Sub topic 7
Proving Loss and Dealing with Uncertainty
The certainty requirement
This chapter assumes you understand the basic elements of a valid contract, the difference between breach and discharge, and the distinction between legal rules and equitable rules.
A claimant seeking damages must prove that the breach caused a legally recognised loss. The claimant must usually prove:
- The defendant breached the contract.
- The breach caused the claimed loss.
- The type of loss is not too remote.
- The amount of loss can be proved with sufficient certainty.
The claimant does not need mathematical precision. Courts often make a reasonable estimate where the evidence supports the existence of loss but the exact amount is uncertain. However, a court will not award damages based only on speculation.
Different kinds of uncertainty
Uncertainty can affect either the existence of loss or its amount.
| Type of uncertainty | The question for the court | Typical result |
|---|---|---|
| Existence of loss | Has the claimant shown that a loss probably occurred? | If no, only nominal damages may be available |
| Amount of loss | Has the claimant provided a reasonable basis for valuing the loss? | The court may make an estimate |
| Causation | Did the breach cause the loss rather than another event? | Unconnected loss is not recoverable |
| Future loss | Is the future loss sufficiently probable? | The court may discount or estimate it |
For example, a supplier breaches a contract to deliver equipment. The buyer proves that it had to pay £8,000 more for replacement equipment. The amount is supported by invoices, so the loss is relatively certain.
By contrast, suppose the buyer claims £100,000 in lost profits from an unlaunched business. The buyer must provide evidence such as market research, comparable sales, orders, operating costs, and the business plan. A bare assertion that the business would have succeeded is unlikely to be enough.
Reasonable estimation
Courts distinguish between uncertainty about the fact of loss and uncertainty about its precise value. Once the claimant proves that loss probably occurred, the court may estimate the value using the available evidence.
A claim for future profits may include assumptions about demand, costs, and the length of the trading period. The court can account for those assumptions by reducing the award or applying a percentage probability. A claim for a lost commercial opportunity may therefore be valued as:
value of successful outcome × probability of success
If a lost contract would have produced £40,000 profit but the claimant had only a 25% chance of securing it, an estimated award might be £10,000, subject to causation, remoteness, and mitigation.
This does not allow a claimant to recover every possible future benefit. The evidence must provide a rational basis for the estimate.
Reliance expenditure and evidential gaps
A claimant may claim reasonable expenditure incurred in reliance on the contract instead of expected profits. This can help where expected profits are difficult to calculate. For example, a claimant might recover money spent preparing for a performance that the defendant cancelled.
Reliance damages are not automatically available merely because the claimant spent money. The defendant may argue that the expenditure would have been wasted even if the contract had been performed. If that argument is persuasive, the expenditure was not caused by the breach.
A claimant must also avoid double recovery. The same loss cannot be recovered once as wasted expenditure and again as lost profit.
A practical proof sequence
Key evidence
Useful evidence can include:
- invoices and replacement quotations;
- accounts, budgets, and sales records;
- expert valuation evidence;
- comparable transactions;
- customer orders or cancelled bookings;
- records showing mitigation or alternative opportunities.
The court evaluates the evidence as a whole. An estimate becomes weaker when it depends on several unsupported assumptions.
Exercise
A contractor breaches a contract to build a shop. The owner proves £12,000 in additional construction costs but claims £200,000 in projected profits from the shop without providing sales records, market evidence, or a business plan. What is the likely approach?
Show answer
The £12,000 additional cost is supported by concrete evidence and may be recoverable if caused by the breach. The £200,000 profit claim is likely to be rejected or substantially reduced because its existence and amount are too speculative.