Sub topic 11
Run and Monitor the Pilot
Assume you understand cycle time, defects, throughput, mean, and variation. You also have a defined process and a baseline period for comparison. This chapter focuses on operating the pilot so that the data remains trustworthy and problems are caught early.
Start with a controlled launch
Before the first pilot transaction, confirm:
- The pilot scope, start date, and end date.
- Which people, shifts, products, or locations use the changed process.
- Which cases remain on the current process.
- The data fields that every case must record.
- The person responsible for daily review.
- The guardrails that can trigger a pause or rollback.
Train the pilot group with realistic examples. Ask participants to perform the changed steps, not merely attend a presentation. Record questions and exceptions. An exception is a case that does not follow the normal pilot path, such as an urgent order or an unavailable system.
Use a short readiness check before launch:
| Check | Evidence |
|---|---|
| Staff can follow the new steps | Observed practice or checklist |
| Required data is captured | Completed test records |
| Rollback is understood | Named owner and written steps |
Monitor the process, not only the outcome
A good monitoring plan uses three kinds of measures:
- Outcome measures show whether the change achieves its purpose. Examples include cycle time and throughput.
- Process measures show whether the new method is being followed. Examples include completion of a required approval or use of a new form.
- Guardrail measures show whether the change creates unacceptable harm. Examples include defect rate, safety incidents, rework, or customer complaints.
Review process and guardrail measures frequently enough to respond before the pilot ends. Review outcome measures on an agreed schedule, because daily values can vary naturally.
flowchart TD
A[Collect pilot data] --> B[Check completeness and definitions]
B --> C[Review process and guardrail measures]
C --> D{Any guardrail breach?}
D -->|Yes| E[Pause or roll back]
D -->|No| F[Review outcome trend]
F --> G{Unexpected issue?}
G -->|Yes| H[Investigate and document]
G -->|No| I[Continue pilot]
H --> I
I --> AUse a daily control routine
At each review, compare the current result with the baseline and the agreed limits. Do not change the success criteria because an early result is disappointing. Instead, record the result, its context, and the next action.
Check for:
- Missing, duplicated, or late records.
- Changes in case mix, staffing, demand, or technology.
- Deviations from the standard work.
- Outliers that need verification rather than automatic removal.
- Feedback from employees and customers.
A guardrail breach requires a predefined response. The response may be to pause new cases, contain affected work, investigate the cause, and restore the previous process. Document who made the decision, when it happened, which records were affected, and whether the rollback worked.
def decide(improvement, target, defect_rate, defect_limit):
if defect_rate > defect_limit:
return "stop"
if improvement >= target:
return "go"
return "adjust"
print(decide(0.15, 0.10, 0.02, 0.03))The example treats a guardrail as more important than the target improvement. A pilot that is faster but unsafe or unreliable should not proceed.
Keep an evidence log
Maintain one log for decisions, deviations, incidents, training issues, and data corrections. Link each entry to the affected date, shift, case, or measure. This log helps distinguish a process problem from a measurement problem and gives the final analysis a traceable history.
Exercise
The pilot reduces cycle time, but the defect rate exceeds its guardrail for two consecutive reviews. What should the team do?
Show answer
Pause or roll back according to the predefined plan, investigate the breach, and document the decision. Do not continue solely because cycle time improved.