Sub topic 6
Exclusive remedies, service credits and claim time limits
This chapter assumes you can read a commercial services or software contract. It also assumes you know what breach of contract is and that damages are the usual remedy. It builds on the idea of a limitation clause as a set of building blocks. Caps and loss exclusions limit how much a party can recover. The tools in this chapter limit which remedy a party can use and when it must use it. This is general legal education, not legal advice, and the rules vary by jurisdiction.
Three tools that shape the claim, not the amount
A cap answers the question "how much?" An exclusion of loss answers "what kind of loss?" This chapter covers three tools that answer different questions.
| Tool | Question it answers | Typical effect |
|---|---|---|
| Exclusive remedy clause | Which remedy can the customer use? | Replaces the general right to sue for damages with a defined remedy |
| Service credit regime | What does the customer get for poor performance? | Gives a fixed price reduction or credit for missed service levels |
| Claim time limit | By when must a claim be made? | Bars or shortens the right to claim after a set period |
All three narrow the customer's options. A supplier uses them to make its exposure predictable. A customer should read them as carefully as it reads the cap, because they can remove a remedy before the cap is ever reached.
Exclusive remedy clauses
An exclusive remedy clause says that a stated remedy is the only remedy for a stated type of failure. Without such a clause, a customer who suffers a breach can usually choose among several remedies. These include damages, termination, specific performance and a price reduction. An exclusive remedy clause removes that choice.
A common example is a warranty clause. The supplier promises that its software will conform to its documentation. The clause then says that, if it does not, the supplier's only obligation is to repair or replace the software. The customer cannot claim damages for the defect unless the repair or replacement fails.
Points to check in this kind of clause:
- Scope. Does the exclusivity apply to one obligation, such as a warranty, or to the whole agreement? A narrow clause is easier to defend and easier to accept.
- Failure of the remedy. What happens if the supplier cannot repair the fault? A well-drafted clause provides a fallback. Examples are a refund, a right to terminate, or a return to the general damages rules. Without a fallback, the customer may be left with a remedy that does not work.
- Termination rights. Does the clause preserve the right to end the contract for serious breach? Customers often insist that it does.
- Other claims. Does the clause purport to cover claims in tort, such as negligence, as well as contract? Courts tend to require clear words before they read a clause as removing a remedy.
Courts generally read clauses that remove a right to damages strictly. If the clause is ambiguous, the ambiguity is usually resolved against the party relying on it. This point is covered in more detail in the chapter on how courts read limitation clauses.
Service credits
A service credit is a pre-agreed amount that the supplier gives the customer when it misses a service level. Cloud, hosting and managed service contracts use them often. The contract sets a measure, such as monthly availability of 99.9%, and a table of credits for missing it.
| Monthly availability | Credit (percentage of that month's fee) |
|---|---|
| 99.9% or above | 0% |
| 99.0% to below 99.9% | 10% |
| 95.0% to below 99.0% | 25% |
| Below 95.0% | 50% |
Credits do two jobs. They give the customer a simple remedy that needs no proof of loss. They also give the supplier a ceiling on its exposure for that failure. The second job depends on whether the credit is the exclusive remedy.
Is the credit exclusive?
This is the most important question about any service credit regime. There are two common positions.
- Credit as sole remedy. The credit is the customer's only remedy for the service level failure. The customer cannot claim damages for the same outage.
- Credit as a first step or an offset. The customer receives the credit and may also claim damages. Any credit paid is then deducted from the damages awarded, so the customer does not recover twice.
A clause for the second position might read as follows.
Service credits are a price adjustment reflecting the reduced value of the services. They are not an estimate of the loss the Customer may suffer. Payment of a service credit does not limit the Customer's right to claim damages for the same failure, but any service credit paid will be deducted from damages awarded for that failure.Treating credits as a price adjustment, not as compensation for loss, helps with a legal problem. A fixed sum payable on breach can be attacked as a penalty if it is out of proportion to the legitimate interest being protected. A price adjustment for reduced service is easier to defend as a commercial term than as a penalty. The detail of the penalty rule differs between jurisdictions.
Gaps to look for
- Claim procedure. Some regimes require the customer to claim the credit within a short period, sometimes 30 days. A missed deadline can mean no credit at all.
- Credits are applied to future invoices. If the contract ends, the credit may have no value. A customer should ask for payment of unused credits on termination.
- Exclusions from the measure. Scheduled maintenance, customer-caused faults and force majeure events are usually excluded from the availability calculation. Check how wide they are.
