Sub topic 8
Surfacing risks early with a pre-mortem
This chapter assumes you have worked on at least one project where plans changed midway, and that you know the basics of planning: goals, priorities, and deadlines. It also assumes you have read the earlier chapters on kinds of uncertainty, psychological safety, and deciding with incomplete information. The pre-mortem builds on all three.
What a pre-mortem is
A pre-mortem is a short team exercise held before or early in a project. The team imagines that the project has already failed and then works backward to explain why. The name comes from the post-mortem, the review a team holds after a failure. A pre-mortem moves that review to a time when you can still change the outcome.
Psychologist Gary Klein popularized the method. It rests on a finding about prospective hindsight: people produce more, and more specific, reasons for an outcome when they treat it as already happened than when they are asked what might go wrong. "Might fail" invites vague worry. "Has failed" invites a story with causes.
Why it fits uncertainty
Under uncertainty, most teams have a gap between what individuals privately suspect and what the group says out loud. A team member may doubt a vendor's delivery date, a technical approach, or a stakeholder's commitment. Speaking up can feel like disloyalty or like being negative. Plans then proceed on shared optimism.
A pre-mortem narrows that gap in three ways:
- It makes doubt the assignment. Naming a risk is the task, not a sign of a bad attitude.
- It starts with private writing, so senior voices do not anchor the room.
- It converts vague unease into a list of causes that can be ranked and owned.
It does not remove uncertainty. It shows you which unknowns matter most, so you can choose a response to each. That links directly to the next chapter's theme, small experiments, which are the usual way to shrink a risk you cannot simply prevent.
Before the session
Preparation decides most of the value. Cover these points:
- Pick the right moment. Hold it after the plan has a shape but before commitments are hard to change. Running it the week before launch finds risks you can no longer afford to fix.
- Define the failure. Agree on one sentence for what "failed" means, for example "we missed the launch date by more than a month" or "customers adopted it and then stopped using it." Different failure definitions produce different risks.
- Invite the right people. Include the people who do the work, not only those who manage it. Add someone from a neighboring team if the project depends on them. Keep the group to about 5 to 10 people so every voice fits in an hour.
- Share a one-page summary of the plan. Everyone should be working from the same description of goals, scope, dates, and dependencies.
- Set the tone. Tell people in advance that you want disagreement and that raising a risk will not count against anyone.
Running the session
The agenda below fits in about an hour. Copy it, fill in the date, and adapt it.
# Pre-mortem
Imagine it is <date> and this project has failed.
1. Each person privately writes the reasons it failed.
2. Collect and group the reasons.
3. For the top risks, decide: prevent, prepare a response, or accept.
4. Assign an owner and a check-in date for each risk we act on.Here is how each step works in practice.
Step 1: Set the scene and write silently (10 minutes)
Read the failure statement aloud. Pick a date far enough ahead that the failure is believable, such as the planned end of the project. Then ask each person to write, alone and in silence, every reason they can think of for the failure. One reason per note works best, on paper or in a shared document where authors are hidden.
Silent writing matters. If people speak first, the most senior or most confident person sets the frame and others adjust to it. Writing alone gets independent views, including the quiet ones that tend to be right about technical details.
Phrase the prompt as a story: "It failed. What happened?" Encourage specifics. "Communication broke down" is weak. "The data team did not know we changed the schema, so their import failed in week 6" is useful.
Step 2: Collect and group (15 minutes)
Gather the notes and read them out or display them without names. Group similar items. Typical groups are people and capacity, technical approach, dependencies on other teams, requirements and stakeholders, and external events.
Do not debate yet. Ask only clarifying questions such as "What did you mean by that?" If a risk appears in several notes, that is a signal. If it appears once, do not discard it. A single note from the person closest to the work is often the most valuable.
Step 3: Rank (10 minutes)
Rank by two questions: how likely is this, and how bad is it if it happens? A quick method is for each person to place three votes on the risks they consider most worrying. You do not need numeric probabilities. A rough high, medium, or low for each question is enough, and false precision hides how little you know.
Pay attention to risks that are both unlikely and severe, and to risks that are hard to see coming. These tend to be under-voted.
Step 4: Choose a response (15 minutes)
For each top risk, pick one of three responses:
| Response | Meaning | Example |
|---|---|---|
| Prevent | Change the plan so the risk cannot happen or is much less likely | Add a second reviewer so one person leaving does not block releases |
| Prepare | Accept the risk may happen and decide now what you will do, and how you will notice it | Agree a fallback supplier and a date by which you switch |
| Accept | Do nothing, and say so deliberately | Minor delay in an optional feature |
"Accept" is a valid choice only when it is explicit and recorded. Unspoken acceptance is just ignoring the risk.
For "prepare," define a trigger: the observable event that tells you the risk is happening. A trigger such as "the vendor has not confirmed by the 15th" is something a person can check. "If things look bad" is not.
Step 5: Assign owners and check-in dates (10 minutes)
Every risk you act on gets one named owner and a date to report back. An owner is not necessarily the person who does all the work. They are the person responsible for noticing changes and raising them. A risk with no owner will not be handled.
A worked example
A team of seven plans to migrate a customer-facing service to a new database in three months. The leader runs a pre-mortem and defines failure as "the migration caused customer-visible downtime longer than one hour, or finished more than a month late."
Silent writing produces these notes, among others:
- "Only one engineer understands the legacy data format, and she is on leave in month two."
