Sub topic 10
Checking that the fix worked
This chapter assumes you can already write a problem statement, build an evidence-backed 5 Whys chain, and define countermeasures for a root cause. Here you learn how to confirm that a countermeasure removed the cause and that the problem has stopped coming back.
Why a fix is a hypothesis
A countermeasure is a prediction: "If we change X, the problem will stop." Until you test that prediction, you only have a plan. Many teams close an action item when the change is made, and the problem returns weeks later. Verification is the step that turns the prediction into a result.
Two separate questions need answers:
- Was the countermeasure implemented as intended? This is a check on the work. Did the procedure change get published? Was the system step added? Do people use it?
- Did the countermeasure change the outcome? This is a check on the cause. Did the problem rate drop, and did it stay down?
A team can pass the first check and fail the second. That result means the root cause was wrong, or incomplete, or the countermeasure did not address it. It is useful information, not a failure of the team.
Define success before you act
Decide what "worked" means before you implement the fix. If you decide afterward, you will tend to read the data in the way that supports the fix.
Write down four things:
- The measure. Use the same measure as the problem statement. If the problem was "3 of 200 orders shipped with the wrong part per week," then the measure is wrong-part shipments per week.
- The target. For example, zero wrong-part shipments caused by bin moves.
- The observation window. How long you will watch before you decide.
- The owner. The one person who collects the data and reports it.
The problem statement you wrote at the start of the 5 Whys is your baseline. If it had no number, you cannot show improvement, so go back and collect one before you change anything.
Check the cause, not only the symptom
The overall problem rate can be misleading. It may fall for reasons unrelated to your fix, such as a seasonal dip in volume or a new employee who is being careful. It may also stay flat because other causes produce the same symptom.
To avoid both errors, measure at two levels:
- The outcome measure. The rate of the original problem, such as wrong-part shipments.
- The cause measure. Whether the root cause condition still occurs, such as bin moves closed without a system update.
In the warehouse example, the root cause was that the bin-move procedure did not require a system update. The cause measure is the share of move tickets closed with a matching system record. If that share is 100% and wrong-part shipments still occur, a different cause is at work, and you return to the chain or to a branch you did not follow.
The table shows how to read the two measures together.
| Cause measure | Outcome measure | Likely meaning |
|---|---|---|
| Fixed | Improved | The fix worked. Continue to monitor. |
| Fixed | Not improved | Wrong or incomplete root cause. Reopen the analysis. |
| Not fixed | Improved | The change is not what helped. Look for another explanation. |
| Not fixed | Not improved | The countermeasure was not carried out. Fix the implementation. |
Choose the observation window
A short window can hide a problem that happens rarely. A long window delays the decision. Choose the window from how often the problem occurred before.
A rough rule: watch for at least several times the usual gap between occurrences. If the problem happened about once a week, a week of quiet proves little. If it happened about once a month, wait for several months, or use the cause measure to get an earlier signal.
For rare problems, the cause measure is your main tool. You may not see enough failures to judge the outcome, but you can see every bin move and check whether the system was updated each time.
Compare against the baseline
Compare the same measure, collected the same way, before and after. Three practices help.
- Use the same definition. If "wrong part" meant any pick error before, do not narrow it to customer-reported errors after.
- Use rates, not counts, when volume changes. Two errors in 100 orders and two in 1,000 are different results.
- Look at the pattern over time, not one point. A single good week can be chance.
A simple run chart, which plots the measure over time with the fix date marked, often shows enough. For a higher-stakes problem, a control chart or a statistical test from the Six Sigma toolkit gives firmer ground. This tutorial does not cover those methods, and a basic run chart is enough for most 5 Whys results.
