Sub topic 8
Raw materials and work in progress
This chapter assumes you can compute NRV for a finished item (selling price less costs to complete and costs to sell) and that you know the lower of cost and NRV rule from the previous chapters. Here you apply the rule to inventory that is not yet ready for sale.
Why materials need a different test
Raw materials are not sold as they are. They are consumed in production, so their own selling price is usually irrelevant. What matters is whether the finished goods they go into will sell for more than they cost.
IAS 2 therefore uses the following rule:
- If the finished goods are expected to sell at or above cost, the materials are not written down, even if the market price of the materials has fallen.
- If a fall in material prices suggests the finished goods' cost will exceed their NRV, the materials are written down to NRV.
- In that second case, the current replacement cost of the materials may be the best available measure of their NRV.
The test therefore runs through the finished product. You ask whether the product is still profitable, and you look at the material price only if it is not.
Work in progress
Work in progress (WIP) is partly finished. Its NRV is computed like a finished item's, with one extra deduction: the costs still needed to complete it.
NRV of WIP = expected selling price of the finished product − costs to complete − costs to sell
Compare this with the WIP's cost so far. Suppose WIP has accumulated cost of 60 per unit, 25 more is needed to finish it, and 10 is needed to sell it. If the expected price is 100, NRV is 65 and WIP stays at 60. If the expected price falls to 80, NRV is 45 and WIP is written down by 15 per unit.
| Item | Compared against | Deductions from expected price |
|---|---|---|
| Finished goods | Cost of the goods | Costs to sell |
| Work in progress | Cost incurred so far | Costs to complete and costs to sell |
| Raw materials | Cost of the materials | Tested through the finished product; written down only if its NRV falls below cost |
Worked example: materials
A manufacturer holds materials costing 30 per unit of finished product. Converting them into a finished unit costs a further 20, so total cost is 50. Selling costs are 5 per unit.
def material_carrying(material_cost, conversion_cost, price, selling_cost):
finished_cost = material_cost + conversion_cost
finished_nrv = price - selling_cost
if finished_nrv >= finished_cost:
return material_cost # product still profitable, so no write-down
# Otherwise the materials' NRV is what is left after conversion.
return min(material_cost, finished_nrv - conversion_cost)
for price in (70.0, 48.0):
carrying = material_carrying(30.0, 20.0, price, 5.0)
print("price", price, "carry materials at", carrying)
# price 70.0 carry materials at 30.0
# price 48.0 carry materials at 23.0At a price of 70, finished NRV is 65, which exceeds the cost of 50, so the materials stay at 30. At 48, finished NRV is 43, which is below 50. The materials' implied NRV is 43 − 20 = 23, so they are written down by 7 per unit.
If the supplier's current price for the same materials is 24, that replacement cost is evidence you can weigh against 23. Choose the figure you can support, and document why.
Common errors
- Forgetting costs to complete. Comparing WIP's cost with the finished selling price less only selling costs overstates NRV.
- Testing materials in isolation. The test must go through the products that will use them.
- Mixing units. Keep cost, price and quantities on the same basis (per kg, or per finished unit) before comparing.
- Ignoring committed contracts. If materials are held for a sales contract at a fixed price, use that price in the finished product's NRV.
Exercise
A firm holds materials that cost 12 per kg. Each finished unit uses 3 kg and needs 18 of further conversion cost. The expected selling price is now 50 per unit, with selling costs of 4 per unit. The materials in stock are enough for 1,000 units. What is the write-down, and at what amount per unit are the materials carried?
Show answer
Finished cost per unit is 3 × 12 + 18 = 54. Finished NRV is 50 − 4 = 46, which is below 54, so the materials must be tested. Their NRV per unit is 46 − 18 = 28, against a material cost of 36. The write-down is 8 per unit, so 8 × 1,000 = 8,000. The materials are carried at 28 per unit of finished product, which is 9.33 per kg.