Sub topic 3
Testing Periods and Deemed Acceptance
This chapter assumes you know the basic offer, acceptance, and consideration structure of a contract, and that you can follow terms such as supplier, customer, and deliverable.
Testing periods and deemed acceptance
An acceptance clause gives the customer a testing period. During that window, the customer checks the deliverable against the written specifications. If the customer sends no notice of failure before the period ends, the clause treats the deliverable as accepted. This is deemed acceptance.
Acceptance. Customer has ten (10) business days after delivery to test the Deliverable against the Specifications. If Customer gives no written notice of failure within that period, the Deliverable is deemed accepted.Three details decide whether this works. The period must have a clear start, usually delivery. It must count business days or calendar days, and say which. The notice must be in writing and must describe the failure against the specifications.
Rejection, cure rights, and remedies
If the customer gives timely written notice, the supplier usually receives a cure period to fix the defect and redeliver. The clause should state the cure period length and what happens if the second delivery also fails. Many contracts leave "material failure" undefined, and that gap is a common source of disputes.
How payment, delivery, and acceptance fit together
Payment often depends on acceptance. If payment is due thirty days after acceptance, a long testing period delays the supplier's cash. An unclear delivery date also makes the testing period unclear, because the clock starts at delivery. Risk of loss and transfer of title may pass at a different moment from acceptance, so the customer can hold goods it has not yet accepted.
What changes with governing law and contract type
Rules differ by jurisdiction. Some legal systems imply a reasonable inspection period even when the contract is silent. Consumer contracts often contain mandatory rules that override the clause. Software, construction, and goods sales each follow their own customs.
A drafting and review checklist
- Define delivery precisely, including place and date.
- State the testing period in business or calendar days, and say when it starts.
- Tie acceptance criteria to written, objective specifications.
- Require written notice, with a delivery method and address.
- Set a cure period and state what happens after a second failure.
- Link payment timing to acceptance explicitly.
- Check the governing law for mandatory rules.
Exercise
A contract deems the deliverable accepted if the customer gives no notice within 10 business days after delivery. Delivery happens on Friday, 2 October. The customer emails a rejection on Monday, 19 October. Is the rejection timely? Assume no public holidays fall in the period.
Show answer
Count business days starting Monday, 5 October. The tenth business day is Friday, 16 October. The rejection on Monday, 19 October is late, so the deliverable is deemed accepted.