Fast-Tracking: Doing Work in Parallel
This chapter assumes you know how to read an activity network, compute early and late dates, and identify the critical path. It also assumes you understand finish-to-start dependencies, where one activity must finish before its successor starts.
Fast-Tracking: Doing Work in Parallel
Fast-tracking shortens a schedule by running activities that were planned in sequence at the same time. The change alters dependencies, not resources or scope. Each overlap saves time, but the successor starts before its predecessor is complete.
design, build = 6, 8
sequential = design + build # finish-to-start: 14 days
build_start = 3 # build starts 3 days before design ends
overlapped = max(design, build_start + build) # 11 days
print(sequential, overlapped, sequential - overlapped) # 14 11 3The Risks of Fast-Tracking: Rework and Coordination
Fast-tracking carries two main risks:
- Rework. The successor may use incomplete inputs. If the design changes after construction starts, the built work must be redone.
- Coordination overhead. Teams must share interim information, which takes meeting time and communication effort.
Treat the saved days as provisional until the overlap is checked against the risk of rework.
Choosing Between Crashing and Fast-Tracking
Crashing adds money and resources to critical activities. Fast-tracking adds risk and coordination effort. Choose crashing when the work cannot safely overlap or when extra resources are available at a reasonable cost. Choose fast-tracking when the successor can start on partial output and the team can absorb rework. Both techniques usually shorten only critical-path activities.
Limits, Diminishing Returns and Combining Techniques
Each additional overlap or crash usually costs more per day saved, and the risk rises as overlaps grow. Stop when the next day costs more than the value of the time it saves, or when rework risk threatens quality. Teams often combine both techniques, crashing one activity while overlapping another, but each combination compounds the risks.
Exercise
Exercise
Design takes 6 days and build takes 8 days, finish-to-start. If build starts 4 days before design finishes, how many days does the project take, and what is the risk?
Show answer
Build starts on day 2 (6 minus 4) and ends on day 10, so the project takes 10 days. The saved time is 4 days, but build may rely on design output that is still changing, so rework is the main risk.