Sub topic 13
Action: turning the plan into work
This chapter assumes you know the RACE stages, the SOSTAC sequence, and basic web analytics terms such as visits and conversion rate. It covers the fifth SOSTAC stage, Action, where the tactics you chose become scheduled, owned and resourced work.
What Action produces
Tactics describe what you will do. Action describes who does it, when, with what, and in what order. The output of this stage is a working plan that a team can follow without further interpretation. It has four parts:
- Responsibilities: one named owner for each tactic.
- Schedule: start dates, deadlines and dependencies.
- Resources: budget, people, tools and any outside agencies.
- Contingency: what happens if a task slips or a result is poor.
In the YAML skeleton from the earlier chapters, the action block holds an owner and a start date. A real plan expands that block into a task list.
Assign one owner per task
A shared task often becomes nobody's task. Name one person as accountable for each tactic, even if several people help. For the abandoned-basket email sequence, the owner might be the email marketer. A developer is responsible for the one-page checkout, but the digital marketing manager stays accountable for the overall result.
Sequence the work by dependency
Some tasks must finish before others can start. Tracking and analytics come first, because without them you cannot measure the baseline or the results. The checkout change should be live before you send traffic to it. The diagram shows an example order.
Build a schedule with dates
Turn the sequence into a table that shows the owner, the dates and the resource each task needs.
| Task | Owner | Start | Due | Resource |
|---|---|---|---|---|
| Set up conversion tracking | Analyst | 1 May | 7 May | Analytics tool |
| Build one-page checkout | Developer | 8 May | 24 May | 10 development days |
| Write email sequence | Email marketer | 8 May | 20 May | Email platform |
| Launch and begin weekly review | Marketing manager | 27 May | Ongoing | Dashboard |
Plan resources and contingency
Estimate costs before you commit. Include staff time, since it is often the largest cost and the one most often left out. Keep a reserve, commonly around 10% of the budget, for tests or delays.
Decide in advance what triggers a change. For example, if the checkout is late by more than one week, you might launch the email sequence first and keep the old checkout for now. Writing this down avoids arguments later.
Common errors in Action
- Vague owners: a team name such as "Marketing" instead of a person.
- Missing dependencies: launching a campaign before tracking works, so results cannot be read.
- No staff time costed: the plan looks affordable but cannot be delivered.
- No contingency: a single delay stalls the whole plan.
Action feeds directly into Control. The dates and owners you set here become the points where you check progress against your KPIs.
Exercise
A plan includes three tactics: a paid search campaign, a new landing page, and conversion tracking. Put them in a sensible order and give one reason for the position of tracking.
Show answer
Tracking first, then the landing page, then the paid search campaign. Tracking must work before any traffic arrives, or you lose the baseline and early results. The landing page should be live before paid search sends visitors to it, so the budget is not spent on a page that is not ready.