A small script to compare before and after
You can compute the rate before and after a fix with a few lines of Python. This example uses weekly counts of wrong-part shipments and orders shipped.
before = [
{"week": 1, "errors": 3, "orders": 200},
{"week": 2, "errors": 2, "orders": 190},
{"week": 3, "errors": 4, "orders": 210},
{"week": 4, "errors": 3, "orders": 200},
]
after = [
{"week": 5, "errors": 0, "orders": 205},
{"week": 6, "errors": 1, "orders": 195},
{"week": 7, "errors": 0, "orders": 200},
{"week": 8, "errors": 0, "orders": 210},
]
def rate_per_1000(weeks):
errors = sum(w["errors"] for w in weeks)
orders = sum(w["orders"] for w in weeks)
return 1000 * errors / orders
print(f"Before: {rate_per_1000(before):.1f} per 1000 orders")
print(f"After: {rate_per_1000(after):.1f} per 1000 orders")The output is:
Before: 14.9 per 1000 orders
After: 1.2 per 1000 ordersThe drop is large, but one error still occurred in week 6. Do not stop at the rate. Look at that error and ask whether it came from the same root cause (a bin move without a system update) or from a different one. If it is the same cause, the countermeasure has a gap. If it is different, it belongs in a new analysis.
Handle partial results
Results are often mixed. Common cases:
- Improved but not to target. The countermeasure helped, but another cause remains. Return to your branching causes. Each branch needs its own check.
- Improved, then relapsed. The fix depended on effort or attention rather than a changed process. A reminder email, for example, fades. Look for a countermeasure that makes the right action the default, such as a system field that blocks ticket closure.
- No change. Confirm the countermeasure was in use. If it was, the chain probably points at the wrong cause. Check each answer's evidence again, starting from the step closest to the problem.
Prevent side effects
A fix can solve one problem and create another. A required system-update step may slow bin moves, or people may skip the move ticket to avoid the step. While you check the outcome, also watch for these effects:
- Longer cycle times or queues at the changed step.
- Workarounds, such as recording a move after the fact.
- New errors at the point where the new step connects to old ones.
Ask the people who do the work. They notice workarounds before the data does.
Make the gain last
When the check shows the fix worked, make the change part of the standard process. Update the procedure, the training material, and any checklist. Remove the dependence on the person who found the problem.
Then keep a light monitor in place. Choose one measure, an owner, and a review date. A common choice is to review the cause measure monthly for a quarter, then move to a longer interval. Record the result with the original analysis so that someone who sees a similar problem can find what you learned.
Common errors in verification
- No baseline. Without a starting number, you cannot show change.
- Declaring success too early. A quiet period shorter than the usual gap between occurrences proves little.
- Measuring only the symptom. The rate may fall for unrelated reasons.
- Changing several things at once. You cannot tell which change helped. When practical, introduce one countermeasure at a time, or measure each one's cause separately.
- Ignoring the one remaining error. A single recurrence is a lead. Trace it with its own evidence.
- Moving the target. Changing the definition of the problem after the fact makes the result look better without making the process better.
Summary
Verification has two checks: the countermeasure was carried out, and the outcome changed. Set the measure, target, window, and owner first. Track both the cause and the outcome, compare against a baseline using the same definition, and look for side effects. If the result is mixed, return to the chain with the new evidence. When the gain holds, standardize it and keep a light monitor.
Exercise
A team found that late invoices were caused by the approval form having no required field for the cost center, so invoices stalled in review. They added the required field. After four weeks, the late-invoice rate fell from 12% to 9%. The cause measure shows that 100% of new forms now include a cost center. What do you conclude, and what do you do next?
Show answer
The countermeasure was carried out, because the cause measure is at 100%. The outcome improved only slightly, from 12% to 9%. This is the "Fixed, but not improved enough" case, so the root cause was incomplete. The missing cost center explains some late invoices but not most. Return to the 5 Whys chain or its branches, look at the late invoices that still occur, and trace each one with evidence. Also check that the observation window is long enough, and compare the rates using the same definition of "late" as before. Do not close the item yet.
Exercise
A hospital unit adds a reminder poster to cut missed hand-hygiene checks. Missed checks drop for two weeks, then return to the old level. Why did this likely happen, and what kind of countermeasure should the team look for?
Show answer
A poster depends on attention, and attention fades. The effect was a temporary change in behavior, not a change in the process. The team should look for a countermeasure that changes the process so the right action is the default or the wrong action is hard, such as placing dispensers at the door so staff pass them on entry, or adding a required check step before the next task can start. They should also revisit the root cause. If a poster only worked for two weeks, the cause may be about the layout or workflow, not about awareness.