Tracking Open Points in an Issues List
Assume you know basic contract structure, can use a word processor, and understand that negotiation involves proposed changes and responses. This chapter focuses on managing unresolved points after you receive or send a redline.
An issues list is a separate working document that records each unresolved negotiation point. It is not a replacement for the contract. It is a control panel for the negotiation: it shows what remains open, who owns the next action, and what outcome is acceptable.
Record decisions, not every markup
Do not create an issue for every tracked deletion or punctuation change. Create one when a change affects risk, money, timing, responsibility, or the ability to perform the agreement.
A useful issue entry answers five questions:
- What clause or schedule is affected?
- What does each side currently want?
- Why does the point matter?
- Who must act next?
- What resolves or closes the point?
Use a stable ID such as LIAB-01 or TERM-02. Keep the ID unchanged across negotiation rounds so that comments, emails, and meeting notes can refer to the same issue.
| ID | Clause | Open point | Owner | Status | Next action |
|---|---|---|---|---|---|
| LIAB-01 | 8.2 Liability | Fixed cap versus fees-based cap | Supplier | Open | Supplier to propose a floor |
| TERM-02 | 4.1 Termination | Notice period for convenience termination | Customer | Pending response | Confirm business requirement |
A status should describe the state of the issue, not your feeling about it. Common statuses include:
- Open: no agreed position exists.
- Pending response: one side has sent a proposal and is waiting.
- Under review: the point needs business, legal, finance, or security input.
- Agreed: both sides have accepted the substance, even if the clean contract is not updated.
- Closed: resolved or removed from the negotiation.
Separate substance from document mechanics
A counterparty may accept the commercial position but fail to reflect it correctly in the next draft. Track that as a drafting follow-up, not as a new commercial dispute.
For example, if both sides agree that the liability cap is based on fees paid in the previous twelve months, the issue can be marked Agreed. A separate action can require someone to check the defined term “Fees,” update a cross-reference, and confirm that the redline matches the decision.
Record the source of each decision. Useful sources include a meeting date, email, comment number, or approval from a named stakeholder. This prevents the team from reopening settled points because nobody can identify how they were resolved.
Use the list to drive the next round
Before sending a response, filter the list for open and pending items. Confirm that every item has an owner and a next action. Group related issues, such as the liability cap and indemnity exclusions, because conceding one may change the acceptable position on the other.
Mark fallback positions clearly, but protect them from accidental disclosure. A fallback might be “accept a fees-based cap with a minimum floor,” while the internal reservation is the lowest acceptable floor. Share only the proposal appropriate for the current round.
A change involving regulatory duties, intellectual property ownership, indemnities, data protection, employment matters, or unusual remedies should be reviewed by a qualified lawyer before you treat it as agreed.
Exercise
The counterparty accepts your proposed termination notice period in an email, but the next redline still shows the old period. How should you track this?
Show answer
Mark the commercial issue as agreed, record the email and date as the decision source, and create a drafting follow-up to verify that the next contract version contains the accepted period.