Sub topic 11
Setting review frequency by risk tier
This chapter assumes you know what a customer risk rating is, what a periodic KYC review is for, and basic Python. It covers how an institution turns a risk tier into a review schedule and where that schedule goes wrong.
Why frequency follows risk
A risk-based approach puts more effort where the risk is higher. For periodic review, that means high-risk customers are refreshed more often than low-risk ones. The risk rating is the input. The review cadence is the output.
Regulators generally do not fix a single interval. Each institution sets its cadence in policy and must be able to justify it. The intervals below are examples only.
| Risk tier | Example interval |
|---|---|
| High | Every 1 year |
| Medium | Every 3 years |
| Low | Every 5 years |
Computing the next review date
The next review date is the date of the last completed review plus the interval for the customer's current tier. The function below also handles an edge case. If the last review was on 29 February and the target year is not a leap year, replace raises ValueError, so the code falls back to 28 February.
from datetime import date
# Example intervals only. Each institution sets its own cadence in policy.
REVIEW_INTERVAL_YEARS = {"high": 1, "medium": 3, "low": 5}
def add_years(d: date, years: int) -> date:
try:
return d.replace(year=d.year + years)
except ValueError: # 29 February in a non-leap target year
return d.replace(year=d.year + years, day=28)
def next_review_date(last_review: date, risk_tier: str) -> date:
return add_years(last_review, REVIEW_INTERVAL_YEARS[risk_tier])
def is_review_due(last_review: date, risk_tier: str, today: date) -> bool:
return today >= next_review_date(last_review, risk_tier)
print(next_review_date(date(2024, 2, 29), "low")) # 2029-02-28
print(is_review_due(date(2023, 6, 1), "high", date(2026, 11, 27))) # TrueThe second call prints True. A high-risk customer last reviewed in June 2023 was due in June 2024, so the review is well overdue.
Common errors
- Counting from the wrong date. Use the date the last review was completed, not the onboarding date or the date it was started.
- Not recalculating after a rating change. If a customer moves from low to high risk, the old five-year date no longer applies. Recompute it from the new tier.
- Treating the schedule as the only trigger. A fixed date does not catch a sanctions match or an ownership change. Event-driven reviews override the calendar, which the next chapter covers.
- Letting overdue reviews pile up. A backlog is a control failure. Track overdue counts by tier and give high-risk cases priority.
- Copying example intervals. Your policy must reflect your own customer base and risk assessment, and the intervals must be applied as written.
Exercise
A customer rated medium risk was last reviewed on 29 February 2024. Using the example intervals, what is the next review date? Then the customer is re-rated high risk on 1 March 2025. What should happen to the schedule?
Show answer
Medium risk gives 3 years, so the next date is 28 February 2027 (2027 is not a leap year, so the code falls back to 28 February). After the re-rating to high risk, the interval becomes 1 year. The review date should be recalculated from the last review date, 29 February 2024, which gives 28 February 2025. That date has already passed, so the review is overdue and should be done promptly, not deferred to a later cycle.