Sub topic 13
Planning Minimums, Lead Times, and the Timeline
Assume you already have a customer brief, edited collection, technical flats, preliminary costs, and a sampling plan. This chapter focuses on turning those decisions into a realistic small-run production schedule.
Understand production minimums
A production minimum is the smallest quantity a supplier will accept for an order. The minimum may apply at different levels:
- A factory minimum may apply to each style, color, or size range.
- A fabric supplier minimum may apply to the total meters ordered.
- A trim supplier minimum may apply to buttons, labels, zippers, or elastic.
- A dye house minimum may apply to one color batch.
For example, a factory may accept a minimum of 30 units per style, while a fabric supplier requires 50 meters per color. Ordering 30 units of a jacket may therefore be possible, but ordering a small amount of a custom-dyed fabric may not be economical.
Ask each supplier for these details before confirming the range:
- Minimum quantity per style and color
- Size breakdown requirements
- Sample and production lead times
- Material ordering deadlines
- Payment terms
- Capacity during your intended production window
- Reorder conditions
Do not calculate minimums only by adding garment quantities. Check whether the required fabric and trims also meet their supplier minimums.
Build the critical path
A lead time is the time between starting a production task and completing it. The critical path is the sequence of tasks that controls the final delivery date. A delay on this path delays the entire collection.
Typical critical-path tasks include:
- Approving the final design and technical flat
- Confirming fabric and trims
- Making the first sample
- Fitting and revising the pattern
- Approving the pre-production sample
- Ordering or reserving production materials
- Cutting and sewing
- Quality checking and packing
Some tasks can happen in parallel. For example, labels can be ordered while the pattern is being revised. Production fabric should not be cut until the fit, measurements, and material quantities are approved.
Create a working timeline
Use weeks rather than exact dates at the beginning. Add dates after the supplier confirms capacity. A small collection might follow this structure:
| Phase | Main work | Typical duration |
|---|---|---|
| Preparation | Confirm styles, quantities, materials, and supplier | 1 week |
| Sampling | Make first sample and revise the pattern | 2–3 weeks |
| Fit approval | Fit on the intended size range and approve measurements | 1 week |
| Material ordering | Secure production fabric, trims, labels, and packaging | 2–4 weeks |
| Production | Cut, sew, press, and finish units | 2–4 weeks |
| Quality and delivery | Inspect, correct, pack, and transport | 1–2 weeks |
These periods can overlap, but do not remove approval points. Each approval should have one responsible person, a deadline, and a recorded decision.
Add a buffer of at least 10–20 percent to supplier estimates. The buffer covers late materials, failed samples, machine problems, public holidays, and transport delays. A ten-week plan should therefore reserve roughly one additional week before promising a delivery date.
Track decisions and dependencies
Use one production tracker for every style. Record the style code, fabric, color, size range, planned quantity, sample status, approval date, material status, and production status. Mark blocked tasks clearly. A factory cannot begin cutting if the fabric is late, even when the pattern is approved.
For a six-style collection, confirm whether the minimum is six separate style minimums or one combined order minimum. A lower total quantity may be possible when several styles share the same fabric and production team, but only the supplier can confirm this.
Exercise
A factory requires 30 units per style and your collection has four styles. You want 20 units of each style. What should you ask before changing the order?
Show answer
Ask whether the factory can combine quantities across styles, whether the minimum changes by fabric or color, and whether a smaller order carries a surcharge. Then compare the surcharge with the cost of producing extra units.