Sub topic 3
Setting working agreements
This chapter assumes you know how a kickoff agenda is structured, how a decision log works, and how a project plan assigns owners and due dates. Have your draft agenda ready.
Setting working agreements
A working agreement is a short list of norms the team agrees on together, such as how fast people reply to messages, where decisions get recorded, and who makes the final call when people disagree. Agree on three to six items and write them into the kickoff notes so the team can check them later.
Facilitating the discussion
Keep each agenda item inside its time box. Ask the lead of each item to state the outcome needed, then invite questions. When one voice dominates, ask quieter attendees for their view by name. Place off-topic issues on a visible parking list and assign an owner to revisit each one.
Recording decisions and action items
Record each decision with the person who made it. Record each action with one owner and one due date. An action with two owners has no owner. Keep open questions in a separate list, with a named person responsible for answering each one.
Following up after the kickoff
Send the summary within one business day. Restate the goal, the decisions, each action with its owner and due date, the open questions, and the next checkpoint. Keep the message under 200 words so people actually read it.
Running the kickoff remotely or in a hybrid setting
Put the agenda and notes in one shared document that everyone can edit. In a hybrid meeting, remote attendees often cannot see the room. Assign one person to watch the chat and raise remote questions. Start with a short round in which each person says their name and one concern, so remote attendees speak early.
Adapting the kickoff to project size and type
A small project may need only 30 minutes and a short agenda. A large program may need a separate session for each workstream, plus a session for stakeholders. Keep the same sections in every case. Change the depth and the number of attendees, not the purpose of each section.
Exercise
Exercise
A kickoff ends with the action "Improve the test environment" and no owner. What is wrong, and how do you fix it?
Show answer
The action has no owner and no due date, so no one is accountable for it. Assign one named person and a due date before the meeting closes. If the group cannot agree on an owner, record it as an open question with a named person who will decide by a set date.