Writing and Prioritizing Delta Requirements
Assume basic familiarity with SAP S/4HANA, ERP projects, and business processes such as order-to-cash and procure-to-pay. A delta requirement records where the standard process does not meet a confirmed business need.
Writing and prioritizing delta requirements
Write each delta as a testable requirement, not as a preferred solution. Include:
- The process and step affected.
- The business reason and evidence.
- The required behavior.
- Priority, owner, and status.
- A proposed approach that respects the clean core principle.
{
"id": "F2S-SD-007",
"processStep": "Create sales order",
"finding": "A customer-specific document layout is required",
"businessJustification": "Contractual requirement",
"proposedApproach": "Review in-app and key-user extensibility first",
"priority": "must-have",
"status": "to be estimated"
}Prioritize by legal or contractual need, operational value, risk, and implementation effort. Do not label every request as a must-have.
Capturing configuration decisions
Record configuration separately from delta requirements. Capture the selected value, the process it affects, the decision owner, dependencies, and the reason for the choice. Link the decision to the relevant scope item and workshop finding. This prevents a temporary workshop assumption from becoming an unnoticed design decision.
Supporting tools for content and tracking
Use SAP Best Practices and Process Navigator to identify scope items and process flows. Use the starter system to demonstrate the delivered process. Track findings, decisions, owners, and statuses in a controlled tool such as SAP Cloud ALM.
From workshop findings to the backlog
Move each accepted finding through a defined path:
Solution scope and change control
Compare each proposed delta with the agreed solution scope. If it adds a process, country, role, or integration, raise a scope change before estimating it. Record the impact on cost, schedule, testing, data, and support. An approved backlog item is not automatically approved scope.
Outputs, review, and sign-off
The workshop package should include classified findings, configuration decisions, delta requirements, open questions, and traceability to scope items. Process owners and the solution lead should review it. Obtain sign-off from the authorized business representatives before using the results as the Realize-phase baseline.
Common pitfalls and how to avoid them
- Recording solutions instead of business requirements: document the need first.
- Treating configuration as customization: verify the standard option.
- Losing traceability: give every finding a unique identifier.
- Accepting unestimated requests: require impact analysis.
- Skipping sign-off: define who approves the workshop baseline.
Exercise
A user requests a custom approval screen because the standard screen appears unfamiliar. What should you record first?
Show answer
Record the business need and test the standard approval process. Classify it as fit or configuration unless a confirmed requirement remains.