Sub topic 2
Mitigation, Proof, and Alternative Remedies
This chapter assumes you know the elements of a valid contract, the difference between breach and discharge, and that courts apply common law and equity as separate rule sets.
Mitigation: the claimant's duty to limit loss
After a breach, the claimant must take reasonable steps to reduce its loss. Losses that reasonable steps would have avoided are not recoverable. The defendant must prove that the claimant failed to mitigate. Reasonable costs of mitigation are recoverable even if the attempt fails.
Proving loss and dealing with uncertainty
The claimant must prove loss on the balance of probabilities. Where a future gain is speculative, the court may award a percentage that reflects the lost chance instead of the full sum.
Reliance damages and restitution as alternatives
When expected profit is too hard to prove, the claimant may claim reliance damages, which recover money spent in performing the contract. Restitution instead returns a benefit the defendant received from the claimant. The defendant may argue that the contract would have lost money, which would reduce a reliance claim.
Agreed damages clauses and the penalty rule
A liquidated damages clause fixes in advance the sum payable on breach. A court enforces it if it protects a legitimate interest and is not out of all proportion to that interest. A clause that is extravagant and punishes breach is a penalty and is unenforceable.
| Clause type | Test | Result |
|---|---|---|
| Liquidated damages | Protects a legitimate interest, not out of proportion | Enforced |
| Penalty | Extravagant, punishes breach | Unenforceable |
Nominal damages and why punitive damages are rare
If breach causes no provable loss, the court may award nominal damages, a token sum confirming that the right was violated. Punitive damages, which punish the defendant, are rare in contract. Courts allow them only in a narrow set of recognized exceptions.
When damages are not enough
Damages are inadequate when the subject matter is unique, such as land or a rare artwork. In those cases the court may order specific performance instead, subject to the bars covered later in this tutorial.
Exercise
A supplier breaches a contract to deliver 10 tonnes of steel at £500 per tonne. The day after breach, the buyer could buy the same steel elsewhere for £550 per tonne. Instead, the buyer waits a month and pays £600 per tonne. What loss is recoverable?
Show answer
The recoverable loss is £500 (10 tonnes × £50), the difference between the contract price and the immediate replacement price. The extra £50 per tonne from waiting is avoidable, so it is not recoverable unless the delay was reasonable.