Sub topic 12
Tracking progress and adjusting the plan
A schedule is a forecast, and forecasts drift. This chapter covers how to measure whether you are on track, how to read those measurements, and what to change when you are not. It assumes you already have a dated, backward-planned calendar with hours allocated by topic area and with practice, review and mock exams placed in it, as built in the earlier chapters. It also assumes you can use a spreadsheet. The Python example is optional.
What to track, and why
Tracking has one purpose: to tell you early enough that you can still fix a problem cheaply. Track a few numbers you can collect in under five minutes a week. Four metrics cover most of what matters.
| Metric | What it tells you | Where it comes from |
|---|---|---|
| Hours logged vs planned | Whether your time budget is holding | A simple log of study sessions |
| Modules completed vs planned | Whether your pace through the curriculum is holding | Your calendar's module checklist |
| Practice accuracy by topic area | Whether the time you spend produces understanding | Question bank results |
| Mock exam score by topic area | Where you stand under exam conditions | Full or half mock exams |
The first two are input measures. They show effort and coverage. The last two are output measures. They show what you actually retain and can apply. Input measures can look fine while output measures are poor, so you need both.
Hours and modules: the pace metrics
Compute a cumulative gap, not a weekly one. Planned hours minus actual hours, summed from week 1, shows whether you are drifting. A single bad week costs little. Four weeks of small shortfalls add up to a gap you can't ignore. Do the same for modules: planned completions minus actual completions.
Hours and modules can disagree. If hours are on plan but modules are behind, you are spending time less efficiently than you estimated, perhaps because a topic is harder than expected. If modules are on plan but hours are short, you may be skimming. Treat either mismatch as a prompt to look at the practice results.
Practice accuracy: the quality metric
Log every practice session as three values: topic area, questions attempted and questions correct. Aggregate by topic area. Two cautions apply.
- Do not read accuracy from a small sample. Ten questions can swing 20 points on luck alone. Wait for roughly 30 or more attempts in a topic area before acting on its accuracy.
- Do not read accuracy from questions you have already seen. Repeated questions measure memory of the answer. Track first-attempt accuracy separately if your question bank allows it.
Mock exam scores: the calibration metric
A mock exam is the only measurement that combines coverage, accuracy and timing. Record the total score, the score per topic area, and the number of questions you did not finish. The CFA Institute does not publish a minimum passing score, so any target is a rule of thumb. Many candidates treat consistent scores around 70% on realistic mocks as comfortable and treat results below that as a warning. Use that as a planning heuristic, not a promise. Watch the trend across mocks more than any single score.
An error log beats a score
Percentages say where you are weak. They don't say why. Keep an error log, which can be a spreadsheet with one row per wrong answer. Use four columns: topic area and module, the question's concept, the cause, and the fix. Classify each cause as one of these:
- Knowledge gap: you did not know the concept.
- Calculation slip: you knew the method but made an arithmetic or calculator error.
- Misread question: you answered a different question from the one asked.
- Time pressure: you guessed or rushed.
The mix of causes decides the remedy. Knowledge gaps call for re-reading and more practice on that module. Calculation slips call for calculator drills. Misreads and time pressure call for timed practice. Spending more hours on a topic does not fix a misreading habit.
A small tracker in Python
This optional script computes the cumulative hour and module gaps and flags topic areas with enough attempts and low accuracy. The data is illustrative. Replace it with your own log.
from collections import defaultdict
planned_hours = [10, 10, 10, 10]
actual_hours = [10, 8, 6, 9]
modules_planned = [4, 4, 4, 4]
modules_done = [4, 3, 3, 4]
# (topic area, questions attempted, questions correct) per session
sessions = [
("Quantitative Methods", 20, 12),
("Quantitative Methods", 25, 15),
("Economics", 30, 24),
("Financial Statement Analysis", 15, 9),
("Financial Statement Analysis", 20, 14),
]
MIN_ATTEMPTS = 30
ACCURACY_TARGET = 0.70
def accuracy_by_topic(sessions):
totals = defaultdict(lambda: [0, 0])
for topic, attempted, correct in sessions:
totals[topic][0] += attempted
totals[topic][1] += correct
return {t: (a, c / a) for t, (a, c) in totals.items()}
hour_gap = sum(planned_hours) - sum(actual_hours)
module_gap = sum(modules_planned) - sum(modules_done)
print(f"Hours behind plan: {hour_gap}")
print(f"Modules behind plan: {module_gap}")
for topic, (attempted, acc) in accuracy_by_topic(sessions).items():
if attempted < MIN_ATTEMPTS:
status = "too few attempts to judge"
elif acc < ACCURACY_TARGET:
status = "WEAK: add time"
else:
status = "on track"
print(f"{topic}: {acc:.0%} over {attempted} questions, {status}")With this data, the script reports 7 hours and 2 modules behind. Quantitative Methods is flagged weak at 60% over 45 questions. Economics has only 30 attempts, which meets the minimum, and its 80% passes. Financial Statement Analysis has 35 attempts at 66%, so it is also flagged. The thresholds are parameters you should set to suit yourself.
