Surfacing Risks Early with a Pre-mortem
Assume you already know how to set a project goal, identify priorities, and track work. This chapter focuses on one technique: a pre-mortem. A pre-mortem is a structured discussion that asks a team to imagine that a project has failed, then work backward to find likely causes.
A normal post-mortem happens after an event. A pre-mortem happens before the outcome is known. The purpose is not to predict the future perfectly. It is to make hidden concerns safe to discuss while the team still has time to respond.
Why pre-mortems help
Teams often notice risks but do not raise them. Someone may worry that a dependency will be late, that a requirement is unclear, or that the schedule leaves no time for testing. They may stay quiet because they do not want to seem negative or challenge a senior person.
The pre-mortem changes the question from “Who thinks this plan is bad?” to “Imagine this plan failed. What might have caused it?” This framing gives people permission to describe problems without claiming that failure is certain.
A useful risk statement includes:
- The possible event.
- The condition that could cause it.
- The effect on the project.
- A signal that would show the risk is becoming more likely.
For example:
| Risk statement | Early signal | Possible response |
|---|---|---|
| The payment provider delays approval, so launch slips by two weeks. | Approval has not started by Friday. | Confirm the review owner and prepare a test account. |
Run the pre-mortem
Set aside about an hour with the people who understand the work, its dependencies, and its users. Include enough seniority to make decisions, but do not let the most senior person speak first.
# Pre-mortem
Imagine it is <date> and this project has failed.
1. Each person privately writes the reasons it failed.
2. Collect and group the reasons.
3. For the top risks, decide: prevent, prepare a response, or accept.
4. Assign an owner and a check-in date for each risk we act on.Start by stating the scenario and the constraints. For example: “It is 30 June. The release missed its date and caused a serious customer problem.” Give participants several quiet minutes to write independently. Private writing prevents early comments from anchoring everyone's thinking.
Collect the risks without debating them immediately. Group similar items, such as dependencies, technical unknowns, staffing, compliance, and adoption. Then ask the group to rank them. A simple ranking considers likelihood and impact. Do not treat the ranking as a precise calculation. Its value is to make priorities visible.
For each high-priority risk, choose one response:
- Prevent: change the plan to lower the chance of occurrence.
- Prepare: define a fallback if the event occurs.
- Accept: record the risk and consciously decide not to spend effort on it.
Every action needs an owner and a date. “The team will monitor the dependency” is too vague. “Priya will confirm the provider's review date by Friday” can be checked.
Turn risks into experiments
Some risks are really unknowns. Instead of arguing about them, design a small experiment that produces evidence. If the team is unsure whether users can complete a new workflow, test it with a few representative users before building every feature.
Define the question, the smallest safe test, the time limit, and the result that would change the plan. A good experiment reduces uncertainty without creating a second large project.
Review the risk list during normal planning meetings. Check whether signals appeared, whether assumptions changed, and whether an action reduced exposure. Retire risks that no longer matter, and add new ones when circumstances change.
Exercise
A team lists “the launch may fail” as a risk but assigns no owner or action. What should you do next?
Show answer
Ask the team to describe the possible failure more specifically, identify an early signal, choose prevent, prepare, or accept, and assign an owner with a check-in date.