Sub topic 3
Force majeure: events beyond a party's control
This chapter assumes you know the elements of a binding contract (offer, acceptance, consideration, and intent to be bound) and have read a basic services agreement. It covers the final parts of a contract, from force majeure to the review checklist. This is general education, not legal advice. Rules vary by jurisdiction.
Force majeure
A force majeure clause excuses a party from performing when an event it cannot control prevents performance. Listed events often include natural disasters, war, pandemics, and government orders. The clause usually requires prompt written notice and suspends the affected obligations only while the event lasts. Payment obligations are often excluded. Whether an event qualifies depends on the exact wording, so a list that omits "supply chain failure" may not cover it.
Breach, notice and cure, and remedies
A material breach is a serious failure to perform. Most contracts require written notice describing the breach and a cure period, commonly 30 days, to fix it. If the breach is not cured, the non-breaching party may claim damages, terminate, or seek an injunction (a court order requiring or stopping an action). Check whether the listed remedies are exclusive or cumulative.
Governing law, jurisdiction, and dispute resolution
Governing law names the legal system that interprets the contract. Jurisdiction names the courts that hear disputes. Dispute resolution clauses often require negotiation or mediation first, then arbitration (a private process where an arbitrator decides) or litigation.
General provisions
Boilerplate clauses address recurring issues:
- Entire agreement: the written contract replaces earlier discussions.
- Amendment: changes must be in writing and signed by both parties.
- Assignment: a party may need consent before transferring its rights.
- Notices: the contract states addresses and delivery methods.
- Severability: if one provision is invalid, the rest still applies.
Schedules and exhibits
Schedules and exhibits are attached documents that hold detail, such as Schedule 1 listing deliverables. A precedence clause states which document controls when they conflict with the main body.
Signatures and execution
The signature block names each signatory, title, and date. Confirm that each signer has authority to bind the company. Check whether electronic signatures and counterparts (copies signed separately) are allowed.
Reading a contract: a review checklist
Read the contract in the order shown below.
Use this checklist:
- Are all parties named by legal name and entity type?
- Is each defined term used consistently?
- Does force majeure list the events you care about, with a catch-all phrase?
- Does breach require notice and a cure period?
- Are governing law and the dispute process stated?
- Are schedules referenced, with a precedence rule?
- Does each signer have authority?
Exercise
A supplier's contract lists "fire, flood, and war" as force majeure events. A factory closes because of a government shutdown order. Does the clause clearly cover this, and what should the customer check?
Show answer
The clause does not clearly cover a government order because the list omits it. The customer should check for a catch-all phrase such as "any event beyond reasonable control," whether the governing law provides relief anyway, and whether the supplier gave the required notice.