Sub topic 4
Building a Mutual Action Plan with Dates and Owners
What this chapter assumes
This chapter assumes you know the basics of a B2B sales cycle (discovery, evaluation, proposal). It also assumes you know what a commercial contract is and who reviews a deal on the buyer's side. The previous chapter covered how to find out the buyer's real review process. Here you turn that knowledge into a shared document that both sides use to run the deal.
A mutual action plan (MAP) is a dated list of the steps between a verbal yes and signature. Each step has one named owner, and the buyer sees and agrees to the plan. It is not an internal seller checklist. The word "mutual" matters because most steps after the verbal yes are done by people who work for the buyer.
Why a mutual plan beats a seller-only plan
Without a shared plan, the seller guesses when security, legal and procurement will finish. Guesses are usually too early. A seller-only forecast also gives the buyer no reason to commit to dates.
A MAP does three things:
- It makes the review process visible, so a missing step (such as vendor onboarding) shows up before it blocks signature.
- It ties each step to a person, so a delay has a name attached and someone to ask.
- It gives your champion, the buyer-side person who wants the deal to happen, a document to take to colleagues when they need to ask for priority.
A MAP does not guarantee the buyer's teams will meet the dates. Security and legal teams have their own queues. The MAP lets you see slippage early and respond to it.
Anatomy of a good MAP
Each step should have these fields:
| Field | Purpose | Example |
|---|---|---|
| Name | What must happen, phrased as a finished state | Security review complete |
| Owner | The one person or role responsible for the step | buyer_infosec |
| Buyer contact | Who on the other side the owner works with, if different | buyer_legal |
| Due date | A calendar date, not "next week" | 2026-12-07 |
| Dependency | What must finish first | Questionnaire submitted |
Two rules keep the plan honest. First, one owner per step. A step owned by "both" is acceptable only for the final approvals gate, where it really is a joint check. Everywhere else, shared ownership means no ownership. Second, write steps as outcomes ("Buyer redlines returned") rather than activities ("Discuss contract"), because you can tell whether an outcome happened.
A worked example
The following plan is for an annual subscription with a target signature date of 18 December 2026. It is written in YAML so it is easy to copy into a shared document or a CRM field.
deal: Acme Corp annual subscription
target_signature: 2026-12-18
steps:
- name: Security questionnaire submitted
owner: seller_solutions_engineer
buyer_contact: buyer_infosec
due: 2026-12-02
- name: Security review complete
owner: buyer_infosec
due: 2026-12-07
- name: First contract draft sent
owner: seller_sales
buyer_contact: buyer_legal
due: 2026-12-03
- name: Buyer redlines returned
owner: buyer_legal
due: 2026-12-10
- name: Vendor onboarding forms complete
owner: seller_finance
buyer_contact: buyer_procurement
due: 2026-12-11
- name: Final approvals
owner: both
due: 2026-12-16
- name: Signature
owner: economic_buyer
due: 2026-12-18Read the plan for what it shows:
- Security and contract work run in parallel. The questionnaire goes out on 2 December and the first draft on 3 December, so neither waits for the other.
- Seller-owned steps (questionnaire, first draft, onboarding forms) come early. The seller controls those dates, so they should be the first to be met.
- The buyer-owned steps (security review, redlines) have dates the buyer's own teams must confirm. A date the buyer never agreed to is a seller wish, not a commitment.
- The final approvals step has two business days before signature. That gap is buffer for a last question.
Working backward from the signature date
Build the plan from the end. The buyer usually has a reason for the target date, such as a budget cycle, the end of a quarter, a contract expiring, or a project start. Ask for that reason and write it down. A date with a real reason is easier to defend when a buyer team is slow.
Then work backward:
- Place the signature date.
- Subtract the time for final approvals. Ask who must approve and whether they meet on a schedule.
- Subtract the time for the longest chain of steps. Redlines often take several rounds, so allow for more than one exchange.
- Place steps that can run in parallel (security, legal, onboarding paperwork) at the same start point.
- Check whether the start date has already passed. If so, the target date is not realistic, and it is better to say so now.
Use the review durations the buyer told you in discovery. If the buyer said legal takes two weeks per round, do not plan for three days.