The weekly review
Pick a fixed 15-to-20-minute slot at the end of each week. Update the log, compute the four metrics, and run the decision loop below. Do this at the same time each week so that it becomes routine and does not depend on how the week went.
Deciding how much to adjust
Match the size of the response to the size of the problem. Making large changes for small deviations wastes effort and makes the plan unstable. Ignoring large deviations ends in a failed exam sitting.
Small gap: absorb it
If you are behind by less than about a week of study hours, move the missed sessions into your scheduled buffer. This is what buffers are for. Note which buffer you used so you know how much remains.
Medium gap: reallocate
If the gap is larger than your remaining buffer, or one topic area is clearly weak, change the allocation. Take hours from the topic areas where your accuracy is comfortably above target and give them to the weak ones. Keep the exam weights in view. A weak area worth 6.5% of the exam deserves less rescue effort than a weak area worth 17.5%. Check that the weak result reflects a gap in knowledge, using the error log, before adding hours.
Large gap: reduce scope or move the date
If the gap exceeds what reallocation can recover, you have three options.
- Raise your weekly hours, but only if the extra hours are realistic given work and family commitments. A plan that requires a pace you cannot sustain will fail again.
- Reduce the depth of low-weight, low-difficulty modules and spend that time on the heavy-weight areas.
- Move to a later exam sitting. This is a legitimate choice, with costs: a new registration fee and a longer wait. Check the current deadlines, fees and rescheduling rules with the CFA Institute before deciding.
Common failure modes
- Tracking effort without outcomes. Logging 10 hours a week feels productive, but if accuracy stays flat, the hours are not working. Watch the output metrics.
- Over-instrumenting. A tracker that takes 45 minutes to update will be abandoned in week three. Keep it minimal.
- Reacting to one data point. A single low quiz score or one bad mock is noise. Wait for a pattern across two or three measurements.
- Chasing the weakest topic forever. If you pour hours into one area while others decay, your total score can fall. Rebalance each week and use spaced review to keep stronger areas warm.
- Letting the plan go stale. If you adjust in your head but not on the calendar, the next review compares you to a plan that no longer exists. Always write the change down.
- Moving only the end date's pressure. Shifting every missed session later pushes the whole backlog into the final weeks, where it collides with mock exams. Resolve gaps as they appear.
What a revised plan should look like
After an adjustment, the calendar should still satisfy the constraints you set at the start. Check each one:
- Total remaining hours cover the remaining modules with practice attached to each.
- At least some buffer remains before the final review block.
- Mock exams still fall at planned intervals, with time after each one to review errors.
- The final weeks are untouched by the backlog.
If you can't meet all four, go back to the large-gap options above.
Exercise
After eight weeks, you are 12 hours behind plan and 2 modules behind. Your remaining schedule has 6 hours of buffer. Accuracy in Fixed Income (12.5% weight) is 58% over 60 questions, while Derivatives (6.5% weight) is 82% over 40 questions. What is a reasonable adjustment?
Show answer
The gap of 12 hours exceeds the 6-hour buffer, so absorbing it is not enough. Use the buffer for part of it, then reallocate: take some hours from Derivatives, which is above target and has a low weight, and add them to Fixed Income, which is clearly weak on a sample large enough to trust. Check the error log first to confirm Fixed Income errors are knowledge gaps and not slips. If the remaining gap still can't be recovered, reduce depth on low-weight modules and, as a last resort, consider a later sitting. Do not remove practice or review sessions to make up the time.
Exercise
Your first mock exam scores 64% overall, but you left 14 questions unanswered because you ran out of time. How should this change your plan?
Show answer
The score is partly a timing problem, not only a knowledge problem, so add timed practice sets (for example, blocks of questions with a per-question time target) before the next mock, and log time-pressure errors separately in the error log. Also review the per-topic scores and the knowledge-gap errors to reallocate hours. Repeat a mock after those changes and compare the trend, rather than judging from one result.