Sub topic 7
Handling third-party claims: notice, defence and settlement
What this chapter covers and what it assumes
This chapter assumes you can already tell a warranty from an indemnity, and that you know an indemnity is triggered by a specified event rather than by proof of breach. Here we look at the machinery that usually sits beside a third-party indemnity: the claim procedure. This is the set of steps that says who must tell whom about a claim, who runs the defence, and who may settle.
The clauses are described as general common-law practice. Details vary by jurisdiction and by contract wording, so always read the actual text.
Why a procedure is needed
A third-party indemnity has a structural problem. The party who is sued (the indemnified party, for example the Customer) is not the party who will pay (the indemnifying party, for example the Supplier). That split creates three risks:
- The indemnifier may not hear of the claim until it is too late to influence it.
- The indemnified party may run up costs or settle on bad terms, knowing someone else pays.
- The indemnifier may take control of the defence and use it in a way that harms the indemnified party's business or reputation.
A claim procedure manages these risks. It gives the indemnifier early warning and a say in the outcome, and it gives the indemnified party protection against a defence conducted at its expense.
The procedure does not create the indemnity. It qualifies it. If the procedure is not followed, the indemnifier may argue that its liability is reduced or lost. That is why the details matter.
The three stages
Most procedures follow the same order: notice, control of the defence, and settlement.
Stage 1: Notice
The sample clause requires the Customer to "give the Supplier prompt written notice of any claim". Three drafting choices shape how this works.
- What counts as a claim. Does notice have to be given for a formal court claim only, or also for a letter of complaint, a demand, or a threat? Wider definitions protect the indemnifier but burden the indemnified party.
- How quickly. "Prompt" is vague. A fixed period, such as 10 business days, is clearer. Courts apply vague words like "prompt" by looking at the facts, so the result is harder to predict.
- What happens if notice is late. This is the most important choice, and the clause often leaves it unsaid.
There are two common positions on late notice:
| Approach | Effect of late notice | Who it favours |
|---|---|---|
| Condition precedent | Indemnity is lost if notice is not given on time | Indemnifier |
| Prejudice-based | Indemnity is reduced only to the extent the delay caused real harm | Indemnified party |
If the clause says nothing, the usual starting point is that late notice is a breach of the procedure. The indemnifier may then have to show that it suffered loss from the delay, but this depends on the wording and the jurisdiction. Do not rely on a default. A party who wants certainty should say which approach applies.
A good notice names the claim, attaches the documents received, and says which indemnity is relied on. Sending it to the address and person stated in the contract's notices clause avoids a separate argument about whether it was validly served.
Stage 2: Control of the defence
The sample clause lets the Supplier "conduct the defence and settlement" of the claim. This is often called a conduct-of-claims clause. Giving the indemnifier control is sensible, because it is paying and will want to keep the cost down. It also has a legal logic: an indemnifier who is allowed to control the defence is usually in a better position to be held to the outcome.
Points that a careful clause settles:
- Is control a right or a duty? The indemnifier may be allowed to take over, or may be required to. If it is only a right and it declines, the indemnified party defends and the indemnifier still pays covered costs.
- Must the indemnifier confirm the indemnity first? Some indemnified parties will not hand over control until the indemnifier admits that the claim falls within the indemnity. Otherwise the indemnifier could run the defence and later deny it has to pay.
- Choice of lawyers. The clause may require reasonably competent counsel, or counsel approved by the indemnified party.
- Cooperation. The indemnified party normally must give access to documents and witnesses at the indemnifier's cost. This is the other half of the bargain.
- Conflicts. If the claim also attacks the indemnified party in ways the indemnity does not cover, or if the two parties' interests diverge, the indemnified party may want to keep its own lawyers at its own cost.
- Reasonable conduct. An indemnifier in control should not let the claim drift or take steps that damage the indemnified party's business relationships. Many clauses say it must act diligently and keep the indemnified party informed.
Stage 3: Settlement
Settlement is where the interests of the two parties most often clash. The sample clause sets up consent rules in both directions:
- The Customer must not "admit liability or settle without the Supplier's prior written consent (not to be unreasonably withheld)".
- The Supplier must not settle "in a way that imposes non-monetary obligations on the Customer without the Customer's consent".
Each rule answers a particular worry.
The first protects the indemnifier. Without it, the indemnified party could agree a generous settlement and send the bill. An admission of liability can also destroy the indemnifier's defences, so admissions are restricted separately from settlement.
The second protects the indemnified party. A settlement that only requires payment costs the indemnified party nothing, because the indemnifier pays. A settlement that requires the Customer to stop using the Software, publish a statement, or accept a licence restriction affects its business. So the indemnifier may agree money alone, and anything more needs the Customer's consent.