Getting the buyer to agree
A MAP only works if the buyer accepts it. A few practices help:
- Draft it first, then review it together. A blank page is harder for the buyer than a draft they can correct. Send your draft before the meeting and ask them to fix what is wrong.
- Ask each owner to confirm their own date. Have the champion confirm the plan as a whole, but also ask the infosec contact about the security date. A date that comes only from the champion may not reflect the security team's queue.
- Put it where the buyer already works. Use a shared document or spreadsheet, not an attachment that becomes stale on one side.
- Name an editor on each side. Without a named person per side, updates stop within a week.
If the buyer will not agree to dates at all, treat that as information about deal risk. It may mean the champion lacks authority over the review, or that the deal is not a priority for the buyer's teams.
Running the plan after it is agreed
A plan that nobody reviews decays. Set a short recurring check, weekly for most deals and twice a week in the last two weeks. At each check:
- Mark each step done, on track, at risk or late.
- For any late step, ask what is blocking it and who can unblock it.
- Move the dates of dependent steps and tell the buyer what moved.
- Check whether the signature date is still realistic.
Change the target date when the evidence says so. Keeping a date that the plan no longer supports weakens your forecast and the buyer's trust in the document.
A short script can flag steps that need attention. This one reads the plan above, saved as map.yaml, and lists steps that are overdue or due soon. It needs the PyYAML package.
import sys
from datetime import date, timedelta
import yaml
def flag_steps(path, today=None, window_days=3):
today = today or date.today()
with open(path) as f:
plan = yaml.safe_load(f)
soon = today + timedelta(days=window_days)
flags = []
for step in plan["steps"]:
due = step["due"]
if isinstance(due, str):
due = date.fromisoformat(due)
if due < today:
flags.append(("OVERDUE", step["name"], step["owner"], due))
elif due <= soon:
flags.append(("DUE SOON", step["name"], step["owner"], due))
return flags
if __name__ == "__main__":
path = sys.argv[1] if len(sys.argv) > 1 else "map.yaml"
for status, name, owner, due in flag_steps(path):
print(f"{status}: {name} (owner: {owner}, due {due})")The script does not know whether a step is complete, so a finished step with a past date appears as overdue. In a real plan you would add a status field and skip steps marked done.
Common errors
- Dates with no buyer confirmation. The plan looks complete, but the buyer never saw it. Fix it by asking each buyer owner to confirm their line.
- Missing steps. The most common omissions are vendor onboarding, tax forms, insurance certificates and a second approver. Ask directly: "What else has to happen before someone can sign?"
- Sequential steps that could be parallel. Waiting for security to finish before sending the contract adds weeks. Start both at once when the buyer allows it.
- No buffer. A plan with zero slack before signature breaks on the first delay.
- Vague owners. "Legal" is a team, not a person. Name the individual reviewer when you can.
- A plan that only the seller updates. If the buyer never edits it, they are not using it.
Exercises
Exercise
In the example plan, "Final approvals" has the owner "both". Why is this acceptable there, and why should most other steps avoid it?
Show answer
Final approvals is a joint gate where people on both sides must sign off, so shared ownership describes the real situation. For ordinary steps, a joint owner means nobody is clearly responsible, so nobody can be asked about a delay. Each ordinary step should have one named owner.
Exercise
A buyer's champion gives you a signature date of 15 January and says legal "usually takes about two weeks" per round. Contracts typically need two rounds of redlines. The first draft can go out on 2 December. Is a redline-complete date of 20 December realistic? Explain.
Show answer
No. Two rounds at two weeks each is about four weeks, so starting 2 December the redlines would finish around 30 December at the earliest. Holidays make it later. A redline-complete date of 20 December ignores the buyer's own stated review time. Either plan around early January with the signature date at risk, or ask legal whether a faster process is possible and get that confirmed by the legal reviewer, not only the champion.
Exercise
The buyer's security team has not confirmed the 7 December date for "Security review complete". What do you do, and what does it tell you if nobody will confirm?
Show answer
Ask the champion to introduce you to the security contact, then ask that person directly for their queue time and what they need from you. Mark the step "at risk" until it is confirmed. If nobody will confirm a date, the champion may not control the security review, or the deal may not be a priority for that team. Treat it as deal risk in your forecast.