Sub topic 6
Structured: a predictable organisation
Assume you can build multi-sheet Excel workbooks, understand basic financial statements, and use relative and absolute cell references. You should also know IF, SUM, AND, ABS, and EOMONTH.
A structured model has a predictable organisation. A reviewer should know where to find assumptions, calculations, outputs, and checks without searching through every sheet. Structure reduces review time and makes changes safer.
Separate the model into layers
A practical layout separates data by purpose:
| Layer | Typical contents | Main rule |
|---|---|---|
| Inputs | Dates, prices, volumes, tax rates | Store assumptions once |
| Calculations | Timelines, operating schedules, statements | Keep formulas consistent |
| Outputs | Summaries, charts, decision metrics | Link to calculations |
| Checks | Balance tests and error flags | Make failures visible |
The exact number of sheets depends on the model. A small model might use Inputs, Model, Outputs, and Checks. A larger model might add separate operating schedules and financial statements. The names matter less than using the same pattern throughout the workbook.
Keep each sheet focused. Do not mix a user-entered assumption into the middle of a long calculation schedule. Link the calculation to the input instead. This gives reviewers one place to inspect and update the assumption.
Use one timeline across schedules
Every calculation schedule should use the same period columns, such as monthly columns from January 2027 through December 2029. Put period start dates, period end dates, and useful flags in dedicated rows near the top.
A flag is a value, usually 1 or 0, that tells a formula whether a condition applies. For example, an operations flag can identify periods between the start and end dates:
F10: =IF(AND(F$6>=Inputs!$D$8,F$7<=Inputs!$D$9),1,0)Here, rows 6 and 7 hold the period dates. The operations dates remain on the Inputs sheet. Every schedule can link to the same flag instead of creating its own date logic. This avoids small differences between schedules.
Repeat formulas consistently
Use one calculation per row and copy the formula across the timeline. If revenue is units multiplied by price, every period should follow that rule:
F22: =F20*F21Avoid changing the formula manually in one period unless the model explicitly requires a transition. A different formula in one column is difficult to spot and often causes a silent error.
Apply the structure in a review
Check whether inputs are separated, timelines align, formulas copy consistently, and outputs link to calculations rather than duplicated hardcodes. Record exceptions and decide whether each exception is necessary.
Exercise
A schedule has monthly columns, but one row starts one month later than all other rows. What should you investigate first?
Show answer
Check whether the row uses the same period headers and timeline flags as the rest of the schedule. If the timing difference is intentional, label and document it; otherwise, correct the alignment.