Force majeure: events beyond a party's control
This chapter assumes you have read the chapters on obligations, term and termination, and breach and remedies. You should know that a party who fails to perform on time is normally in breach, and that breach opens the door to remedies such as damages and termination. Force majeure is a clause that changes that result for a defined set of events. This is general education, not legal advice, and rules differ by jurisdiction.
What a force majeure clause does
"Force majeure" is French for "superior force". A force majeure clause says that a party is excused from, or given more time for, performing an obligation when a listed event outside its control prevents or delays that performance.
Without the clause, a party that cannot perform is usually in breach, even if the cause was not its fault. The clause moves that risk. It decides who bears the loss when something goes wrong that neither party caused.
The concept has a different footing in different legal systems:
- In many civil law systems, force majeure is a doctrine in the code. A clause may refine it.
- In English law and most US states, there is no general doctrine that fits this role. The right exists only if the contract grants it, so the wording of the clause decides the outcome.
- Related doctrines such as frustration (English law) or impracticability (US law) may help when no clause exists. They apply narrowly and usually end the contract rather than pause it.
Because of this, you should read the clause itself and never assume that it follows a standard meaning.
The parts of a clause
Most clauses contain the same five parts. When you review one, check that each is present and clear.
| Part | Question it answers | Typical wording |
|---|---|---|
| Trigger events | What counts as force majeure? | Natural disasters, war, terrorism, government action, strikes, pandemics |
| Causation test | How closely must the event cause the failure? | "prevents", "hinders", or "delays" performance |
| Control and foreseeability | What must be true about the event? | "beyond the reasonable control of the affected party" |
| Procedure | What must the affected party do? | Prompt written notice, steps to reduce the effect |
| Consequences | What happens to the contract? | Suspension, extension of time, termination after a long delay |
Trigger events
Clauses list events in one of two ways. A closed list names specific events, and only those qualify. An open list ends with a general phrase such as "or any other cause beyond a party's reasonable control". Courts often read the general phrase narrowly, as covering only events similar to those listed.
Pay attention to events the list leaves out. The usual disputes involve pandemics, cyberattacks, supplier failure, changes in law, and sanctions. If a risk matters to your business, name it, or say clearly that it is excluded.
Causation
The wording sets a threshold. "Prevents" is strict, because performance must be impossible. "Hinders or delays" is easier to meet. Under most clauses, a party cannot rely on the clause just because performance became more expensive or less profitable. A supplier whose raw materials double in price is still bound unless the clause says price rises qualify.
Control and foreseeability
The event must be outside the affected party's reasonable control. Some clauses add that the event must be one that the party could not reasonably have foreseen or avoided. If the party could have prevented the event or its effect, for example with a backup site, the clause may not apply.
Two points follow from this. A failure by a subcontractor is usually not force majeure unless the subcontractor itself was hit by a qualifying event. A party's own labor dispute is often excluded, even though strikes in general may be listed.
Procedure
Clauses usually require the affected party to give notice within a stated time, describe the event and its likely duration, and take reasonable steps to limit the effect. Many courts treat the notice as a condition. A party that gives notice late, or not at all, can lose the protection even when the event was real.
Consequences
The common sequence is shown below.
A typical clause suspends the affected obligations while the event lasts and extends deadlines by a matching period. It then sets a long-stop date, often 30 to 90 days, after which either party may terminate by notice. Without a long-stop date, a contract can stay frozen indefinitely.
A sample clause
Neither party is liable for a failure or delay in performing its obligations, other than an obligation to pay money, to the extent the failure or delay is caused by a Force Majeure Event. "Force Majeure Event" means an event beyond the reasonable control of the affected party, including fire, flood, earthquake, war, terrorism, epidemic, or order of a government authority, but excluding a strike by the affected party's own employees and any change in market prices.
The affected party shall give written notice within five (5) business days after the event begins, describing the event and its expected duration, and shall use reasonable efforts to limit its effect. If the event continues for more than sixty (60) days, either party may terminate this Agreement by written notice.Notice what this clause does. It excludes payment obligations, so a customer cannot delay paying fees because of a flood at its office. It excludes the party's own strikes and price changes. It sets a five-business-day notice period and a 60-day long-stop date.
Common errors and edge cases
- Treating the clause as a general escape. The clause excuses performance only to the extent the event caused the failure. If the party was already late before the event, the earlier delay stays a breach.
- Forgetting payment. Money can almost always still be paid. Most clauses exclude payment obligations, and courts rarely excuse them.
- Missing the notice deadline. Diary the notice period when the event starts. This is the most common avoidable loss.
- Ignoring mitigation. The affected party must usually look for alternatives, such as another supplier or route. A clause that says "reasonable efforts" does not require a party to accept a ruinous cost, but it does require real attempts.
- Assuming a pandemic is covered. Unless named, an epidemic or a government lockdown may or may not qualify. Courts decided these disputes differently after 2020, depending on the wording.
- Overlooking the interaction with other clauses. Check whether the clause suspends service-level credits, minimum purchase commitments, and exclusivity. Also check whether it affects the termination-for-breach right, since a party excused by force majeure is not in breach.
- One-sided drafting. A clause that protects only the supplier, or that lets only one party terminate, shifts risk without saying so.
Review points
When you meet this clause in a contract, ask these questions:
- Is the list of events closed or open, and does it cover the risks that matter here?
- Does the clause excuse failure, delay, or both?
- Are payment obligations excluded?
- What notice is required, and by when?
- Is there a duty to mitigate?
- What is the long-stop date, and who may terminate?
- Does the clause apply equally to both parties?
Exercise
A software supplier agrees to deliver a hosted service by 1 June. On 20 May its main data center loses power because of a regional storm, which is a listed force majeure event. The supplier has a backup data center that it chose not to configure to save money. The clause requires "reasonable efforts to limit the effect" and notice within five business days. The supplier sends notice after nine days. Can the supplier rely on the clause? Give two reasons.
Show answer
Probably not. First, the notice was late, and if notice is a condition, the supplier loses protection even though the storm was real. Second, the supplier could have limited the effect with the backup site, so it likely failed the duty to use reasonable efforts, and a court may find the failure was not caused solely by an event beyond its control.
Exercise
A customer owes a fee on 15 July. A government order closes its offices on 10 July, a listed event. The clause excludes "an obligation to pay money". May the customer withhold payment until the order ends?
Show answer
No. The clause excludes payment obligations from the excuse, so the customer must still pay on time, for example by electronic transfer. Withholding payment would be a breach.