This chapter assumes you know what divergent and convergent thinking are, and that you have used techniques from each, such as brainstorming and dot voting. It covers how to order those two modes across a whole project. It does not cover the pitfalls that can derail the sequence, group facilitation, or a full worked project. Later chapters handle those.
One diamond: widen, then narrow
The diamond model is a picture of a single idea. Draw a diamond lying on its side. The left point is a starting question. The shape widens as you generate options, reaches its widest point, and narrows as you choose among them. The right point is a decision.
- The left half is divergent thinking. You add possibilities, and you defer judgment.
- The widest point is the moment you stop adding and start evaluating.
- The right half is convergent thinking. You apply criteria and remove possibilities.
- The right point is one choice, or a short list you are ready to test.
The width of the diamond stands for the number of live options at that moment. Seen this way, a project is a pattern of option counts: few, many, few. The shape also makes clear that the narrowing is deliberate. A discussion that never reaches the right point has not finished the diamond.
The Double Diamond
The best-known version is the Double Diamond. The British Design Council published it in 2004, after studying how design teams at several companies worked. It puts two diamonds side by side. They share a middle point, and each one asks a different kind of question.
- The first diamond works in the problem space. It asks "What is the real problem?"
- The second diamond works in the solution space. It asks "What is the right way to solve that problem?"
Each diamond has a diverge half and a converge half, which gives four phases named Discover, Define, Develop and Deliver.
What each phase does
| Phase | Mode | Question | Typical activities | Output |
|---|---|---|---|---|
| Discover | Diverge | What is going on here? | Interviews, observation, data review, "how might we" restatements | A wide set of observations and candidate problems |
| Define | Converge | Which problem matters most? | Clustering, ranking by evidence and impact, framing | A problem statement or design brief |
| Develop | Diverge | What could we do about it? | Brainstorming, brainwriting, SCAMPER, sketching, prototypes | A wide set of candidate solutions |
| Deliver | Converge | Which solution works, and does it hold up? | Weighted matrix, testing, pilots, refinement | One solution ready to release |
The phase names matter less than the alternation. Your team may call the phases "explore, frame, ideate, select". The structure is the same.
Why two diamonds
Many teams run only the second diamond. They receive a problem statement, such as "We need a mobile app for booking," and start generating solutions. The first diamond is the one that checks whether that statement is right.
Diverging on the problem means asking why the problem exists, who has it, and what other framings fit the same facts. A support team told to "reduce ticket volume" might find that most tickets come from one confusing billing email. The first diamond turns the task from "deflect tickets" into "fix the email." That is a different second diamond with different options.
Skipping the first diamond is called solution jumping. A very good solution to the wrong problem still fails, and it costs more the later you find out.
Different criteria in each converge step
The two converge steps are not the same activity. They use different criteria because they choose different things.
- The first converge (Define) chooses a problem. Useful criteria are evidence (how sure are we this happens?), size (how many people, how often?), and fit with the team's scope and goals.
- The second converge (Deliver) chooses a solution. A common set of criteria is desirability (do people want it?), feasibility (can we build it?), and viability (does it pay for itself?).
Reusing solution criteria on problems tends to favor problems that are easy to fix, not important ones. Reusing problem criteria on solutions tends to favor options that address the most evidence, not the ones that are practical.
Planning the phases as a budget
A diamond is also a time plan. Each half needs a time allowance, and the convergent halves are the ones most often cut. This small script divides a project's working days across the four phases using weights you choose.
phases = [
("Discover", "diverge", "problem", 0.30),
("Define", "converge", "problem", 0.15),
("Develop", "diverge", "solution", 0.30),
("Deliver", "converge", "solution", 0.25),
]
def plan(total_days):
total_weight = sum(weight for *_, weight in phases)
if abs(total_weight - 1.0) > 1e-9:
raise ValueError("phase weights must sum to 1.0")
schedule = []
start = 0.0
for name, mode, space, weight in phases:
length = total_days * weight
schedule.append((name, mode, space, start, start + length))
start += length
return schedule
for name, mode, space, begin, end in plan(20):
print(f"{name:<9} {mode:<9} {space:<9} day {begin:4.1f} to {end:4.1f}")For 20 days it prints Discover from day 0.0 to 6.0, Define to 9.0, Develop to 15.0, and Deliver to 20.0. The weights are a starting point, not a rule. A well-understood problem can shrink Discover. A risky solution can grow Deliver, because testing belongs in that phase.