The words "not to be unreasonably withheld" turn a veto into a standard. A party who refuses consent must have a reason that a reasonable person would accept. A refusal based on a better settlement being available, or on harm to the party's business, is easier to defend than a refusal based on preference.
If the indemnified party settles without the required consent, a common consequence is that the indemnifier is not bound by the settlement amount. It may have to pay only what it proves was a reasonable settlement, or nothing, depending on the clause.
A worked example
A Customer licenses Software from a Supplier under the sample indemnity. A third party, Brightline Ltd, writes to the Customer alleging that the Software infringes its patent and demanding payment.
- Notice. The Customer sends the Supplier written notice within a week, attaching the letter and stating that it relies on the infringement indemnity. This meets the "prompt" requirement under any reasonable reading.
- Control. The Supplier confirms the claim falls within the indemnity and takes over the defence. It appoints patent counsel. The Customer supplies documents showing how it uses the Software.
- Settlement proposal. Brightline offers to settle if the Supplier pays a lump sum and the Customer agrees to stop using one feature of the Software.
- Consent. The lump sum is a monetary term and the Supplier may agree it alone. The feature restriction is a non-monetary obligation on the Customer, so the Supplier needs the Customer's consent. The Customer may refuse if the feature is important to its business. The clause does not say its consent must not be unreasonably withheld, so the Customer is free to refuse. Notice that this asymmetry is a choice made in the draft. The Supplier might have asked for the same standard.
- Outcome. If no deal is reached, the claim continues under the Supplier's control, and the Supplier pays the covered loss, subject to any cap in the agreement.
Now change one fact. Suppose the Customer, worried about publicity, settles with Brightline directly for a payment, without telling the Supplier. The Supplier can refuse to pay. The Customer breached the no-settlement rule, and the Supplier lost its chance to defend. The Customer would then have to prove the settlement was reasonable in a separate argument, if the clause lets it try.
Interaction with caps and other limits
The procedure sits inside the rest of the contract. Defence costs are usually part of the "losses, liabilities, damages, costs and expenses" that the indemnity covers, so they may count towards any liability cap. Check whether a cap applies to the indemnity, and whether defence costs are inside it or on top of it. The next chapter covers caps, baskets and carve-outs in more detail.
Common errors
- No procedure at all. The indemnified party can then settle freely, and the indemnifier will argue that the settlement was unreasonable. Both sides lose certainty.
- A procedure that only binds one side. If only the indemnified party has duties, the indemnifier has little incentive to defend well.
- "Prompt" with no consequence. The clause demands speed but never says what late notice costs.
- Silence on admissions. A casual statement to the claimant, such as an apology, may count as an admission of liability.
- Using the procedure for first-party claims. A notice-and-defence procedure fits claims by outsiders. It does not suit a loss the indemnified party suffers directly, such as damage to its own goods, where no third party exists to defend against.
- Ignoring insurance. An insurer of either party may have its own notice and consent conditions. A clause that conflicts with them can put cover at risk.
Summary of the key points
- A claim procedure gives the indemnifier early warning and a voice, and protects the indemnified party from an abusive defence.
- Notice terms should define what a claim is, set a deadline, and state the effect of delay.
- Control of the defence should settle whether it is a right or a duty, the standard of conduct, and cooperation.
- Settlement clauses restrict admissions and require consent, usually from both sides in different circumstances.
- Breaking the procedure can reduce or remove the indemnity, so follow it exactly.
Exercise
A Supplier gives the Customer the infringement indemnity shown in this chapter. The Customer receives a demand letter from a third party, waits two months, and then agrees a payment with the third party without telling the Supplier. The Customer then asks the Supplier to pay. Identify two procedural problems with the Customer's conduct and one argument the Customer might still make.
Show answer
First, the Customer did not give prompt written notice; two months is unlikely to be prompt. Second, it settled without the Supplier's prior written consent, and it removed the Supplier's chance to conduct the defence. The Customer might still argue that the settlement was reasonable and that the Supplier suffered no prejudice from the delay, for example because the claim was clearly valid and the amount was fair. Whether that argument works depends on whether the clause makes notice and consent conditions precedent or only breaches that must cause real harm.
Exercise
Why does the sample clause allow the Supplier to settle for money alone but require the Customer's consent for any settlement with non-monetary obligations?
Show answer
A money-only settlement costs the Customer nothing, because the Supplier pays it. A settlement that restricts the Customer's use of the Software, requires a public statement, or imposes other obligations affects the Customer's business, so the Customer must have a say.