Sub topic 3
Choosing among options with explicit criteria
This chapter assumes you have a TOWS matrix and a ranked list of SWOT entries. You should also be comfortable with weighted scoring, where each rating is multiplied by how much it matters.
Choosing among options with explicit criteria
Write down the criteria before you score any option. Rate each option from 1 to 5 on each criterion, where 5 is always the better result. Then assign weights that add up to 1.0. The weights show what the team values most.
criteria_weights = {"cost": 0.4, "time": 0.3, "risk_reduction": 0.3}
options = {
"Second supplier": {"cost": 3, "time": 3, "risk_reduction": 5},
"Stockpile parts": {"cost": 2, "time": 5, "risk_reduction": 3},
"Redesign part": {"cost": 2, "time": 1, "risk_reduction": 4},
}
scores = {
name: sum(criteria_weights[c] * rating[c] for c in criteria_weights)
for name, rating in options.items()
}
for name, score in sorted(scores.items(), key=lambda kv: kv[1], reverse=True):
print(f"{score:.2f} {name}")The script prints the options from highest to lowest score. Check the top two options against the evidence before you commit.
Recording the decision: owner, measure, review date
A decision needs four facts: the choice, the owner, the measure of success, and the review date.
Decision: Add a second supplier for the key part.
Based on: Weakness W2 (single supplier) x Threat T1 (supply disruption)
Owner: Head of Operations
Measure: share of parts sourced from a second supplier
Review date: end of next quarterCommon pitfalls and how to avoid them
| Pitfall | Fix |
|---|---|
| Choosing weights after seeing the scores | Agree on weights before scoring |
| Vague entries such as "strong brand" | Replace them with a measurable claim |
| Unranked lists | Sort entries by impact and confidence |
Keeping the analysis current
Revisit the SWOT on the review date in the record. Remove entries that no longer hold, add entries from new evidence, and keep the previous version so you can see what changed.
Exercise
Using the weights cost 0.2, time 0.5, and risk_reduction 0.3, which option ranks first? Show the arithmetic for the top two.
Show answer
Second supplier: 0.2×3 + 0.5×3 + 0.3×5 = 3.60. Stockpile parts: 0.2×2 + 0.5×5 + 0.3×3 = 3.80. Stockpile parts ranks first because time now carries the most weight.