Force Majeure and Breach: When Performance Fails
This chapter assumes you understand basic business transactions, such as buying services or software. It also assumes you can follow cross-references between contract sections. No legal training is required. Rules about force majeure, excuse, and remedies differ by jurisdiction.
Force majeure: events beyond a party's control
A force majeure clause addresses an exceptional event that prevents or seriously delays a party from performing. Common examples include natural disasters, war, government orders, epidemics, strikes, and major failures of utilities or transport.
The clause does not automatically excuse every difficult event. Its wording usually determines:
- Which events qualify.
- Whether the event must be unforeseeable.
- Whether it must prevent performance or merely make performance more expensive.
- What notice the affected party must give.
- What steps the party must take to reduce the delay.
- How long the other party must wait before terminating.
A party usually cannot rely on force majeure when its own poor planning caused the problem. A shortage of ordinary supplies, for example, may not qualify unless the contract expressly includes it. Payment obligations are also often excluded because a party may still owe money even when another duty is delayed.
If an event beyond a party's reasonable control prevents performance, that party shall promptly notify the other party and use reasonable efforts to resume performance. The affected obligation is suspended only for the duration of the event. Either party may terminate this Agreement if the suspension continues for more than sixty (60) days.Notice matters because it gives the other party a chance to make alternative arrangements. A clause may require notice within a fixed period and may limit relief if notice is late.
Breach, notice and cure, and remedies
A breach is a failure to perform a contractual obligation. A material breach is a serious failure that substantially deprives the other party of the expected benefit. Contracts often connect breach to a notice-and-cure process.
The usual sequence is:
- The non-breaching party sends written notice describing the breach.
- The breaching party receives a stated cure period.
- The breaching party fixes the problem within that period, if possible.
- If the breach remains uncured, the non-breaching party may terminate or seek another remedy.
Some breaches require immediate action. A contract may allow immediate termination for insolvency, unauthorized disclosure of confidential information, or an infringement of intellectual property rights. Check whether the clause distinguishes curable from non-curable breaches.
Common remedies include damages, specific performance, an injunction, suspension of services, and termination. Damages are money awarded for loss. An injunction is a court order requiring or preventing conduct. A limitation-of-liability clause may restrict damages even when a breach is established.
| Review question | Why it matters |
|---|---|
| What counts as a material breach? | It determines when termination may be available. |
| How must notice be delivered? | An ineffective notice may delay or defeat a remedy. |
| How long is the cure period? | It sets the time available to correct the failure. |
| Which remedies are limited or excluded? | It shows the practical value of a successful claim. |
Exercise
A supplier's factory closes after a government evacuation order. The contract covers government orders, requires prompt notice, and suspends delivery duties during the event. The supplier gives notice but makes no effort to find an available alternative facility. What issue should the customer examine?
Show answer
The customer should examine the mitigation requirement. The event may qualify as force majeure, but the supplier may lose some protection if it failed to take the reasonable steps required by the contract.