- "Load testing used synthetic data, so real traffic patterns surprised us."
- "The reporting team relies on a table we dropped, and nobody told them."
- "We assumed the vendor's migration tool handles our data volume. We never checked."
The group sorts these into capacity, testing, dependencies, and unverified assumptions. After voting, they act on four items:
| Risk | Response | Trigger or action | Owner | Check-in |
|---|---|---|---|---|
| Single point of knowledge on legacy format | Prevent | Pair a second engineer with her before month two and write a short format guide | Dana | Week 3 |
| Synthetic load tests miss real patterns | Prevent | Replay a sample of anonymized production traffic | Marcus | Week 6 |
| Reporting team depends on dropped table | Prepare | List downstream consumers; notify them by week 2; keep a compatibility view | Priya | Week 2 |
| Vendor tool may not handle data volume | Test | Run a small experiment on a 10% copy and measure time | Lee | Week 2 |
The last row shows the bridge to the next chapter. An unverified assumption is cheaper to test than to debate. The pre-mortem turned a silent worry into a small experiment with an owner and a date.
Recording the outcome
Record what you decided and when you will revisit it. The decision record template from the chapter on deciding with incomplete information works well for the larger choices that come out of a pre-mortem, such as changing scope or adding a dependency check.
# Decision record
- Decision: Run the vendor migration tool on a 10% copy before committing to the cutover plan
- Date: <date>
- Type: reversible
- What we know: The vendor documents support for our database version
- What we are assuming: The tool handles our data volume within the cutover window
- Why we decided now: A wrong assumption found in month 3 would delay the whole project
- Review trigger: Test results, due end of week 2
- Owner: LeeKeep the risk list somewhere visible, such as the project page, and review it in a regular meeting. A short standing item, "Any risks moved? Any new ones?", is enough. Your weekly uncertainty update can also list the top risks under "Known" and "Unknown."
Diagram: the pre-mortem flow
Common errors
- Running it too late. If scope, staffing, and dates are locked, the output is a list of complaints. Hold it while you can still change the plan.
- Letting the leader speak first. Your view anchors the group. Write your own notes with everyone else and share last.
- Skipping the private writing step. Open brainstorming favors the loudest people.
- Treating it as a blame session. Risks should name causes and conditions, not people. "Dana is unreliable" is not a risk. "Only one person knows the legacy format" is.
- Producing a list and stopping. Without owners, triggers, and dates, nothing changes. The list is the start of the work.
- Only listing external risks. Include risks from your own team's habits, such as unclear ownership or rushed reviews.
- Doing it once. Uncertainty changes as you learn. Repeat a shorter version at major milestones or when the plan shifts.
- Ignoring the mood. If the session turns gloomy, remind the group that finding a risk now is the purpose, and that each one you can act on makes the project safer.
When a pre-mortem is not enough
A pre-mortem finds risks that someone on the team can already imagine. It does not find unknown unknowns, the things nobody has thought of. For those, rely on short feedback loops and small experiments, which reveal surprises early. It also depends on psychological safety. If people do not believe their notes are safe, they will write only safe risks. In that case, work on trust first, using anonymous notes in the meantime.
Finally, a long list does not mean a safer project. Aim for a short list of risks you will act on, and accept that you will not address everything.
Exercise
Your team of six is starting a four-month project to replace a payment provider. You are the leader and you strongly believe the main risk is the provider's API quality. Describe how you would run the first 25 minutes of a pre-mortem so that your belief does not shape the results, and name one risk statement that is weak and a stronger rewrite.
Show answer
Open by defining failure in one sentence (for example, "payments failed for more than 1% of customers for a week after launch") and setting the scene as a date in the future. Ask everyone, including yourself, to write reasons privately for about 10 minutes, one per note, with no discussion. Collect the notes anonymously, then group them for about 15 minutes, asking only clarifying questions and keeping your own API concern as one note among the others rather than announcing it first. A weak statement is "Testing was poor." A stronger rewrite is "We tested only with sandbox accounts, so real card declines and refund edge cases failed in production." The stronger version names a cause, a condition, and a consequence, so someone can own it and design a check for it.
Exercise
A pre-mortem produced the risk "The finance team might change the approval process." Choose prevent, prepare, or accept, and give the trigger, the owner role, and the check-in you would set. Explain why you chose that response.
Show answer
Prepare is the most reasonable choice. You cannot prevent another team from changing its process, and the impact could be large enough that accepting it silently is risky. Set a trigger such as "finance announces or schedules a process review, or our approval step is not confirmed by week 4." Assign the person who works most closely with finance (for example the project coordinator) as owner, with a check-in at week 4 and again before the build phase ends. The prepared response could be to design the approval step as a replaceable module so a change costs days, not weeks. Accept would be defensible only if the cost of a change were small, and you would record that reasoning.
Exercise
Two weeks after a pre-mortem, the risk list has not been looked at and one risk has already happened without anyone noticing. Name two likely causes and one change that would prevent a repeat.
Show answer
Likely causes include no named owner for the risk, no observable trigger, and no recurring slot where the list is reviewed. Any two of these are correct. A fix is to add a standing item to the weekly meeting, "Any risks moved? Any new ones?", and to give each risk an owner and a trigger that a person can check, such as "vendor has not confirmed by the 15th." The owner reports status at that meeting even if nothing has changed.