Preparing an organisation: a readiness checklist
This chapter turns the package into a work plan. It assumes you know the difference between a regulation and a directive, and you have read the earlier chapters on customer due diligence (CDD), beneficial ownership, enhanced due diligence (EDD), reporting and the timeline. It does not repeat them. It shows how to order the work, what to check, and where teams usually go wrong.
Start from the dates
The AML Regulation (EU) 2024/1624 applies directly from 10 July 2027. National laws implementing the sixth Directive (EU) 2024/1640 are due around the same time, with some provisions earlier or later. AMLA has operated since mid-2025. It will select entities for direct supervision during 2027, and that supervision starts in 2028. Some sectors have longer transition periods, so confirm the date for your own sector.
Because the Regulation applies directly, the obligations come from one text rather than from 27 national transpositions. Your own plan therefore has two fixed points: 10 July 2027, and any earlier supervisory contact you expect.
Workstream 1: scope and gap analysis
First establish whether you are an obliged entity, and in which capacity. The Regulation extends scope to sectors such as crypto-asset service providers and certain other newly covered firms. A firm that was outside the earlier framework may now be inside it.
- List every legal entity in the group and every activity it performs.
- Map each activity to the Regulation's list of obliged entities.
- Compare current controls with the Regulation article by article. Do not compare them with your national law, because national gold-plating no longer defines the baseline.
Workstream 2: risk assessment and governance
The business-wide risk assessment drives everything else, so do it early. Check that it covers customers, products, delivery channels and geographies, and that it is documented and approved by management.
- Name the person responsible for compliance and confirm their authority and independence.
- Check group-wide policies. A group must apply consistent standards in all its entities, including those in third countries.
- Plan review triggers, such as a new product, a new market or an AMLA guideline.
Workstream 3: CDD, beneficial ownership and EDD
This is usually the largest remediation effort, because it touches existing customer files.
- Identify which data fields the Regulation requires and compare them with what your systems hold.
- Test your beneficial-ownership logic. Ownership percentages multiply along a chain. A control test is also needed, because a percentage test alone is never sufficient.
- Recheck your EDD triggers for politically exposed persons (PEPs) and high-risk third countries.
- Define how you will handle files where the data is missing: re-contact the customer, restrict the relationship, or exit it.
Workstream 4: cash, crypto and transfers
- Cash: check whether your business accepts cash payments for goods or services. The Regulation sets an EU-wide cap on such payments, and member states may set a lower one.
- Crypto: crypto-asset service providers should review account types and wallet services against the Regulation's restrictions on anonymous accounts and similar products.
- Transfers: the travel-rule requirements of Regulation (EU) 2023/1113 already apply. Treat them as a baseline you must keep meeting.
Workstream 5: reporting and cooperation
Suspicious transaction reports go to the national financial intelligence unit (FIU). Check that you have an internal escalation path, a decision log and a way to answer FIU requests within the time the law sets. Check also that your reporting channel works with the FIU's format and that staff know the rules on not tipping off the customer.
Tracking status in code
A simple tracker keeps the plan honest. The script below holds each workstream with an owner, a due date and a status, and lists the items that are overdue or blocked.
from dataclasses import dataclass
from datetime import date
@dataclass
class Item:
workstream: str
owner: str
due: date
status: str # "not_started", "in_progress", "blocked", "done"
def at_risk(items, today):
"""Return items that are blocked, or past due and not done."""
return [
i for i in items
if i.status == "blocked" or (i.status != "done" and i.due < today)
]
plan = [
Item("Business-wide risk assessment", "MLRO", date(2027, 3, 31), "in_progress"),
Item("CDD data remediation", "Operations", date(2027, 6, 15), "blocked"),
Item("Staff training", "HR", date(2027, 6, 30), "not_started"),
Item("Gap analysis", "Compliance", date(2027, 1, 31), "done"),
]
for item in at_risk(plan, date(2027, 4, 15)):
print(item.workstream, item.owner, item.status)With the example dates, it prints the risk assessment (past due) and CDD data remediation (blocked).
Summary table
| Workstream | Key question | Typical evidence |
|---|---|---|
| Scope | Which entities and activities are covered? | Entity and activity map |
| Risk assessment | Is it current, documented and approved? | Signed assessment, review log |
| CDD and ownership | Do files meet the Regulation's data requirements? | Remediation statistics |
| EDD | Are PEP and high-risk-country triggers up to date? | Screening configuration, case samples |
| Cash and crypto | Do products respect the limits and restrictions? | Product review notes |
| Reporting | Can we escalate and file on time? | Escalation procedure, filing records |
| Training | Does staff understand the new rules? | Attendance and test results |
Common mistakes
- Treating the project as a policy rewrite only. Most of the effort lies in data and systems.
- Waiting for every technical standard before starting. Some AMLA standards and guidelines will arrive late, so build on the Regulation text and adjust.
- Ignoring the group view. A subsidiary in another member state is not covered by your head office's national interpretation.
- Assuming AMLA supervision does not affect you. If AMLA selects your group, you will deal with AMLA directly, but the national supervisor remains relevant for others.
Exercise
Your group has 80,000 customer files. Half have no recorded control assessment for legal-entity customers, and the risk assessment is not yet approved. Which workstream do you start first, and why?
Show answer
Start with the business-wide risk assessment. It sets the risk categories that decide the depth of CDD and the EDD triggers, so remediation done before it may have to be repeated. Run the data-gap analysis in parallel, because it tells you the size of the remediation task and lets you plan resources.