Sub topic 3
Fiscal year ends and the annual timeline
This chapter assumes you know basic Excel formulas, relative and absolute references, SUMIFS, and the YEAR, MONTH and MOD functions. It builds on the monthly timeline from the previous chapter, where row 6 holds month-end dates and row 9 holds each month's fiscal year-end date.
Fiscal year ends and the annual timeline
Put the fiscal year-end month number in an input cell, for example C3 = 6 for a June year-end. Row 9 then gives each month's fiscal year-end date:
Row 9 (fiscal year end): D9: =EOMONTH(D6,MOD($C$3-MONTH(D6),12))
Row 10 (fiscal year): D10: =YEAR(D9)The MOD term counts the months from the period end to the next fiscal year-end month. EOMONTH then lands on that date. A period ending 31-Jan-2025 with a June year-end returns 30-Jun-2025, so its fiscal year is 2025.
Rolling monthly figures up to annual totals
Set the first annual header from the model start date, then step forward 12 months at a time:
Annual header (row 14): D14: =EOMONTH(C2,MOD($C$3-MONTH(C2),12)) E14: =EOMONTH(D14,12)
Annual revenue (row 15): D15: =SUMIFS($D$20:$AM$20,$D$9:$AM$9,D$14)SUMIFS adds each monthly value whose fiscal year-end matches the annual header. Because the match uses dates, not labels, the totals stay correct if the year-end month changes.
Dated events: payments, anniversaries and maturities
For events that happen on a set day each month, calculate every date from the original anchor with EDATE. Do not chain EDATE from the previous date, because a clamped day can carry forward.
Inputs: C4 = loan drawdown date (31-Jan-2025)
Payment date for period n (n in row 8): =EDATE($C$4,D8)Period 1 returns 28-Feb-2025, and period 2 returns 31-Mar-2025. Period 2 returns 31 March because it counts from 31 January, not from 28 February.
Mid-month start dates and stub periods
If the model starts on 15-Jan-2025, the first period starts on 1-Jan because row 5 uses the first of the month. The first column should count only the days after the start date:
D7: =D6-MAX(D5,$C$2)+1This returns 17 days for January. Later columns keep the normal day count.
Checks that catch broken timelines
Add these checks below the timeline:
Continuity (row 11): E11: =E5-D6 -> must equal 1
Month end (row 12): D12: =D6=EOMONTH(D6,0) -> must be TRUE
Annual tie-out: =SUM(D20:AM20)-SUM(D15:H15) -> must be 0Exercise
With C3 = 3 (March year-end) and a period end of 15-Nov-2025, what does row 9 return?
Show answer
31-Mar-2026. MOD(3-11,12) = 4, so EOMONTH adds 4 months to 30-Nov-2025 and returns 31-Mar-2026.