Start with a work breakdown structure
A work breakdown structure (WBS) is a tree that splits a project into smaller pieces of work. A Gantt chart schedules tasks, so you need a WBS to produce the list of tasks first.
Prerequisites
This chapter assumes you know basic project terms such as task, deadline, and deliverable. You should also be comfortable reading dates on a calendar.
Decompose the deliverable
Put the final deliverable at the top of the tree. Split it into major parts, then split each part again. Stop when each leaf is a task one person can finish and estimate.
Estimate task durations
Give each leaf task a duration in working days. Round up to whole days, and state the unit in your plan.
| Task | Duration (working days) |
|---|---|
| Wireframes | 5 |
| Mockups | 7 |
| Frontend | 10 |
Link tasks with dependencies
A dependency says one task must finish before another can start. This is a finish-to-start link. Each task starts when its latest predecessor finishes. The following script computes the earliest finish day for each task from day 0:
tasks = {
"Wireframes": (5, []),
"Mockups": (7, ["Wireframes"]),
"Frontend": (10, ["Mockups"]),
}
finish = {}
for name, (duration, preds) in tasks.items():
start = max((finish[p] for p in preds), default=0)
finish[name] = start + duration
print(finish) # {'Wireframes': 5, 'Mockups': 12, 'Frontend': 22}Mark milestones
A milestone is a point in time that marks an event, such as an approval or a launch. It has no work of its own. Add a milestone after the task that produces the event, such as "Design approved" after Mockups.
> The note below is a callout, not a quote.
Exercise
The Backend task takes 8 days and depends on Wireframes, which takes 5 days. Starting from day 0 with no other dependencies, on which day does Backend finish?
Show answer
Day 13. Wireframes finishes on day 5, so Backend starts on day 5 and finishes 8 days later, on day 13.