Sub topic 5
Writing Acceptance Criteria
This chapter assumes you understand basic project roles and have already identified the project’s objectives, stakeholders, and proposed deliverables. We will use a customer portal refresh as a running example.
Acceptance criteria are the conditions a deliverable must meet before the person authorized to accept it approves it. They turn a general promise into something that can be checked. Without them, “finished” often means different things to the project team, customer, and sponsor.
From deliverables to verifiable conditions
A deliverable is an outcome produced by the project. For example, “self-service password reset” is a deliverable. It describes what the project will provide, but it does not yet explain how anyone will decide whether the result is acceptable.
Acceptance criteria answer questions such as:
- What must the user be able to do?
- What result must the system produce?
- What limits or rules apply?
- What evidence will show that the condition is met?
- Who has authority to accept the result?
Each criterion should describe an observable result. Avoid criteria that depend only on effort or intent, such as “the team will work carefully” or “the page will be user-friendly.” Those statements are difficult to test consistently.
A useful distinction is:
| Statement | Type | Problem or value |
|---|---|---|
| Build a password reset feature | Deliverable | Names the outcome but not the required behavior |
| A user can reset a password using a link sent to the registered email | Acceptance criterion | Describes a result that can be demonstrated |
| The team will spend two weeks on testing | Activity or estimate | Does not prove that the deliverable works |
Characteristics of good criteria
Good acceptance criteria are specific, testable, and connected to the deliverable. They should be understandable to both technical and nontechnical stakeholders.
Use these properties:
- Observable: Someone can see, use, inspect, or measure the result.
- Unambiguous: Different readers reach the same interpretation.
- Complete: The important behavior and boundaries are included.
- Independent: Each criterion checks a meaningful condition without hiding several unrelated requirements.
- Traceable: The criterion can be linked to a requirement, objective, or deliverable.
- Agreed: The relevant stakeholder understands and accepts the condition before work is complete.
Avoid vague words such as “fast,” “simple,” “modern,” “secure,” and “easy” unless you define how they will be measured. For example, replace “the page loads quickly” with “the account settings page displays its main content within two seconds for 95% of monitored requests under the agreed test load.”
Writing criteria step by step
Start with the deliverable and its intended user or stakeholder. Then describe the required result and add measurable boundaries.
For the password reset deliverable, a concise set of criteria might be:
deliverable:
id: D1
name: Self-service password reset
acceptance_criteria:
- A user can request a reset link by entering a registered email address
- The reset link is sent to the registered email address
- The link expires 24 hours after it is issued
- A user can set a new password through an unexpired link
- The system rejects an expired or already-used link
- The new password works on the next sign-inThese criteria describe behavior rather than implementation. They do not require a particular programming language, database, or email provider. That separation gives the delivery team room to choose an implementation while preserving the outcome the stakeholder needs.
For criteria involving quality attributes, add a threshold and a measurement method:
quality_criteria:
- The reset request response completes within 2 seconds for 95% of requests under the agreed test load
- Reset links cannot be used more than once
- The system does not reveal whether an email address is registeredThe last criterion addresses privacy by defining the externally visible behavior. It does not prescribe the internal security design.
Mapping a criterion to a verification method
Decide how each criterion will be checked. A demonstration may be enough for a user workflow, while a test report or inspection may be needed for performance or security.
Common verification methods include:
- Demonstration: A stakeholder observes the feature being used.
- Test: A defined set of inputs produces the expected results.
- Inspection: A reviewer checks a document, configuration, or physical result.
- Analysis: Measurements or calculations show that a threshold is met.
Record the evidence expected for each criterion. Evidence might be a test result, screenshot, signed review record, report, or demonstration note. This prevents a later disagreement about what “verified” meant.
Common errors and corrections
A frequent error is combining too many conditions in one sentence. “The page lets users change their details, works on mobile, saves instantly, and is secure” contains several different criteria. Split it into separate statements so each condition can be tested and discussed.
Another error is adding implementation instructions as acceptance criteria. “Use a specific vendor’s identity library” may be a technical requirement, but it does not describe whether the deliverable meets the user’s need. Keep implementation constraints in the appropriate project records unless the technology itself is part of the agreed requirement.
Criteria can also be too narrow. If they cover only the successful path, they may ignore expired links, invalid data, permissions, or duplicate submissions. Ask what should happen when the user makes an error or when an external dependency is unavailable.
Review and baseline the criteria
Review criteria with the person who will accept the deliverable and with the team responsible for producing it. The stakeholder confirms that the criteria represent the intended outcome. The team confirms that the criteria are understandable and verifiable.
Once agreed, baseline the criteria in the scope statement, requirements record, or deliverable register. Changes should use the project’s change control process. A request to add multi-factor authentication, for example, may affect schedule, cost, testing, and other deliverables. It should not quietly become part of the original acceptance test.
Exercise
A stakeholder says, “The account settings page must be easy to use.” Rewrite this as one acceptance criterion that can be verified.
Show answer
Example: “In a usability test with five representative users, at least four users can change their notification preferences and save the change without assistance.”