the change.
Exercise
A step finishes 4 items per day and has 20 items in progress. Using Little's Law, what is the average cycle time? If the WIP limit drops to 8 with the same throughput, what is the new cycle time?
Show answer
20 / 4 = 5 days. With WIP at 8: 8 / 4 = 2 days.