Deciding How Much Historical Data to Bring
Assume you know SAP ERP modules, enterprise system landscapes, custom ABAP code, and the difference between master data and transactional data. This chapter focuses on data scope after choosing a transition direction.
Historical Data Scope
A project does not always need to move every old document into S/4HANA. Separate data into:
- Open transactions: Items that still require processing, such as unpaid invoices or open purchase orders.
- Required history: Older data needed for audits, legal retention, reporting, or customer service.
- Reference history: Data that users may occasionally inspect but do not need in the new system.
- Obsolete data: Data that can remain archived or be deleted according to policy.
Moving less history can reduce migration effort, testing, storage, and cutover time. Keeping history available in the new system can simplify reporting and user access. The decision must include legal retention rules and the cost of operating an archive.
Selective Data Transition: Combining Both Worlds
Selective data transition moves chosen organizational units, periods, or data objects into a new S/4HANA system. It can preserve useful parts of the existing design while allowing process changes and data cleansing.
This approach is useful when a company wants a new organizational structure but must retain selected business history. It usually requires careful mapping, reconciliation, and tooling that supports selective extraction.
Clean Core and Extensibility
A clean core keeps the S/4HANA standard as unchanged as possible. Replace unnecessary modifications with configuration, released extension points, or side-by-side applications. Historical data decisions should not justify carrying obsolete custom code into the target system.
Running the Project with SAP Activate
SAP Activate organizes work into phases such as Discover, Prepare, Explore, Realize, Deploy, and Run. During Explore, teams confirm process and data requirements. During Realize, they build migration objects, test mappings, and perform trial loads. Several mock cutovers should validate timing and reconciliation.
Cutover Planning, Downtime, and Risk
Cutover is the controlled switch to production. Freeze transactions, complete the final extraction, load and reconcile data, run technical checks, and release the system to users. More history usually means more extraction, validation, and downtime. Archiving or preloading historical data can reduce the final outage.
Choosing a Path
Compare each path against these criteria:
| Criterion | Greenfield | Brownfield | Selective transition |
|---|---|---|---|
| Historical data | Redefined scope | Broadly retained | Chosen subsets |
| Process change | Highest | Lowest | Medium |
| Data cleansing | Highest | Medium | High for selected data |
| Cutover complexity | Medium | High | High |
Exercise
A company wants redesigned processes, must retain seven years of invoices, and has limited tolerance for production downtime. What should the team investigate first?
Show answer
Investigate selective transition or a greenfield implementation with archived history, then test preload and archive options through mock cutovers.