Sub topic 8
Surfacing Risks, Assumptions, and Dependencies
This chapter assumes you know the project’s goals, deliverables, roles, and draft timeline. You also know how to participate in a team meeting and record follow-up actions.
A kickoff should expose conditions that could affect delivery. It does not need to solve every problem. Its purpose is to make uncertainty visible, assign ownership, and decide which issues need attention first.
Distinguishing the three categories
These terms describe different kinds of uncertainty:
- A risk is a possible event that could harm or delay the project. For example, a supplier may miss a delivery date.
- An assumption is something the team is treating as true so planning can continue. For example, the test environment will be available in April.
- A dependency is something the project needs from another person, team, system, or event. For example, testing depends on the security team approving access.
One item can belong to more than one category. If the team assumes that a vendor will deliver on time, the vendor delivery is also a dependency. If that assumption may be wrong, late delivery is a risk.
Prepare a starting list
Before the kickoff, review the project brief and draft timeline. Look for statements that contain uncertainty or rely on work outside the team’s control.
Ask:
- What could prevent a milestone from being reached?
- Which facts have not been confirmed?
- What must another team, supplier, or decision-maker provide?
- Which decision is still waiting for information?
- What constraint could change the scope, cost, or schedule?
Bring a short starting list to the meeting. Do not present it as complete. The team should add items from its own experience.
Use a table that makes ownership and timing explicit:
| Type | Item | Effect if unresolved | Owner | Next action | Review date |
|---|---|---|---|---|---|
| Risk | Vendor API may be late | Integration milestone slips | Priya | Confirm delivery date and backup plan | 2026-04-10 |
| Assumption | Legal review takes five business days | Launch date depends on this estimate | Marco | Validate service-level target | 2026-04-08 |
| Dependency | Security team must approve production access | Release cannot proceed | Lee | Book approval review | 2026-04-12 |
An owner is responsible for moving the item forward. The owner does not have to solve it alone.
Discuss items during the kickoff
Reserve a focused section of the agenda for risks, assumptions, and dependencies. Start with the items that could affect the earliest milestone or the project’s main success criterion.
For each item, guide the group through four questions:
- What exactly might happen or what must be true?
- What would be the effect on the project?
- Who can confirm, reduce, or manage it?
- What action will happen next, and by when?
Avoid vague entries such as “communication may be difficult.” Replace them with a specific condition, effect, and action: “The operations team has not confirmed weekend support. Without support, the migration cannot start on Saturday. Lee will confirm coverage by Friday.”
Do not turn the kickoff into a detailed problem-solving workshop. If an issue needs more analysis, record the decision needed, assign an owner, set a due date, and schedule a separate discussion.
Map how items affect the plan
Show important relationships rather than listing isolated concerns. In the example below, the approval dependency creates a risk to the release milestone.
At the end of the discussion, read back the highest-priority items. Confirm each owner and date aloud. Update the project plan when an item changes a milestone, scope boundary, or communication need.
After the meeting
Track the list with the project’s normal planning tool. Review it at the agreed cadence, not only when a problem appears. Close an item when its condition is no longer relevant or when the team has accepted the remaining exposure.
Send the updated list with the kickoff follow-up. This gives people a shared record and makes early action visible.
Exercise
The project assumes that a partner will provide test data before development begins, but the partner has not confirmed a date. How should you record this?
Show answer
Record the unconfirmed delivery as a dependency, the unverified date as an assumption, and the possible development delay as a risk. Assign an owner to confirm the date and set a due date for that action.