Sub topic 4
Value-adding and non-value-adding work
This chapter assumes you know the basic lean idea of delivering what the customer wants with less effort, and that you have worked in or managed a process. The previous chapters covered why you go to the gemba and why respect for people is the ground rule. Here you learn the first lens to use once you are standing there: sorting what you see into work that adds value and work that does not.
Why sort work at all
A gemba walk produces a lot of raw sightings: people walking, machines running, boxes waiting. Without a way to sort them, every sighting looks equally important or equally trivial. The value-added question gives you a first filter. It also changes what you notice. Most processes are busy, so activity tells you little. Value tells you much more.
The sorting is about the work, not the worker. A person can be working hard on a step that adds no value, and the cause is almost always the process design. Keep that in mind in every conversation on the floor.
The three categories
Lean practice sorts every step of a process into one of three categories.
| Category | Short name | Meaning | Typical example |
|---|---|---|---|
| Value-adding | VA | Changes the product or service in a way the customer would pay for | Assembling, cooking, coding a feature, giving a treatment |
| Necessary non-value-adding | NNVA | Adds no value for the customer, but is required now by law, safety, or the current process design | Safety checks, regulatory records, machine setup |
| Non-value-adding | NVA | Adds no value and is not required. Also called pure waste | Waiting, searching, rework, moving items back and forth |
A step is value-adding only if it passes all three tests:
- The customer cares about the step, or would pay for it if they saw it.
- The step changes the product or service. It transforms, shapes, or delivers it.
- The step is done right the first time. Rework is not value-adding, even if the original task was.
Note that NNVA is a label for today, not forever. A quality inspection exists because the process can make defects. If the process improves, the inspection may become unnecessary. Treat NNVA steps as candidates to reduce, not as steps to defend.
A worked example
Suppose you follow one customer order through packing line 2 and time each step. You are only recording here. You are not judging anyone.
| Step | Minutes | Category |
|---|---|---|
| Order waits in queue before packing | 120 | NVA |
| Operator fetches box and tape from far shelf | 3 | NVA |
| Pack items into box | 4 | VA |
| Wait for labels to arrive | 4 | NVA |
| Apply label | 1 | VA |
| Check weight against the order | 2 | NNVA |
| Seal box | 1 | VA |
| Box waits for carrier pickup | 60 | NVA |
The total elapsed time, called the lead time, is 195 minutes. Only 6 of those minutes add value. The ratio of value-adding time to lead time is the process cycle efficiency (PCE). Here it is 6 / 195, about 3.1%.
A PCE this low does not mean the packers are slow. It is typical for processes that were never examined for flow, and it shows that the big opportunities are in the waiting between steps. The packers' own work is a small part of the 195 minutes.
You can compute the same figures from a walk sheet:
steps = [
("Order waits in queue", "nva", 120),
("Fetch box and tape", "nva", 3),
("Pack items", "va", 4),
("Wait for labels", "nva", 4),
("Apply label", "va", 1),
("Check weight", "nnva", 2),
("Seal box", "va", 1),
("Wait for pickup", "nva", 60),
]
totals = {"va": 0, "nnva": 0, "nva": 0}
for _name, category, minutes in steps:
totals[category] += minutes
lead_time = sum(totals.values())
for category in ("va", "nnva", "nva"):
print(f"{category}: {totals[category]} min")
print(f"Process cycle efficiency: {totals['va'] / lead_time:.1%}")Running it prints:
va: 6 min
nnva: 2 min
nva: 187 min
Process cycle efficiency: 3.1%Using the lens on the walk
When you stand at the gemba, apply the classification in this order.
- Name the customer of the step. For a step in the middle of a process, the customer may be the next station. Ask who receives the output of the step.
- Watch one unit of work, not the whole area. Following a single order, patient, or ticket exposes the waiting between steps, which a view of busy stations hides.
- Note time as well as category. A stopwatch or a clock reading on the walk sheet turns "a lot of waiting" into "4 minutes, twice an hour".
- Record what you saw, then classify afterwards. Classifying aloud in front of the operator ("that's waste") sounds like a verdict on their work.
Chapter 5 returns to the eight wastes, which give names to the NVA category. For now you only need to decide whether a step is VA, NNVA, or NVA.
Edge cases and gray areas
Classification is a judgment, and reasonable people disagree on the edges. These are the cases that come up most often.
- Inspection. Inspection does not change the product, so it is not VA. It is usually NNVA while defects are possible. Inspecting the same item three times is NVA.
- Setup and changeover. Changing a machine to a new product adds no value for the customer. It is NNVA until the process is changed to shorten it.
- Transport. Moving a part to the next station is NNVA at best. In a service such as delivery, though, transport is the product and counts as VA.
- Service and knowledge work. Value is harder to see. In software delivery, writing code that a user will use is VA. Waiting for a review, re-explaining a requirement, or fixing a defect found after release are not. In healthcare, the treatment is VA while the patient's wait in a corridor is NVA.
- Rework. The first attempt at a step may have been value-adding, but redoing it is not. Count the redo as NVA.
- Batch waiting. Items that sit while the rest of the batch is finished are waiting, even though the people around them are busy.
If you cannot decide, write the step down with a question mark and ask the operator what the customer receives from it. Their answer often settles the point.
Common errors
- Treating NNVA as untouchable. Required steps can still be made faster, simpler, or occasionally removed if the reason for them disappears.
- Treating NVA as someone's fault. Waste is a property of the process. Naming a person damages the trust that gives you honest observations.
- Cutting NNVA first. Removing a safety or regulatory step to raise PCE is a serious mistake. Reduce waiting and motion first, and change required steps only through the proper review.
- Judging from one observation. One slow order may be unusual. Repeat the observation across several units and shifts before drawing a conclusion.
- Confusing busy with valuable. A full workbench of work in progress is often a sign of waiting, not progress.
Exercises
Exercise
On a walk through a clinic you time one patient: 25 minutes in the waiting room, 3 minutes of registration questions required by law, 10 minutes with the doctor, 5 minutes waiting for a test result, 2 minutes of the doctor explaining the result. Treat the doctor's consultation and the explanation as value-adding. Treat the registration as necessary non-value-adding. Calculate the process cycle efficiency.
Show answer
Lead time is 25 + 3 + 10 + 5 + 2 = 45 minutes. Value-adding time is 10 + 2 = 12 minutes. PCE = 12 / 45 = about 26.7%. Waiting is 30 minutes and registration is 3 minutes.
Exercise
An operator assembles a part correctly in 6 minutes. Later the part fails a check and the operator spends 6 more minutes redoing the assembly. How should the 12 minutes be classified, and why?
Show answer
The first 6 minutes are not value-adding in the strict sense, because the step was not done right the first time and the customer would not accept the result. The usual practice is to count the redo of 6 minutes as non-value-adding, and to treat the original attempt as value-adding only if it produced a good part. In this case the part failed, so most practitioners count both attempts as effort spent on one good result and focus on the cause of the defect.