Action: turning the plan into work
This chapter assumes you know the SOSTAC stages and have a strategy and a tactics list to work from. It also assumes you can read a simple schedule and a YAML file. Action is the fifth SOSTAC stage. It answers one question: who does what, with which resources, and by when?
What Action produces
Tactics describe what you will do, such as an abandoned-basket email sequence or a one-page checkout. They do not say who builds them, what they cost, or which one must finish first. Action closes that gap. Its output is a plan people can start work from on Monday morning. It has three parts:
- Resources: budget, people's time, tools, agencies and freelancers.
- Schedule: start dates, deadlines, dependencies and review points.
- Responsibilities: one named owner for each piece of work.
A plan that stops at tactics usually fails here. Work gets assigned loosely ("marketing will handle it") or in the wrong order. For example, a campaign launches before the tracking that would measure it is installed.
Resources
List the resources each tactic needs before you commit to a date. There are four kinds to check.
- Budget. Separate media spend (paid search, paid social) from build costs (design, development) and running costs (software subscriptions, content production).
- People. Estimate time in days, not just "involved". A checkout redesign may need five developer days and two design days. If those people are also on other projects, the real calendar duration is longer.
- Tools. Check what you already own (analytics, email platform, tag manager) and what you must buy or configure.
- Skills. Decide whether to build the skill in-house, hire it, or outsource it. Outsourcing shifts effort to briefing and review, so it is not free of internal time.
If the resources do not cover the tactics, you have two honest options. Cut tactics or reduce the objective. Quietly stretching the same team over more work is the third option, and it usually fails.
Responsibilities
Each task needs exactly one owner, the person accountable for it being done. Others may contribute, but a task with two owners effectively has none. A simple RACI matrix (Responsible, Accountable, Consulted, Informed) helps when many people are involved. Do not confuse this RACI with the RACE framework. They share four letters and nothing else.
| Task | Owner | Contributes | Informed |
|---|---|---|---|
| Install conversion tracking | Analyst | Web developer | Marketing manager |
| One-page checkout | Web developer | Designer, analyst | Customer support |
| Abandoned-basket emails | Email marketer | Copywriter | Marketing manager |
| Weekly dashboard review | Marketing manager | Analyst | Leadership |
Schedule and dependencies
A schedule is more than a list of dates. Some work must finish before other work can start, and these dependencies decide the order. In this plan, tracking has to be live before the checkout change goes out. Otherwise you cannot tell whether the new checkout raised the conversion rate.
Check these points when you build the schedule:
- Baseline first. Tracking and baseline measurement come before any change you want to evaluate.
- Lead times. Content approval, legal review, design and developer queues often take longer than the work itself.
- Seasonality. Avoid launching a major change just before a peak trading period, when a mistake is most costly.
- Review points. Put checkpoints in the schedule, not only deadlines. They are where the Control stage connects back to Action.
- Slack. Leave buffer. A schedule with no slack is already late.
Writing Action into the plan
The skeleton in the Topic Spine keeps the action section short: an owner and a start date. That is enough for a one-objective plan. A larger plan expands it into tasks, each with an owner, dates and dependencies. This version uses the same tasks as the chart above.
action:
owner: Digital marketing manager
start: 2026-05-04
budget:
build: 6000
media: 0
tools: 300
tasks:
- id: tracking
owner: Analyst
start: 2026-05-04
end: 2026-05-08
depends_on: []
- id: checkout
owner: Web developer
start: 2026-05-11
end: 2026-05-29
depends_on: [tracking]
- id: email_sequence
owner: Email marketer
start: 2026-05-11
end: 2026-05-22
depends_on: [tracking]
- id: launch_review
owner: Digital marketing manager
start: 2026-06-01
end: 2026-06-05
depends_on: [checkout, email_sequence]You can check a schedule like this automatically. The script below flags the most common Action errors: a task with no owner, an end date before its start date, an unknown dependency, and a task that starts before the work it depends on has finished.
from datetime import date
tasks = {
"tracking": {"owner": "Analyst", "start": date(2026, 5, 4),
"end": date(2026, 5, 8), "depends_on": []},
"checkout": {"owner": "Web developer", "start": date(2026, 5, 11),
"end": date(2026, 5, 29), "depends_on": ["tracking"]},
"email_sequence": {"owner": "Email marketer", "start": date(2026, 5, 11),
"end": date(2026, 5, 22), "depends_on": ["tracking"]},
"launch_review": {"owner": "Digital marketing manager",
"start": date(2026, 6, 1), "end": date(2026, 6, 5),
"depends_on": ["checkout", "email_sequence"]},
}
problems = []
for name, task in tasks.items():
if not task["owner"]:
problems.append(f"{name}: no owner")
if task["end"] < task["start"]:
problems.append(f"{name}: ends before it starts")
for dep in task["depends_on"]:
if dep not in tasks:
problems.append(f"{name}: unknown dependency '{dep}'")
elif tasks[dep]["end"] >= task["start"]:
problems.append(f"{name}: starts before '{dep}' has finished")
if problems:
print("\n".join(problems))
else:
print("No problems found")Run as shown, it prints No problems found. Change the start date of checkout to date(2026, 5, 6) and it reports that checkout starts before tracking has finished.
Connecting Action to RACE and Control
Action is where RACE stages become workloads. A plan with objectives at several stages needs parallel workstreams, for example SEO content (Reach), landing page testing (Act), checkout changes (Convert) and a loyalty email programme (Engage). Each stage often belongs to a different team, so ownership has to be explicit. Shared stages, such as the handover from Act to Convert, are where work most often falls between two teams.
Action also feeds Control. The review points you schedule now become the monitoring routine later. For each task, decide in advance what "done" means and which KPI or output will show it. "Checkout live and tested" is a done-state. "Conversion rate at 2.0%" is an outcome, and it can only be judged after the task is done and traffic has passed through it.
Common errors
- Owner is a team, not a person. "The web team" cannot be asked for an update. Name one individual.
- Tracking scheduled after launch. You lose the baseline and cannot attribute any change.
- Dates with no resource check. The schedule assumes people are free when they are not.
- Everything starts at once. Parallel work looks fast on paper, but it overloads the same few people.
- No decision points. If a test fails, nobody has authority to stop or change course. Name who decides, and when.
- Budget only for media. Build, content and tooling costs get missed, and the plan overruns.
Checklist
Before you move to Control, confirm that:
- Every tactic maps to at least one task.
- Every task has one named owner, a start date, an end date and a done-state.
- Dependencies are written down, and baseline tracking comes first.
- Budget and people's time cover all tasks, not just media.
- Review points are scheduled and linked to the KPIs in Control.
Exercise
A plan has three tasks: "A/B test the new landing page" (owner: Web team, 1–12 June), "Install conversion tracking on the landing page" (owner: Analyst, 8–19 June), and "Write test report" (owner: Analyst, 15–19 June, depends on the test). Identify two problems with this Action section and say how you would fix each.
Show answer
First, the test starts on 1 June but the tracking it needs is not finished until 19 June, so the test would run without measurement. Move tracking to finish before the test starts, or move the test after tracking, and add tracking as a dependency of the test. Second, the owner "Web team" is a group, not a person, so no one is accountable. Name one individual as owner. The report is also scheduled to start on 15 June, before the test ends on 12 June, which is fine for ordering, but it should still be set after the tracking is live so it has data to report on.