Timeline, Budget, and Responsibilities
Assume you understand basic public relations planning, common communication channels, and simple percentages and counts. This chapter shows how to turn a campaign strategy into an organized delivery plan.
Turn strategy into a work plan
A campaign timeline connects activities to dates, dependencies, and decision points. A dependency is a task that must happen before another task can begin. For example, a spokesperson briefing must happen before a media interview.
Start with the campaign launch date and work backward. Include time for:
- Research, approvals, and message development
- Content production and accessibility checks
- Spokesperson training
- Partner or stakeholder coordination
- Media outreach and follow-up
- Community or digital activities
- Monitoring, evaluation, and reporting
A task should have one clear owner, even when several people contribute. Use milestones for important points such as “key messages approved” or “launch materials published.”
Build a realistic budget
A campaign budget estimates the money needed to deliver the plan. Group costs by activity so that decision-makers can see what each part of the campaign requires.
| Budget category | Example cost | Planning question |
|---|---|---|
| Content production | $2,500 | Which writing, design, video, or translation work is needed? |
| Distribution and promotion | $1,500 | Are paid placements, printing, or event costs required? |
| People and suppliers | $3,000 | Which work needs staff time or external expertise? |
| Contingency | $700 | What unexpected costs could affect delivery? |
Separate fixed costs from variable costs. A fixed cost does not change when reach changes, such as a design fee. A variable cost changes with volume, such as printing more leaflets.
A contingency is reserved money for reasonable uncertainty. For example, a campaign may need extra translation, event security, or rapid content changes. State the contingency percentage rather than hiding it in individual line items.
You can check a draft budget with a simple calculation:
production = 2500
distribution = 1500
suppliers = 3000
contingency_rate = 0.10
subtotal = production + distribution + suppliers
contingency = subtotal * contingency_rate
total = subtotal + contingency
print(f"Subtotal: ${subtotal:,.2f}")
print(f"Contingency: ${contingency:,.2f}")
print(f"Total budget: ${total:,.2f}")Assign responsibilities clearly
A responsibility matrix prevents missed tasks and duplicated work. A common model is RACI:
- Responsible: does the work
- Accountable: owns the final result and approval
- Consulted: gives input before completion
- Informed: receives updates
Give each task one accountable person. Several people may be responsible, but unclear accountability creates delays.
| Task | Responsible | Accountable | Consulted | Informed |
|---|---|---|---|---|
| Approve launch release | PR writer | Communications director | Legal adviser | Project team |
Review the matrix with the people named in it. Check that they have the time, authority, and budget access needed for their roles. Add an escalation route for blocked approvals or emerging risks.
Exercise
Exercise
A campaign has a $12,000 subtotal and a 15% contingency. What is the total budget, and who should be accountable for approving it?
Show answer
The contingency is $1,800, so the total budget is $13,800. The person with authority over the campaign budget, such as the communications director or project sponsor, should be accountable for approving it.