Allocating the Transaction Price to Performance Obligations
Assume you know the five-step revenue model, accrual accounting, and basic percentage calculations. This chapter focuses on step 4: allocating the transaction price after identifying the performance obligations.
Allocating the price using relative standalone selling prices
A standalone selling price (SSP) is the price a customer would pay for a promised good or service separately. Allocate the transaction price in proportion to each obligation’s SSP:
\[ \text{Allocation} = \text{Transaction price} \times \frac{\text{Obligation's SSP}}{\text{Total SSPs}} \]
from decimal import Decimal
price = Decimal("100000")
ssps = {
"license": Decimal("60000"),
"implementation": Decimal("30000"),
"support": Decimal("30000"),
}
total_ssp = sum(ssps.values())
allocation = {
item: price * ssp / total_ssp
for item, ssp in ssps.items()
}
print(allocation)The $100,000 price is allocated as $50,000 to the license, $25,000 to implementation, and $25,000 to support.
Estimate SSP using observable prices when available. Otherwise, use an adjusted market assessment, expected cost plus a margin, or the residual approach. The residual approach is permitted only when the price is highly variable or uncertain and the other SSPs are observable.
When a discount belongs to specific obligations
Normally, a bundle discount is allocated across all obligations using relative SSPs. Allocate the discount only to specific obligations when evidence shows that:
- those obligations are regularly sold at a discount;
- the discount relates directly to them; and
- allocating it there faithfully represents the arrangement.
Allocating variable consideration to part of a contract
Variable consideration, such as a bonus or usage fee, may be allocated entirely to one obligation when its terms relate specifically to that obligation and the allocation matches the contract’s economics. Otherwise, allocate it across all obligations using relative SSPs. Apply the constraint so that recognized revenue is not likely to reverse later.
Changes in the transaction price
When the transaction price changes after inception, allocate the change using the original allocation basis unless the change relates specifically to one obligation. Recognize the resulting amount as a cumulative catch-up, prospectively, or through a contract modification analysis, depending on whether the related obligations have already been satisfied and whether the modification creates a separate contract.
Worked software-bundle example
A customer pays $100,000 for a license, implementation, and one year of support. Their SSPs are $60,000, $30,000, and $30,000. The total SSP is $120,000, so the relative allocations are $50,000, $25,000, and $25,000. Recognize license revenue when control transfers, implementation revenue as that service is performed, and support revenue over the year.
Exercise
What amount of a $100,000 transaction price is allocated to an obligation with an SSP of $40,000 when total SSPs are $80,000?
Show answer
$50,000, calculated as $100,000 × ($40,000 ÷ $80,000).