- Interaction with the cap. Does the credit count towards the aggregate cap? If it does, every credit paid reduces the room left for other claims.
- Chronic failure. A customer should ask for a right to terminate if service levels are missed repeatedly, for example in three months out of six. Credits alone do not help a customer that needs to leave.
Claim time limits
A contractual time limit sets a period within which a claim must be notified or started. After that, the claim is barred. Two forms are common.
- Notification period. The customer must tell the supplier about a problem within a set time, such as 30 days after it becomes aware of it.
- Claim period. The customer must start formal proceedings within a set time, such as 12 months after the event.
A notice requirement and a limitation period are different things. Statutes set default limitation periods for claims. In many jurisdictions the period for a contract claim is several years from the breach. Parties can often shorten the period by agreement, but the rules on how far they can go differ. Some systems control very short periods through reasonableness or unfair terms rules. Some do not allow the parties to extend the statutory period at all. Always check the local law before relying on a contractual limit.
Drafting issues with time limits
| Issue | Why it matters |
|---|---|
| When does the clock start? | The date of the breach, the date of discovery and the date of the loss can all differ. A clause that starts the clock on discovery favours the customer. |
| What counts as a claim? | A written notice may be enough, or the clause may require court or arbitration proceedings. |
| Latent defects | A short period can expire before a hidden defect appears. Customers often ask for longer periods for defects found later. |
| Carve-outs | Fraud and other uncapped liabilities should normally sit outside the time limit as well. |
| Mismatch with the cap period | A cap based on fees paid in the 12 months before the event is not a time limit. Do not confuse the look-back period with the claim period. |
How the three tools combine
The tools work in sequence. A customer with a claim usually meets them in this order.
The diagram is a simplification. In practice, carve-outs for death, personal injury and fraud sit outside all of these controls, and statutory tests can override any step. It shows why the order of review matters. A customer that misses a notification period never gets as far as the cap.
A worked example
A customer buys hosted payroll software. The contract has these terms:
- Monthly availability target of 99.9%, with the credit table shown above.
- Credits are the sole remedy for availability failures.
- Defects in the software are remedied by repair or replacement within 30 days. If that fails, the customer may terminate and receive a refund of prepaid fees.
- Claims must be notified within 60 days of the customer becoming aware of the event.
In March, the service is available for 98.2% of the month, and the customer cannot run payroll on the last working day. Employees are paid late, and the customer pays interest and compensation to them.
The customer should work through the following steps.
- Check the time limit. It must notify the supplier within 60 days of becoming aware. It should send a written notice at once.
- Identify the remedy. Availability of 98.2% falls in the 25% credit band. Because credits are the sole remedy for availability failures, the late payment costs may not be recoverable in damages.
- Look for exceptions. Did the outage come from a software defect rather than from availability? If so, the repair and refund route applies, not the credit table. Characterisation of the failure can decide which clause applies, so the facts matter.
- Check for a breach of another obligation. If the supplier also failed to give prompt notice of the outage, a separate breach may fall outside the credit regime. The claim would then be subject to the exclusions and the cap.
The example shows that the dispute is often about which clause governs the failure, before any question of amount arises.
Common errors
- Assuming a service credit is compensation. It is usually a price adjustment, and the contract should say whether it is exclusive.
- Missing a notification deadline because the clause sits in a schedule, not in the main liability clause. Read the service level schedule as part of the review.
- Treating a short contractual time limit as always valid. Reasonableness and unfair terms rules, and mandatory limitation rules, may restrict it.
- Failing to give a fallback when the exclusive remedy fails, which can leave the customer with no effective remedy and invite a challenge to the clause.
- Forgetting that a credit paid may count towards the cap.
Exercise
A hosting contract says service credits are the customer's "sole and exclusive remedy" for failure to meet the availability target. It also says the customer must claim a credit within 30 days of the end of the month in which the failure occurred. A two-day outage in May causes the customer to lose a large order. The customer notices the outage straight away but sends a claim on 15 July. What are the customer's problems, and what changes would you ask for in the contract?
Show answer
There are two problems. First, the claim for the credit is late. The 30-day period ran from 31 May and ended on 30 June, so the supplier may refuse even the credit. Second, because credits are the sole remedy, the customer probably cannot claim damages for the lost order, however large. Changes to ask for: make credits a non-exclusive price adjustment that is deducted from any damages; allow damages for serious or repeated failures; lengthen the claim period or start it from the date the customer could reasonably know of the failure; and add a right to terminate for chronic failure. A fallback should also apply if the credit regime does not give a real remedy.