Sub topic 1
Start with the Business Goal
Prerequisites
Assume you know basic terms such as impressions, clicks, and conversions. You should also be comfortable with percentages and simple arithmetic.
Start with the Business Goal
A marketing budget should follow a business result, not a channel habit. Start by stating the target and its time frame:
- Revenue target: $500,000 this quarter
- New-customer target: 500 customers
- Maximum acceptable customer acquisition cost (CAC): $80
- Required payback period: six months
Then translate the target into a measurable marketing objective. For example, “Generate 500 new customers at or below an $80 CAC” is more useful than “increase social spending.”
Know Your Numbers: CAC, Margin, and Break-Even ROAS
CAC is the average amount spent to acquire one customer:
CAC = marketing spend / new customers
Gross margin is the share of revenue left after the direct cost of delivering the product. If revenue is $100 and direct cost is $60, gross margin is 40%.
Return on ad spend (ROAS) is attributed revenue divided by advertising spend. Break-even ROAS depends on gross margin:
break-even ROAS = 1 / gross margin
With a 40% margin, break-even ROAS is 2.50. Every $1 of advertising must produce $2.50 in revenue before the order covers advertising and direct costs. This calculation does not include overhead, refunds, or future customer value, so it is a starting point rather than a complete profit model.
How Much to Spend: Budget-Setting Methods Compared
| Method | Calculation | Best use |
|---|---|---|
| Goal-based | Customers × target CAC | Clear acquisition target |
| Percent of revenue | Revenue × fixed percentage | Stable, established business |
| Test budget | Fixed amount with success limits | New channel or uncertain demand |
Choose the method that matches your evidence. A goal-based budget is defensible when CAC is known. A percent-of-revenue budget is simpler but can ignore changes in demand or efficiency. A test budget limits risk while you learn.
Exercise
A company wants 500 customers and expects an $80 CAC. What goal-based budget should it plan?
Show answer
$40,000, calculated as 500 × $80. It should still check whether that CAC is consistent with margin and payback requirements.