The check that weights sum to 1.0 guards against a common planning error. If you widen one phase without trimming another, the plan quietly overruns.
Diamonds inside diamonds
The Double Diamond is the top-level view. Real work contains smaller diamonds.
- During Discover, a team may diverge on interview questions, then converge on five. That is a small diamond inside a larger diverge phase.
- During Develop, a team may diverge on ten concepts, converge on three, then diverge again on variations of those three before the Deliver phase.
- A single one-hour workshop is a diamond in its own right: twenty minutes of generating, ten of clustering, ten of voting, and the rest of agreeing on next steps.
A useful habit is to name the mode before each activity: "For the next fifteen minutes we are diverging." Doing this keeps people from critiquing ideas during a generating phase, and from adding new ideas during a choosing phase. Both of those cause the stalls described in the pitfalls chapter.
The model is not a straight line
The diagram looks like a pipeline, but real projects loop. Three loops are common.
- Back to Define. A prototype test shows that users do not care about the problem as framed. You return to the first converge step with new evidence and reframe. This is the dashed arrow in the diagram.
- Back to Discover. The facts are too thin to define a problem. You collect more before you converge.
- Another pass of Develop. None of the candidate solutions meets the criteria. You diverge again, with the criteria now clearer than they were the first time.
Going back is not failure. It is the model working as designed, because each pass uses what the previous one revealed. What the model warns against is going back without a reason, such as reopening a decision because someone dislikes it. A good rule is that you reopen a converge step only when you have new evidence or you find that a criterion was wrong.
The Design Council later extended the original model with a broader framework that adds principles such as working in the open and engaging people, but the two-diamond core is unchanged.
When one diamond is enough
Not every problem needs both diamonds. Use this table to decide.
| Situation | Suggested shape |
|---|---|
| The problem is clear, agreed, and measurable (for example, "page load time must drop below two seconds") | Second diamond only |
| The symptoms are clear but the cause is not | Full Double Diamond, with extra time in Discover |
| The decision is small and reversible | A single short diamond, perhaps ten minutes |
| The team already has a well-tested solution | Skip diverging, and spend the time on converging and delivery |
The cost of skipping the first diamond is the risk of solving the wrong problem. The cost of running it when it is not needed is time. Weigh them against how hard the work would be to undo.
Practical checklist
Before starting a project with this model, answer these questions in writing.
- What is the starting question, and is it a problem or a solution in disguise?
- What will the output of each converge step look like (a one-sentence problem statement, a ranked shortlist, a tested prototype)?
- What criteria will you use at each converge step, and who agreed them?
- How much time does each half get, and who will stop the diverge half when time is up?
- What new evidence would justify going back a step?
If you cannot answer question 2, the team cannot tell when a diamond is complete. That is the most common reason diamonds stay open.
Exercise
A team is told "build a better onboarding tutorial." They immediately brainstorm tutorial formats for an hour, vote, and start building. Using the Double Diamond, name which diamond they skipped, give one concrete first-diamond activity they could run, and explain what kind of criteria they should use when converging in that diamond.
Show answer
They skipped the first diamond (Discover and Define), so they never checked whether a tutorial is the right answer to an onboarding problem. A first-diamond activity could be interviewing recent new users and reviewing where they stopped using the product, then listing the possible problems (unclear first step, missing data, confusing terms). To converge in Define they should use problem criteria such as strength of evidence, how many users are affected, and fit with the team's scope, not solution criteria such as ease of building. The output should be a problem statement, which then starts the second diamond.
Exercise
A project has 30 working days. The team wants Discover 20%, Define 20%, Develop 30% and Deliver 30%. How many days does each phase get, and which two phases form the problem space?
Show answer
Discover gets 6 days, Define 6 days, Develop 9 days and Deliver 9 days, which sums to 30. Discover and Define form the problem space (the first diamond). Develop and Deliver form the solution space (the second diamond).