Sub topic 3
Planning an SAP ECC to S/4HANA Roadmap
Assume you understand FI, CO, MM, SD, databases, and custom ABAP. This chapter focuses on planning rather than transaction-level differences.
Planning around the deadlines
For the commonly used SAP ERP 6.0 enhancement package 6–8 line, SAP lists mainstream maintenance through December 31, 2027. Optional extended maintenance runs through December 31, 2030, subject to SAP’s conditions and fees. Confirm the dates for your exact release in the SAP Support Portal, because maintenance depends on the product and enhancement package.
Treat the deadline as a planning constraint, not as the project start date. Include time for assessment, procurement, remediation, testing, training, and cutover.
Three ways to get to S/4HANA
- New implementation: Build a new system and migrate selected master and transactional data. This supports process redesign but requires substantial data and organizational work.
- System conversion: Convert an existing ECC system in place. This preserves more configuration and history, but custom code and incompatible processes need remediation.
- Selective data transition: Combine redesign with selected historical data and configuration. It offers balance, but its scope and tooling require careful definition.
| Approach | Main strength | Main planning risk |
|---|---|---|
| New implementation | Clean process design | Data migration and adoption |
| System conversion | Preserves existing investment | Technical debt |
| Selective transition | Controlled redesign | Complex scope decisions |
Assessing readiness with SAP tools
Use the Simplification Item Catalog to identify changed functions and required adaptations. Run SAP Readiness Check to analyze business, data, and technical impacts. Use Maintenance Planner to validate the target product version, add-ons, and conversion path.
Custom code: finding and fixing what breaks
Inventory custom ABAP, interfaces, reports, and modifications. Use ABAP Test Cockpit and the Custom Code Migration tools to find obsolete tables, transactions, and APIs. Prioritize code that touches simplified data structures, such as finance totals or material documents. Replace direct table access with released APIs where possible, then test the business result.
Choosing an approach and building a roadmap
Choose conversion when current processes and data must remain largely intact. Choose a new implementation when process redesign is the main goal. Choose selective transition when both controlled redesign and selected history matter.
Set milestones for assessment, target release selection, remediation, testing, training, and cutover. Assign owners and make the ECC maintenance date a fixed governance checkpoint.
Exercise
Which SAP tool helps validate the target product version, add-ons, and conversion path?
Show answer
Maintenance Planner.