Checking a SIPOC Diagram Against the Real Process
Assume you already know the five SIPOC columns: Suppliers, Inputs, Process, Outputs and Customers. This chapter focuses on validation, which means checking whether the diagram matches what people and systems actually do.
A SIPOC is useful only when it describes the real process at a high level. A team can easily create a neat diagram that reflects a written procedure, an outdated assumption or one person’s experience instead. Validation finds these gaps before the SIPOC guides later Lean Six Sigma work.
What to validate
Check each column and the connections between columns.
- The process starts and ends at the agreed boundaries.
- The process steps occur in the correct order.
- Each step is broad enough for a SIPOC, but specific enough to describe the work.
- Every important output has a customer.
- Every important input has a supplier.
- Inputs support at least one process step.
- Outputs are produced by at least one process step.
- Customer requirements describe what makes an output acceptable.
- The diagram includes normal work, not unusual exceptions that would require a separate analysis.
Validation is not a search for every task, decision or system field. A detailed process map belongs later. The goal is to confirm that the high-level view is complete and credible.
Validate from both directions
A useful review starts with the process and then checks the relationships around it.
Review the process flow
Ask people who perform the work to walk through the steps in order. Use questions such as:
- What triggers the first step?
- What event shows that the process is complete?
- Does this step always happen?
- What happens when information or material is missing?
- Is a step performed by another team or system?
- Are any steps shown in the wrong order?
For example, an order-fulfilment team might reveal that payment approval happens before stock is checked. If the SIPOC places those steps in the opposite order, correct the diagram or investigate whether different order types follow different paths.
Trace inputs and outputs
For every input, ask which supplier provides it and which process step uses it. For every output, ask which step creates it and who receives it.
| Validation question | Example finding | Possible correction |
|---|---|---|
| Who supplies the delivery address? | The customer supplies it, but the CRM also verifies it. | Show the customer as the source and the CRM as a supporting supplier only if it provides a separate input. |
| Which step creates the shipping notice? | The carrier sends the notice after pickup. | Add the carrier response to the output or clarify the process boundary. |
| What does the customer require? | The parcel must arrive by the promised date. | Add “on-time delivery” as a requirement for the shipment output. |
A customer can also be an internal team. For example, a shipping team may receive a packed parcel, while the external customer receives the final order.
Use evidence, not consensus alone
During a workshop, record disagreements instead of resolving them by majority vote. Check the real process with evidence such as:
- A sample of recent orders
- System timestamps and status histories
- Work instructions
- Forms, emails or handoff records
- Interviews with different roles
- Direct observation of the work
Compare several recent cases. One case may be unusual. If the cases follow different paths, decide whether the SIPOC should show the common path, include a broad step for the variation or be split into separate process scopes.
| Suppliers | Inputs | Process | Outputs | Customers |
|---|---|---|---|---|
| Customer | Order and delivery address | Receive and review order | Confirmed order | Customer |
| Inventory system | Stock status | Check stock | Stock decision | Warehouse team |
| Warehouse team | Items and packing materials | Pick and pack order | Packed parcel | Carrier |
| Carrier | Shipping label | Ship order | Delivery notice | Customer |Validate the boundary and ownership
Show the draft to people at the start and end of the process. Ask the starting role what it receives and the ending customer what it expects. Boundary disputes often reveal hidden handoffs.
For example, “ship order” might end when a parcel leaves the warehouse, when the carrier accepts it or when the customer receives it. Each choice produces a different SIPOC. State the chosen endpoint clearly in the project charter.
A short validation workshop
Use this sequence:
- Display the draft SIPOC and state the start and end points.
- Ask a process performer to narrate a recent normal case.
- Mark missing, misplaced or disputed items.
- Compare the discussion with records or direct observation.
- Update the SIPOC and record unresolved questions.
- Confirm the revised version with the affected teams.
After validation, keep a version date and identify the people who reviewed it. This makes later changes traceable.
Using the validated SIPOC
A validated SIPOC can support a project charter by defining the project scope and affected customers. It can guide a detailed process map by showing which high-level steps need further breakdown. It can also support a voice-of-the-customer study by identifying which customers to interview and which outputs to examine.
Exercise
A SIPOC says that the process ends when the warehouse prints a shipping label, but customers judge success by receiving the parcel. What should the team do?
Show answer
Discuss the project purpose and choose an explicit endpoint. If customer delivery is in scope, extend the process boundary to include shipment and delivery. If the project ends at label creation, document that boundary and treat delivery as a later process.