Sub topic 1
Contract basics you need before reading an MSA
Prerequisites
This chapter assumes you know what a contract is and can name common roles: client, vendor, project manager, and legal counsel.
Contract basics
A contract is a legally binding agreement. Four elements matter most in service agreements:
- Parties: the people or companies bound by the terms.
- Obligations: what each party must do or deliver.
- Consideration: what each side receives in return, usually payment.
- Written terms: the signed text that records the deal. Courts and counterparties usually start there when a dispute arises.
Enforceability varies by jurisdiction, so treat this as general education, not legal advice.
The master service agreement
A master service agreement (MSA) is a reusable legal framework. It sets the general terms once: warranties, indemnities, limitation of liability, confidentiality, intellectual property, term, termination, and dispute resolution. The parties sign it once and reuse it across projects.
What the MSA leaves out
An MSA usually does not describe the work itself. That job belongs to the statement of work.
The statement of work
A statement of work (SOW) is a project-specific agreement issued under an MSA. Each SOW covers the scope, deliverables, acceptance criteria, schedule, pricing, and change control for one project. Several SOWs can sit under one MSA.
Which document wins
When documents conflict, an order-of-precedence clause decides which one controls. A common order is: signed change orders, then the SOW where it expressly overrides the MSA, then the MSA, then other attachments. Without such a clause, a conflict becomes an argument about which text was meant.
Defining scope, deliverables, assumptions and exclusions
Scope states what the vendor will do. Deliverables are the tangible outputs, each with measurable acceptance criteria. Assumptions list what the vendor relies on, such as the client providing test data by a set date. Exclusions name work that is out of scope.
## 2. Scope of Services
In scope:
- Migrate customer records to the new platform
Out of scope:
- Data cleansing before migrationExercise
A signed change order conflicts with the SOW on a deadline. Which document controls under the common order of precedence?
Show answer
The signed change order controls for the matters it changes, because it ranks above the SOW and the MSA.